6-Treatment and Conveyance

   

 

 

 

 

 

Home
Basis of Planning
Environmental Impact
Facilities Plan

 

 

Draft Wastewater Facilities Plan
Chapter 6. Treatment and Conveyance
Back Next

6.1        Introduction

This chapter evaluates the issues of where to locate treatment facilities to handle Spokane County’s wastewater, and how much capacity to assign to existing or new treatment facilities.  To address these questions, five major concepts were developed and evaluated.  For some concepts, multiple “sub-alternatives” were considered.

Prior to presentation of the alternatives, information is presented regarding the development of representative treatment and conveyance components incorporated in the wastewater management options.

6.2        Development of Representative Treatment Systems

To meet future capacity needs and more stringent effluent quality requirements, all of the alternatives include upgrades and expansions of existing facilities and/or construction of new treatment plants.  The following sections describe the assumptions and methodology used to determine treatment facility requirements and develop estimated costs.

6.2.1        Expansion of the SAWTP

Currently, Spokane County owns a capacity allocation in the Spokane Advanced Wastewater Treatment Plant (SAWTP) of 10 mgd, based on “average dry-weather flow”.  The various alternatives involve treatment scenarios that maintain, increase or decrease the County’s capacity allocation at the SAWTP.

For each scenario, it has been assumed that the City of Spokane will continue to use the SAWTP for wastewater treatment.  It also has been assumed that the level of treatment at the SAWTP will be improved to meet future, more stringent effluent quality requirements.  Based on discussions with City staff and their consultant, the process configuration shown in Figure 6‑1 has been used as the basis for facility planning.  This treatment train assumes continued use of chemical phosphorus removal addition, addition of ballasted flocculation and filtration, and conversion to UV disinfection.

Facility requirements and costs associated with the SAWTP are presented in Error! Reference source not found., Error! Reference source not found..  A summary of the findings is presented in the following discussion.

Maintain Current Capacity Allocation

To maintain the current 10 mgd capacity allocation, the County must increase its investment in the SAWTP.  There are several reasons for this:

·        Restoration of 44 mgd capacity.  Following the major expansion of the SAWTP in the late 1970s, the plant had a nominal “dry weather” capacity of 44 mgd, of which 10 mgd was allocated to the County and 34 mgd to the City.  With the establishment of more stringent ammonia-nitrogen limits in recent NPDES discharge permits, the

 

Figure 61.  Anticipated Future Process for SAWTP

 

City’s consultant has estimated that the nominal capacity of the current facility has been reduced to 40 mgd.  Restoring the capacity to 44 mgd requires increasing the aeration basin volume and implementing other secondary treatment improvements.

·        Maintenance and safety improvements.  A number of aging equipment items such as clarifier mechanisms, pumps and digester covers are deteriorating, and require replacement or upgrades.  A reserve account for equipment replacement has not been established as part of the SAWTP operating fund, so these measures must be funded from the capital program.  Major system improvements also are needed to improve odor control, upgrade solids processing facilities, convert disinfection to ultraviolet (UV) radiation, and improve access for maintenance.  These improvements do not significantly increase the capacity of the plant, but are needed to improve operation or to resolve aesthetic, safety, or code compliance issues.

·        Improved level of treatment.  To meet anticipated future effluent quality requirements, it has been assumed that effluent filtration will be required.  Furthermore, the City’s consultant has projected that ballasted flocculation may be needed as an intermediate process between the secondary clarifiers and filters.  Other process modifications will include conversion of the activated sludge process to a step-feed system providing partial denitrification.

The total projected capital cost of these improvements, including contingencies and allowances is $100 million.  The County’s proportionate share (10/44th) of the costs would be $22.7 million.  This equates to a unit cost of $2.27 per gallon of dry weather capacity. 

Increase Capacity Allocation

The City’s consultant developed preliminary estimates of the facility requirements and capital cost to increase the dry weather capacity of the SAWTP to 75 mgd.  These projections were then adjusted to match a flow rate of 65 mgd, which is the projected combined dry-weather flow rate from the City and County in 2025 (see Error! Reference source not found.).

The total projected cost to take the plant from its current condition to a 65 mgd capacity and improved level of treatment is $216 million[1].  Subtracting the cost to maintain a nominal capacity of 44 mgd with improved treatment levels results in a cost of $116 million associated with capacity expansion.  For the additional 21 mgd of capacity attained, the unit cost is $5.54 per gallon.

Reduce Capacity Allocation

If the County were to reduce its 10 mgd capacity allocation in the SAWTP, the unused allotment could be sold the City, or perhaps to another agency.  The true value of this capacity can be determined only through negotiations; however, a brief analysis was conducted to provide insight as to the potential value of this asset.

Sale to City

If the treatment capacity were sold to the City, two primary considerations would impact the potential price:

·        Deferred cost of plant expansion.  This is the avoided cost associated with using existing County capacity rather than expanding the SAWTP.  As shown above, the unit capital cost would be $5.54 per gallon.

