SPOKANE COUNTY PUBLIC WORKS ROAD CONSTRUCTION AND MAINTENANCE
JUNE 4-11, 2021
http://www.spokanecounty.org/3828/Weekly-Travel-Impacts-Map
ROAD CONSTRUCTION
Bigelow Gulch Phase 3
Road Reconstruction (remove and replace), culverts, stormwater, guardrail and illumination system. Completed: August 31, 2021.
Weile Av: CLOSED from Bigelow Gulch Rd to Thierman Rd – through July 31,
2021. Detour through Jensen Road.
Bigelow Gulch Road: from Weile Avenue to Weile Avenue
Lane restrictions (both directions, all lanes): Only allowing access from Bigelow Gulch and Weile to the Koi Farm and Bill Johnson’s Differential Shop – through August 31, 2021.
Additional Info - Bigelow Gulch Phase 3
Road Closure – Dates: May 24 – June 14, 2021.
Bigelow Gulch Road: from Weile Avenue to Argonne Road
Road CLOSED. Look for electronic traffic signs for updates on the closure.
Centennial Trail
Roadway excavation, embankment compaction, culvert pipe, crushed surfacing top course, hot mix asphalt, silt fence, wattles, seeding and mulching, temporary traffic control, erosion control. From Nine-Mile Dam to Carlson. Completed: June 15, 2021.
Chattaroy Road Rebuild from US 2 to Elk-Chattaroy Road
Crews will pulverize the existing pavement, pour the concrete, shaping and striping. The project is from US 2 to Elk-Chattaroy Road. Completed: June 30, 2021
Elk-Chattaroy Rd: from Chattaroy Rd to US-2 (Newport Hy)
Lane restrictions (both directions, all lanes): Flaggers may be present and/or a Pilot Car to direct traffic. Motorists should be prepared for long delays.
Geiger Blvd - Soda to Grove Rd *****ROAD CLOSED FROM THOMAS MALLEN TO GROVE*****LOCAL BUSINESSES ARE OPEN!
New road, including drywells, asphalt, signing, pavement marking. Dowdy and Geiger Road are Open. Completed: June 30, 2021.
Geiger Blvd: from Thomas Mallen Road to Spokane City Limits (Electric Ave)
Lane Restrictions (Both Directions, All Lanes): Geiger at Grove is closed. Crews will be working on removing existing roadway. Use Alternate Route. Electric Avenue is open. Thomas Mallon is open. Local businesses are open, please use extreme caution when travelling inside the work zone. Spotted is CLOSED.
PRIVATE CONTRACTOR WORK BY PERMIT
STA Four Lakes Station
WM Winkler crews are paving First Avenue. The project includes the sidewalks, curbs and gutters – along with demolishing part of Spokane Street. 150-feet of road will be reduced to a seven-foot wide walking path south of First Avenue. Completed: July 30, 2021.
First Avenue: from Electric Ave. to Cheney Street.
ROAD CLOSED on First Avenue on the east and west side of Highway 904 from 8:00 a.m. to 5:00 p.m. as needed.
ROAD MAINTENANCE
(Road maintenance projects are subject to change due to weather conditions and other road maintenance priorities)
Adding gravel to Scribner Rd from Forker Rd to Scribner Lane.
Crews are adding gravel to Scribner Rd from Forker Rd to Scribner Lane. Expect lane restrictions & flaggers. Dates: June 7-10, 2021.
Scribner Rd: from Forker Rd to Scribner Branch Rd
Lane restrictions (both directions, all lanes): Motorists should watch for flaggers.
Asphalt Overlay on Grove Rd from Cheney-Spokane Rd to Hallett Rd.
Asphalt Overlay on Grove Rd from Cheney-Spokane Rd to Hallett Rd. Expect lane restrictions, delays & flaggers. Dates: June 9-17, 2021.
Grove Rd: from Cheney-Spokane Rd to Hallett Rd
Motorists should expect delays (both directions, all lanes). Please slow down and watch for flaggers.
Asphalt Overlay on Melville Rd from Spotted Rd to Hwy. 904.
