Bigelow Gulch Road Project 4

Project No: CRP-2989

Project Manager: Mick Flugel

Project Timeline: Construction began on April 24th, 2019 and was completed October 21st, 2019

Project Description: Spokane County Public Works replaced the existing 2 lane road (which had narrow lanes, no shoulders, and multiple vertical curves) with a 4 lane road (with a 12’ turn lane or center median, 8’ shoulders and 12’ climbing lanes where needed). 


Bigelow Gulch Road Corridor Projects


Prior to the construction of the project looking South from Old Argonne

Big 4 prior to construction


Prior to the construction project looking South from Lehman Rd

Big 4 prior looking South from Lehman


Prior to the construction project looking south from Transmission Right of Way

Big 4 prior looking south from Trans ROW


After construction was completed October 12th, 2019

Big 4 after construction


After construction was completed October 12th, 2019

Big 4 after const on october 12th