·        Upgrade cost to address maintenance and compliance issues.  To make the County’s capacity of use to the City, investments would be needed for maintenance, odor control, code compliance and enhanced operation.  The unit capital cost of these investments is $2.27 per gallon.

The total potential value would equal the difference between the two items.  This results in a net unit value of $3.27 per gallon.

In addition to the value of the treatment facilities, reduction of County flows to the City system would free up conveyance capacity in the City’s interceptor system.  This capacity has value to the City, particularly with respect to CSO control.  This issue is addressed later in this chapter under the heading “Development of Conveyance Requirements”.

Sale to Another Agency

If the County’s unused capacity allocation were sold to another agency, the following considerations would impact the potential price:

·        Deferred cost of new plant construction.  This is the avoided cost of building new treatment capacity.  The estimated present-worth unit cost for this capacity is roughly $8.00 per gallon, as discussed in the next section on “new treatment plants”. 

·        Upgrade cost to address maintenance and compliance issues.  This cost is the same as described for “Sale to City” -- $2.27 per gallon.

The total potential value to a new agency would be the difference between these two unit costs, or $5.73 per gallon.

Operating Cost of SAWTP

At the beginning of 2001, the City charged the County a unit cost for operations and maintenance (O&M) of $1,171 per million gallons (MG).  The monthly charge is based on the sum of the readings for the North Spokane, North Valley and Spokane Valley meter stations. Recently, the City announced that the unit O&M charge will increase.  At the time of this report, the new rate had not been announced.

6.2.2        New Treatment Plants with Year-Round Discharge

To facilitate an “apples to apples” comparison of the treatment alternatives, each of the potential new treatment facilities was assumed to have similar processes for treatment of the liquid and solids streams.  Facility requirements and cost estimates are based on the process configuration shown in Figure 6‑2.

The liquid treatment scheme would be similar to that projected for the future SAWTP, with the exception that biological phosphorus would be provided, eliminating the need to feed alum to the primary clarifiers. Sludge treatment would consist of gravity thickening for primary sludge, flotation thickening for secondary and chemical sludge, anaerobic digestion, sludge storage, and dewatering.  The resulting Class B sludge would be hauled by truck to agricultural fields for beneficial reuse.

It is anticipated that this treatment system would produce effluent quality equal to or better than the upgraded SAWTP treatment process shown in Figure 6-1. Effluent from this facility would be suitable for discharge to surface water or may be used in a variety of reuse applications such as urban or agricultural irrigation. 

Once the preferred number, location and capacities of the treatment plants have been determined, other effluent and biosolids management options (see Chapters 5 and 8) may be incorporated into the preferred wastewater management concept.

Figure 62.  Anticipated Future Treatment Process for New Plant

 

Capital Costs for New Treatment Plants

Estimates of the unit capital cost for new treatment facilities were developed in two ways:

·        Comparison with recent, similar plants.  In this approach, construction cost data were obtained for four treatment plants built in the past decade that had similar characteristics to the proposed concept for a new Spokane County plant.  These plants had design capacities ranging from 4 to 12 mgd.  The cost data for each plant were then adjusted to account for differences in the types of treatment processes provided, the level of architectural treatment and odor control implemented, and such allied costs as contingencies, sales tax, design allowances, etc.  Finally, the costs were adjusted to 2001 dollars and a $1.00 per gallon “safety factor” was added to account for miscellaneous costs that may not have been accounted for in the cost analysis.

Figure 63.  Projected Unit Capital Cost for New Treatment Plants

·        Process-by-process estimates.  HDR’s Envision Cost Model was used to develop projected costs for each of the unit treatment processes anticipated in the new plants.  The unit process costs were then totaled to produce an estimate for the complete plant.  The cost model is based on cost curves that HDR developed for the U.S. Environmental Protection Agency.

Based on these analyses, the unit capital costs shown in Figure 6‑3 were used in the alternative comparisons. These costs demonstrate the economy of scale associated with new plants in the capacity range of 3 to 12 mgd.

Operating Cost for New Treatment Plants

Recent benchmarking studies of competively-operated wastewater treatment facilities indicate that a 10 to 20 mgd plant providing nutrient removal, effluent filtration and Class B biosolids production would be expected to have an operating cost of $900 to $1,000/MG of wastewater treated.  For smaller plants, the operating cost would increase slightly.  For this study, operating costs of $1,000 to $1,200/MG were used, depending on the size of the plant.  Unit operating costs were assumed to increase at a rate of 3 percent per year.

6.3        Development of Conveyance Requirements

All of the alternatives involve new or expanded conveyance facilities to route projected flows to the treatment plants.  In this evaluation, the analysis for conveyance facilities is limited to the following areas:

·        Major interceptor and/or pumping facilities needed to convey flow from the North Valley and Spokane Valley Interceptors to new or existing treatment facilities.

