Hazard Road - Mechanically Stabilized Earth Retaining Wall
Project No: CRP 3257
Project Engineer: Pete Bauman
Project Timeline: 2019 Construction
Current Project Status - The projects gabion wall construction, roadway paving, and guard rail installation is complete. Hazard Road is now open to the public.

Project Description - This project implemented a mechanically stabilized earth wall to mitigate the slope failure. The compromised outboard lane was excavated and reclaimed. The undermined guard rail, curb, and pavement was replaced as needed.