Jackson Road Bank Stabilization

Project No: N/A

Project Manager: Dawson Matthews

Project Timeline: Summer/Fall 2021

Project Description: Repair of Jackson Road shoulder and eroded stream bank on tributary to Rock Creek. Project will be completed by installing vegetated soil lifts to stabilize the stream bank and rebuild the road shoulder.

Project Update: Design in process.

12/20/21 - Project is in permitting and design phase, likely to be constructed summer/fall 2022.

8/18/22 - Currently under construction. Widening the road and stabilizing the shoulder.

Project Funding: Maintenance