·        Interceptor improvements needed to convey North Spokane flow to the SAWTP.

·        Interceptor improvements needed to reroute North Spokane flow to a new treatment facility.

Collection system requirements upstream of these facilities were considered common to all alternatives and are addressed in the Year 2001 Comprehensive Wastewater Management Plan for Spokane County.

6.3.1        Conveyance to New or Expanded Treatment Plants

To allow fair comparison of the alternatives, cost estimates for conveyance facilities were based on the providing sufficient capacity to handle projected peak flows through the year 2025.   When these facilities are actually implemented, design would be based on a longer planning horizon (50 years).

Sizing of gravity systems was based on accommodating peak flows with a water depth in the pipeline of 70% of the pipe diameter.  Cost estimates were based on data from the County’s sewering program, updated to 2001 dollars.

Cost estimates for pumping stations and force mains were based on HDR’s cost data for similar facilities constructed n the Northwest.  All costs were updated to 2001 dollars.

6.3.2        Sale of Conveyance Capacity

If the County were to reduce its capacity allocation in the City’s conveyance system, the unused conveyance capacity potentially could be sold the City.  The true value of this capacity would need to be determined through negotiations between the City and County.  In this analysis, a nominal amount was included for this transaction.

6.3.3        Reuse Conveyance

For the baseline comparison of the alternatives, no costs have been included for conveyance of treated effluent to reuse applications.

6.4        Treatment Alternatives

During the fall of 2000, workshops were held to brainstorm and screen alternatives for providing wastewater treatment capacity for Spokane County.  The following concepts survived the screening process.

·        Alternative 1 – All Flow to Spokane Advanced Wastewater Treatment Plant (SAWTP)

·        Alternative 2 –New Mid-Valley Plant Combined with SAWTP and/or New North Spokane Plant

·        Alternative 3 – New In-City Plant Combined with SAWTP and/or New North Spokane Plant

·        Alternative 4 – Multiple Mid-Valley Plants Combined with SAWTP and/or New North Spokane Plant

·        Alternative 5 – No Action

Figure 64.  General Locations of Potential Sites for New Wastewater Treatment Facilities

 

Generalized locations for potential new treatment facilities are shown in Figure 6‑4.

For Alternatives 2, 3 and 4, a number of “sub-alternatives” were developed that represented differing allocations of treatment capacity amongst the multiple treatment facility locations.

The following sections of this chapter provide brief descriptions of each alternative and sub-alternative.  Facility requirements are based on the projected flow that will be generated from the County’s service area in the year 2025.

 

Accompanying the descriptions are simplified flow schematics.  These schematics:

 

·        Depict the amount of flow generated in each of the County’s major service areas:  North Spokane, North Valley and Spokane Valley. 

·        Present the number and size of treatment facilities.

·        Identify major facilities required to convey the wastewater.

 

Within the schematics, two flow values are usually shown.  The average flow represents the annual-average daily flow, expressed in millions of gallons per day (mgd).  The peak flow represents the maximum flow rate that must be conveyed or treated.  Peak flows usually occur following major, intense rainfalls.  The flow values represent County flows only.  Flows generated by the City of Spokane or other jurisdictions are not presented.

6.4.1        Alternative 1 – All Flow to Spokane Advanced Wastewater Treatment Plant (SAWTP)

Alternative 1 continues the current practice for conveyance, treatment and discharge of wastewater; however, it expands and improves those practices to meet anticipated permit requirements and to accommodate projected growth (see Figure 6‑5).  In this approach, the SAWTP would be expanded to handle all flow from both the County and City through the year 2025.  The County’s average flow in the year 2025 is projected to be 22 mgd, whereas the combined City/County flow is estimated to be 65 mgd.  It is likely that this combined flow would exhaust the capacity of the current SAWTP site, requiring the construction of additional treatment facilities to handle the region’s growth beyond 2025. 

 

Figure 65Alternative 1 – All Wastewater Routed to SAWTP (Year 2025 County Flows)

 

 

The County and City conveyance systems also would need to be expanded to handle the projected flows.  The major cost would be associated with conveying County flows from the Valley to the SAWTP.  Based on the current interlocal agreement between the City and County, the allowable peak flow through the City’s interceptor system is limited to 15.5 mgd.  This falls far short of the projected peak flow of 37 mgd from the Valley.   Providing the additional conveyance capacity is complicated by the fact that the City experiences multiple combined sewer overflows (CSOs) along the interceptor system that conveys Valley flows.  Given this significant restriction, it has been assumed that all Valley flows in excess of 15.5 mgd would be pumped through a new force main to the SAWTP.  This would require one or two new pumping stations and approximately 8 miles of force main.  Much of the force main would need to be routed through densely developed portions of the City.

 

In North Spokane, some segments of the City’s interceptor system would need to be increased in size to handle the future County flows.