Asphalt Overlay on Melville Rd from Spotted Rd to Hwy. 904. Expect delays and flaggers. Completed: June 9, 2021.
Melville Rd: from Spotted Rd to SR-904
Motorists should expect delays (both directions, all lanes). Please slow down and watch for flaggers.
Chip Sealing on Martin Rd from Mullinix Rd to Lincoln County Line.
Crews are chip sealing on Martin Rd from Mullinix Rd to Lincoln County Line. Expect flaggers, delays & pilot vehicles through project. Dates: June 7-9, 2021.
Martin Rd: from Lincoln County Line to Mullinix Rd
Motorists should expect delays (both directions, all lanes). Please slow down, watch for flaggers and pilot cars guiding traffic through the project.
Chip Sealing on Mullinix Rd from Martin Rd to Cheney City Limits.
Chip Sealing on Mullinix Rd from Martin Rd to Cheney City Limits. Expect flaggers, delays & pilot vehicles through project. Dates: June 9-17, 2021.
Mullinix Rd: from Martin Rd to UPRR Crossing #31222 (Cheney City Limits)
Motorists should expect delays (both directions, all lanes). Please slow down, watch for flaggers and pilot cars guiding traffic through the project.
Crack Sealing on Sherman Rd from Montgomery Rd to Bridges Rd. Expect lane restrictions.
Crack Sealing on Sherman Rd from Montgomery Rd to Bridges Rd. Expect lane restrictions and flaggers. Dates: June 7-10, 2021.
Sherman Rd: from Montgomery Rd to Bridges Rd
Lane restrictions (both directions, all lanes). Please slow down and watch for flaggers.
Euclid Rd Bridge Closure
Euclid Rd Bridge is closed and a detour is in place. Replacing the bridge is the responsibility of the Burlington Northern Santa Fe Railroad.
Euclid Rd: from Bridge #1508 Over BNSF to Lyons Rd
Road Closed – Euclid Rd Bridge Closed
Re-graveling Bridges Road from Madison Road to Elk-Chattaroy Road.
Crews are re-graveling Bridges Road from Madison to Elk-Chattaroy Road. Completed: June 10, 2021.
Bridges Road: from Madison Road to Elk-Chattaroy Road.
Lane restrictions (both direction, all lanes) and expect flaggers: Motorists should slow down in the work zone.
Re-graveling Frideger Road from Darknell Road to Madison Road.
Crews are re-graveling Frideger Road from Darknell Road to Madison Road. Completed: June 10, 2021.
Frideger Road: from Darknell Road to Madison Road.
Lane restrictions (both direction, all lanes) and expect flaggers: Motorists should slow down in the work zone.
Re-graveling Madison Road from Frideger Road to Bridges Road.
Crews are re-graveling Madison Road from Frideger Road to Bridges Road. Completed: June 10, 2021.
Madison Road: from Frideger Road to Bridges Road.
Lane restrictions (both direction, all lanes) and expect flaggers: Motorists should slow down in the work zone.
Sweeping loose material from fresh Chip Seal on Martin Rd, from Mullinix Rd to Lincoln County Line.
Sweeping loose material from fresh Chip Seal on Martin Rd, from Mullinix Rd to the Lincoln County Line. Expect lane restrictions. Dates: June 9-10, 2021.
Martin Rd: from Lincoln County Line to Mullinix Rd
Lane restrictions (both directions, all lanes). Please slow down in the work zone.
Sweeping loose material from fresh Chip Seal on Mullinix Rd from Martin Rd to Cheney City Limits.
Sweeping loose material from fresh Chip Seal on Mullinix Rd from Martin Rd to Cheney City Limits. Expect lane restrictions. Dates: June 10-17, 2021.
Mullinix Rd: from Martin Rd to UPRR Crossing #31222 (Cheney City Limits)
Lane restrictions (both directions, all lanes). Please slow down in the work zone.
Spokane County crews are repairing potholes, sweeping and spraying weeds as the weather permits. For more information, go to: www.spokanecounty.org/publicworks
The mission of Spokane County Public Works is to provide our citizens and the traveling public with safe and maintained roads, bridges and stormwater facilities through efficient and quality Operations, Construction, Engineering and Planning services.