Project Cost

How much will this cost?
The project costs have been reduced by some $54 million from original estimates. However, the Sheriff and the Commissioners will continue working to reduce these numbers to ensure that the public's safety dollars are spent in the best and efficient way possible.

Project Component
Cost
Geiger Replacement
$78,546,000
County Jail Modernization
$30,532,000
Community Corrections Center
$15,303,000
Geiger Demolition and Relocation
$9,673,000
Site Acquisition, Infrastructure
$6,222,000
Fees, Engineering, Overhead
$59.215,800
Total
$199,490,800

Return to FAQs.