6.5        Alternative 2 – New Mid-Valley Plant Combined with SAWTP and/or New North Spokane Plant

6.5.1        Overview

In this concept, a new treatment plant would be constructed in the western part of the Spokane Valley service area.  This plant would serve part or all of the County flow generated in the Spokane Valley and could serve flow from the eastern portion of the City’s service area.  To handle all County flows, additional capacity would be provided at the SAWTP and/or at a new plant located in North Spokane.

Five sub-alternatives were identified that involve different allocations of flow to the three treatment plant sites.  These allocations are summarized in Table 6‑1.

 

 

Table 61Allocation of Projected Average Flows from Spokane County in 2025

Alternative 1

SAWTP, mgd

Mid-Valley2, mgd

North Spokane, mgd

Total, mgd

2A

10

11.9

0

21.9

2B

10

7.0

4.9

21.9

2C

14.9

7.0

0

21.9

2D

4.9

17.0

0

21.9

2E

0

17.0

4.9

21.9

1.   Values shown are County flow only. 
2.   The Mid-Valley plant also could receive flow from the City of Spokane’s service area.

6.5.2        Sub-Alternative 2A – SAWTP at 10 mgd; No Plant in North Spokane

In this concept, the County would retain its current 10-mgd capacity allocation in the SAWTP to treat all flow from the North Spokane Service Area and a portion of the flow generated in the Spokane Valley.  Valley flow that could not be sent to the SAWTP would be treated at a new 12-mgd Mid-Valley Plant that would discharge to the Spokane River below the Upriver Dam.  A schematic of Sub-Alternative 2A is shown in Figure 6-6. 

For initial planning purposes, it has been assumed that the new Mid-Valley plant would be located in the vicinity of the North Valley interceptor, but that an influent pumping station would be needed to lift the North Valley flow into the treatment works.   To convey flow from the Spokane Valley Interceptor to the new treatment plant, a new pump station and force main would be required.

 

Figure 66.  Alternative 2A – 12 mgd Mid-Valley Plant, SAWTP at 10 mgd, No North Spokane Plant (Year 2025 County Flows)

Figure 67 Schematic of Current City of Spokane Interceptor System

With this approach, the amount of flow that must be conveyed from the Spokane Valley to the SAWTP would be substantially reduced.  No County flow would be routed to the portion of City Interceptor I-05 located upstream of the convergence with the Southeast Spokane Interceptor (see Figure 6-7).  This would reduce flows in a section of interceptor with multiple CSO locations.  Also, the total County flow from the Spokane Valley would be reduced to an average rate of 5 mgd and a peak rate of 10 mgd, which is well below the County’s current capacity allocation in the City’s interceptor system (15.5 mgd).  This negates the need for the County to expand capacity in this section of the City’s system, and helps alleviate the potential for CSOs in the central portions of the City’s conveyance system.

To convey future North Spokane flows to SAWTP, some segments of the City’s interceptor system must be replaced, or parallel sewers must be installed.

6.5.3        Sub-Alternative 2-B – SAWTP at 10 mgd with North Spokane Plant

This alternative retains the County’s 10 mgd capacity at SAWTP and builds a new 5-mgd plant in North Spokane to handle flows from that service area.  To handle all 22 mgd of the County’s flow in 2025, the required size of the new Mid-Valley Plant would be 7 mgd. A schematic of Sub-Alternative 2B is shown in Figure 6‑8.

The North Spokane Plant would require an outfall to the Little Spokane River.  Conveyance of wastewater to the new plant would require a major reconfiguration of the conveyance system serving North Spokane.  Currently, wastewater flows to multiple lift stations that pump the flow southward over a ridge to the SAWTP.  Reversing the direction of flow and converting the collection system to gravity flow would involve installation of a number of interceptors and abandonment of some current pumping stations.

 

Figure 68.  Alternative 2B – 7 mgd Mid-Valley Plant, SAWTP at 10 mgd, 5 mgd North Spokane Plant (Year 2025 County Flows)

The new Mid-Valley plant would receive flow primarily from the North Spokane Interceptor.  Similar to Alternative 2A, this would eliminate County flows from entering the upper reaches of the City’s CSO-prone I-05 interceptor (see Figure 6-7).

A difficulty with Alternative 2B is the conveyance of flows from the Spokane Valley.  In 2025, the average flow generated in this portion of the County’s service area is projected to be 10 mgd, which matches the County’s capacity allocation at SAWTP.  However, the projected peak flow is 20 mgd, which exceeds the County’s capacity in the City interceptor system.  Given the City’s CSO issues, the County may not be able to obtain additional conveyance capacity in this section of the City’s system, or it may prove to be expensive.  For planning purposes, it has been assumed that the County would install a pumping station along the Spokane Valley Interceptor that would send all flow above 15.5 mgd to the new Mid-Valley Plant.  This would require that the Mid-Valley plant be designed to withstand high peak flows.  The Spokane Valley pumping station would operate only intermittently during peak flow conditions.

