Project No: CRP 3232
Project Design Engineers: Dawson Matthews, EIT
Project Timeline: Bid Opens 4/29, Anticipated Start Date 6/15, Construction End Date 7/31
Project Funding: FEMA Emergency Management Department
Project Description: The County plans to replace two culverts (on Hazard Road and Dalton Road) and perform stream restoration work along a tributary area to Dartford Creek. The stream restoration includes installing seven (7) beaver dam analogs within the incised channel on the south side of Hazard Road and approximately 1.5 acres of riparian plantings along the stream corridor. The stream restoration will be completed through a local partnership organization, The Lands Council. The project also includes rock-check dams for erosion and sediment control on the north side of Hazard Road.