6.5.4        Sub-Alternative 2-C – Increased Flow to SAWTP

In this approach, the County would increase the amount of flow treated at the SAWTP to 15 mgd, with 5 mgd originating in North Spokane and 10 mgd being sent from the Spokane Valley service area.  A new 7 mgd plant would be built in the Mid-Valley to handle the remaining flows generated in the County’s service area.  Figure 6‑9 presents a schematic of this concept.

The Mid-valley plant would be identical to that presented for Sub-Alternative 2B.  Similarly, the conveyance facilities required to handle North Valley and Spokane Valley flows would be identical to Sub-Alternative 2B.   

 

Figure 69.  Alternative 2C – 7 mgd Mid-Valley Plant, SAWTP at 15 mgd, No North Spokane Plant (Year 2025 County Flows)

To convey future North Spokane flows to SAWTP, some segments of the City’s interceptor system must be replaced, or parallel sewers must be installed.

 

6.5.5        Sub-Alternative 2-D – North Spokane Only to SAWTP

In Sub-Alternative 2D, only the flow from North Spokane would be sent to the SAWTP.  All flow from the Valley would be routed to a new, 17-mgd Mid-Valley treatment plant.  Figure 6‑10 shows this arrangement.

Facility requirements for conveyance of North Spokane flows would be the same as described for Sub-Alternative 2A.

 

Figure 610.  Alternative 2D – 17 mgd Mid-Valley Plant, SAWTP at 5 mgd, No North Spokane Plant (Year 2025 County Flows)

 

To convey Spokane Valley flows to the new Mid-Valley plant, a 20 mgd pumping station and force main would be needed.

This alternative completely removes all County wastewater from City interceptors I-05, I-04 and I-02, all of which have significant capacity limitations or CSOs (see Figure 6-7).

Implementation of Alternative 2D would allow the County to sell to the City its conveyance capacity between the Valley and SAWTP.

6.5.6        Sub-Alternative 2E – No Flow to SAWTP

 

Figure 611.  Alternative 2E – 17 mgd Mid-Valley Plant, No Flow to SAWTP, 5 mgd North Spokane Plant (Year 2025 County Flows)

This approach sends all County flows to new treatment plants, eliminating treatment of County flow at the SAWTP.  It requires building a 5 mgd plant to serve North Spokane and a 17 mgd plant to serve the Spokane Valley (see Figure 6‑11). 

In this alternative, the County would sell treatment and conveyance capacity back to the City.

 

 

 

6.6        Alternative 3 – New In-City Plant Combined with SAWTP and/or New North Spokane Plant

6.6.1        Overview

This alternative is similar to Number 2, except a new In-City Plant, constructed in the south-central part of the City of Spokane, would replace the Mid-Valley Plant.  This plant would serve part or all of the County flow generated in the Spokane Valley and would likely serve flow from the southern portion of the City’s service area.  Again, treatment of County flows would be provided at two and possibly three locations.  The division of flows for the Alternative 3 “sub-alternatives is presented in Table 6‑2.

Table 62.  Allocation of Projected Average Flows from Spokane County in 2025

Alternative 1

SAWTP, mgd

In-City2, mgd

North Spokane, mgd

Total, mgd

3A

10

11.9

0

21.9

3B

10

7.0

4.9

21.9

3C

14.9

7.0

0

21.9

3D

4.9

17.0

0

21.9

3E

0

17.0

4.9

21.9

     1.   Values shown are County flow only. 
     2.    In-City plant would also receive flow from the City of Spokane’s service area.

6.6.2        Sub-Alternative 3A – SAWTP at 10 mgd; No Plant in North Spokane

 

Figure 612.  Figure 6-12.  Alternative 3A – 12 mgd In-City Plant, SAWTP at 10 mgd, No North Spokane Plant (Year 2025 County Flows)

In this concept, the County would retain its 10 mgd capacity allocation in the SAWTP to treat all flow from the North Spokane Service Area and a portion of the flow generated in the Spokane Valley.  Valley flow that could not be sent to the SAWTP would be treated at the new In-City Plant.  Given the limited conveyance capacity owned by the County and the occurrence of CSOs along the City’s interceptors, it has been assumed that all County flow sent to the In-City plant must be pumped through a new force main.  A schematic of Sub-Alternative 3A is shown in Figure 6‑12.

6.6.3        Sub-Alternative 3B – SAWTP at 10 mgd with North Spokane Plant

 

Figure 613.  Alternative 3B – 7 mgd In-City Plant, SAWTP at 10 mgd, 5 mgd North Spokane Plant (Year 2025 County Flows)

This alternative retains the County’s 10 mgd capacity at SAWTP and builds a new plant in North Spokane to handle flows from that service area.  Compared to Sub-Alternative 3A, this would reduce the amount of County flow to be treated at a new In-City Plant. A schematic of Sub-Alternative 3B is shown in Figure 6‑13.

 

 

 


 

6.6.4        Sub-Alternative 3C – Increased Flow to SAWTP

 

Figure 614.  Alternative 3C – 7 mgd In-City Plant, SAWTP at 15 mgd, No North Spokane Plant (Year 2025 County Flows)

In this approach, the County would increase the amount of flow treated at the SAWTP to 15 mgd.  This would make maximize use of the capacity that the County has purchased in the City’s interceptor system.  A new 7 mgd In-City Plant would be built to handle the remaining flows generated in the County’s service area.  Figure 6‑14 presents a schematic of this concept.

 

6.6.5        Sub-Alternative 3D – North Spokane Only to SAWTP

 

Figure 615.  Alternative 3D – 17 mgd In-City Plant, SAWTP at 5 mgd, No North Spokane Plant (Year 2025 County Flows)

In Sub-Alternative 3D, only the flow from North Spokane would be sent to the SAWTP.  All flow from the Valley would be routed to a new, 17-mgd In-City treatment plant.  Figure 6‑15 shows this arrangement.

Implementation of Alternative 3D would allow the County to sell to the City its conveyance capacity between the Valley and SAWTP.

 


 

6.6.6        Sub-Alternative 3E – No Flow to SAWTP

 

Figure 616.  Alternative 3E – 17 mgd In-City Plant, No Flow to SAWTP, 5 mgd North Spokane Plant (Year 2025 County Flows)

This approach sends all County flows to new treatment plants, eliminating treatment of County flow at the SAWTP.  It requires building a 5 mgd plant to serve North Spokane and a 17 mgd plant to serve the Spokane Valley (see Figure 6‑16).

In this alternative, the County would sell treatment and conveyance capacity back to the City.

 

6.7        Alternative 4 –  Multiple Mid-Valley Plants Combined with SAWTP and/or New North Spokane Plant

6.7.1        Overview

This alternative builds on the concept presented in Alternative 2, but rather than constructing a single wastewater plant in the Spokane Valley, two smaller plants would be built.  This would place treatment facilities close to 1) where the wastewater is generated and 2) where the treated effluent could potentially be sent to reuse applications (irrigation, industrial, etc.).  Two sub-alternatives considered the potential of building an additional plant in North Spokane. 


 

6.7.2        Sub-Alternative 4A – Two Mid-Valley Plants; No Plant in North Spokane

 

Figure 617.  Figure 6-17.  Alternative 4A – Two Mid-Valley Plants (7 mgd & 5 mgd), SAWTP at 10 mgd, No North Spokane Plant (Year 2025 County Flows)

In this approach, a 7 mgd plant would be built to serve all wastewater generated in the North Valley service area.  A second 5-mgd plant would be built to serve a portion of the flow from the Spokane Valley service area.  The remaining flow from Spokane Valley and all flow from North Spokane would be sent to the SAWTP.  A schematic is shown in Figure 6‑17.

 

 

6.7.3        Sub-Alternative 4B – Two Mid-Valley Plants with North Spokane Plant

 

Figure 618.  Alternative 4B – Two Mid-Valley Plants (4 mgd & 3 mgd), SAWTP at 10 mgd, 5 mgd North Spokane Plant (Year 2025 County Flows)

In Sub-Alternative 4B the capacity of the treatment plants along the North Valley and Spokane Valley interceptors would be reduced to 4 and 3 mgd, respectively, with all remaining flow from the Valley (10 mgd) being sent to the SAWTP.  A new 5 mgd plant would be built to serve North Spokane.  Figure 6‑18 presents this concept.

 

 

 

6.8        Alternative 5 – No Action

Under this alternative, Spokane County would take no action to improve or expand wastewater conveyance and treatment facilities.  Consequently, it would fail to provide adequate capacity to complete the septic tank elimination program, and for projected growth within the service area, and may fail to meet permit requirements for discharge to the Spokane River.  No action may result in fines being levied against Spokane County.  Most likely, it would also result in a building moratorium for the County and may result in the imposition of judicial control over the County’s wastewater management program.

6.9        Cost of Alternatives

6.9.1        Capital Costs

Projected capital costs were developed for each alternative and subalternative.  These are summarized in Error! Reference source not found..  It should be noted that the capital costs are presented as if all of the infrastructure components needed to accommodate Year 2025 flows were built today (2001).  To simplify the analysis, no consideration was given to the optimal phasing of the individual alternatives. 

The costs in Error! Reference source not found. are divided into the following categories:

·        Treatment Capacity Construction.  These line items reflect the cost to:

·        Upgrade and maintain the 10 mgd of capacity that the County owns in the SAWTP.  All alternatives include this $22.7 million line item.  If part of the County’s current capacity in the SAWTP is to be sold to the City, that cost adjustment is addressed under “Treatment Capacity Sale”.

·        Build 12 mgd of additional capacity at the SAWTP and/or new treatment facility locations.  These costs include the treatment plants and outfalls to the receiving streams.

·        Treatment Capacity Sale.  For those alternatives that involve reducing the County’s flow to SAWTP below 10 mgd, this value reflects the estimated “fair market value” for sale of the unused capacity to the City.  To attain this value, the County must first participate in upgrading the current SAWTP plant to restore capacity, provide maintenance and safety improvements and improve the level of treatment.

·        Land.  Costs for land are included for new treatment plant sites.  The cost is based on 2 acres per mgd of capacity.  The unit price for land varies with the location of the proposed treatment plant, as described in Chapter 3.

·        Treatment Plant Siting/Permitting.  For each new treatment site, an estimated cost of $1 million was allowed for siting, permitting and environmental documentation.

·        Conveyance Construction.  These line items reflect the cost of major pumping stations, force mains and interceptors needed to convey the sewage to the treatment plants

·        Sale of Conveyance Capacity.  This line item identifies the potential value that may be received from sale of unused conveyance capacity to the City.  It applies to those alternatives that divert flow away from the City’s interceptor system.  

6.9.2        Operating Costs

As described earlier in this chapter, the current unit operating charge at the SAWTP is $1,171/MG.   Benchmarking surveys of competively-operated treatment plants similar to those anticipated for Spokane County indicate a unit operating cost of $900 to $1,200/MG may be anticipated, with the higher cost associated with small treatment facilities (3 to 6 mgd).

To assess the impact of operating costs on the alternatives comparison, a present value calculation was made of the projected cost to treat Spokane County flows from 2007 through 2025.  During this period, the unit operating costs were assumed to increase by 3 percent each year, and the present value calculation was based on a 6.375 percent discount rate.  The analysis found that each $100/MG increase in the unit operating cost translates to a present value increase of $10 million. 

6.10    Screening of Alternatives to Identify Finalists

Following development of the 14 subalternatives, a workshop was held to reduce the number of final alternatives to a manageable number for detailed comparison.  Primarily, this involved selecting the best subalternative for Alternatives 2, 3 and 4.  In conducting this screening, the following conclusions were reached:

·        For Alternatives, 2, 3 and 4, it is cost effective to maintain the County’s current 10 mgd of capacity at SAWTP.  This conclusion eliminated alternatives that sold all or part of the County’s capacity in SAWTP (Subalternatives 2D, 2E, 3D and 3E.)

·        Siting a new treatment plant in North Spokane proved unattractive for the following reasons:  1) the North Spokane conveyance system would require major realignment to accommodate this change, 2) there are few suitable sites for a new treatment plant in North Spokane, 3) from an overall “cost of conveyance” perspective, it is best to send all North Spokane flow to SAWTP and to reduce the flow from the Spokane Valley to SAWTP, and 4) it was recognized that siting a new plant in North Spokane and permitting a new discharge to the Little Spokane River would be controversial, resulting in potential implementation delays.   Consequently, Subalternatives 2B, 3B and 4B were eliminated.

·        Subalternatives 2C and 3C were considered unattractive relative to other remaining alternatives because they required constructing new treatment plants plus constructing new conveyance capacity between the Spokane Valley and SAWTP.  The remaining alternatives eliminated one or the other of these requirements. 

Based on this screening exercise, the selected finalists were as follows:

·        Alternative 1 – All Flow to SAWTP

·        Alternative 2A – 12 mgd Mid-Valley Plant, SAWTP at 10 mgd, No North Spokane Plant

·        Alternative 3A – 12 mgd In-City Plant, SAWTP at 10 mgd, No North Spokane Plant

·        Alternative 4A – Two Mid-Valley Plants (7 mgd and 5 mgd), SAWTP at 10 mgd, No North Spokane Plant

·        Alternative 5 – No Action

6.11    Discussion of Final Alternatives Relative to Evaluation Criteria

The final treatment location alternatives were compared relative to one another using the evaluation criteria developed for this planning effort.  A summary of the comparison is presented in Error! Reference source not found..  Key findings are presented in the following sections, with emphasis placed on factors that strongly differentiate the alternatives.  Comparison of the treatment and conveyances alternatives with the evaluation criteria is summarized in Figure 6‑19

6.11.1    Capacity

This criterion addresses the alternative’s ability to meet the County’s near-term and long-term requirements for wastewater treatment capacity. The near-term requirement relates to the ability to implement the solution before 2007, when County flows are projected to reach the capacity allocation in the SAWTP.  The long-term requirement relates to the alternative’s ability to provide a long-term (50-year) solution.

Alternative 1 rated poorly against this criterion because 1) it does not offer a long-term capacity solution and 2) it may be difficult to implement by 2007.  In 2025, the projected wastewater flows from the City and County will total 65 mgd.  If all of this flow is treated at SAWTP, the estimated maximum capacity of the site will be reached and conveyance systems feeding the plant will be at or above current capacity.  Consequently, additional treatment plants at new locations would likely be needed to handle flows beyond 2025.  Implementing Alternative 1 would require negotiation of a new interlocal agreement with the City and construction of major conveyance facilities through urban areas. 

Alternative 3A rated only slightly higher than Alternative 1.  While this alternative provides an effective long-term capacity solution, its ability to be implemented by 2007 is strongly dependent on development of the City’s strategy for CSO control.  At this time, the City is developing planning tools and gathering data to develop a CSO control plan.  Identification of recommended control measures, including the potential role of new treatment plants within the CSO management strategy, is not expected for 2 to 3 years.  Delaying key implementation decisions by this amount of time would make it very difficult to site and build a new treatment plant by 2007. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

Figure 619.  Comparison of Treatment Location Alternatives with Evaluation Criteria

Alternatives 2A and 4A rated high against the capacity criterion.  Both alternatives provide considerable flexibility as long-term capacity solution, including the ability to accept wastewater from portions of the City’s service area.  With respect to implementation, the alternatives are not dependent on completion of the City’s CSO plan.

Alterative 4A rated somewhat lower than Alternative 2A because two facilities would need to be sited and built, which may require additional implementation time.

Alternative 5 (No Action) received the lowest rating because it fails to meet the County’s near-term and long-term capacity needs.

6.11.2    Technical

This considers the operational complexity of the alternative.  Since the alternatives will likely use similar treatment technologies, the number of plants and major pumping facilities that must be maintained primarily affects the criterion.  Fewer facilities result in a higher rating.  Consequently, Alternative 1 rated the highest and 4A rated the lowest.

6.11.3    Conveyance

This criterion applies to the extent and complexity of sewers and pump stations that must be implemented.  Alternative 1 has the greatest conveyance requirements, including routing of a major force main though urban areas.  Similarly, Alternative 3A requires construction of a new force main through the downtown area, although the pipeline length is shorter than for Alternative 1.  Alternatives 2A and 4A also include pump stations and force mains, but these facilities are smaller than those needed for Alternatives 1 and 3A, and would be located in areas where construction would be less difficult and disruptive.  Alternative 5 (No Action) would build no conveyance facilities.

6.11.4    Implementation

Here, consideration is given to challenges associated with acquiring property and permits.  Generally, siting an In-City plant was considered more challenging than siting a Mid-Valley plant.  Also, siting multiple new facilities resulted in a lower rating.

Alternative 1 received the highest rating since no new treatment plants must be sited.  However, construction of the pipelines would require a significant number of right-of-ways and permits.  Alternative 2A had the next best rating since only one new plant site in the Spokane Valley would be required.  Alternative 3A rated low because of the need to site a new plant near downtown Spokane.  Alternative 4A rated low because two new plants must be sited and permitted. Alternative 5 has no siting or permitting requirements.

6.11.5    County Control

This factor relates to the County’s ability to implement the alternative on its own, without relying on actions by other jurisdictions.  This criterion is significant given the need to implement additional capacity by 2007.

Alternatives 2A and 4A rated highest because the County could implement these solutions without the need for interlocal agreements with other jurisdictions.  Alternatives 1 and 3A would require interlocal agreements with the City.  With respect to Alternative 1, the City could elect to deny the County additional capacity at the SAWTP.

Alternative 5 (No Action) would result in the County’s failure to meet its requirements as a utility provider and could result in the wastewater being taken over by the courts or another entity.

6.11.6    Regulatory

This criterion addresses anticipated impacts to the receiving streams and the potential for compliance with discharge permits.  Generally, alternatives that spread the location of effluent discharge along receiving waters are rated higher because they lessen localized in-stream impacts.  Alternatives with multiple plants were rated lower because they result in more permits to comply with.

Alternative 1 received the lowest rating because it provides a single point of discharge for all City and County flows.  This concentrated loading increases the potential for toxicity or temperature impacts and makes limited use of the river’s assimilative capacity for organic and nutrient loadings.

Alternatives 2A, 3A and 4A spread the effluent discharge to multiple locations along the river, lessening localized water quality impacts.  Alternatives 2A and 4A achieve a greater separation of discharge locations than Alternative 3A and are considered better from a receiving water perspective.  Alternative 4A was de-rated somewhat because addition of another plant increases the number of permit conditions that must be complied with.

Alternative 5 (No Action) would result in severe compliance violations.

6.11.7    Water Resource

This factor considers the proximity of the treatment plants to potential reuse opportunities.  Alternative 4A, which was designed to maximize reuse potential, rated the highest.  Alternatives 2A and 3A also offer significant reuse potential, with Alternative 2A being rated slightly higher because of he industrial reuse potential associated with Inland Empire Paper.  Reuse opportunities for Alternative 1 appear more limited and would require long pipelines to reach locations with significant water demand.  Alternative 5 provides no reuse opportunities.

6.11.8    Impact

This criterion addresses the environmental and community impact of building and operating wastewater facilities.  Alternatives 2A, 3A and 4A were considered similar with respect to this criterion since all involve construction and operation of new treatment plants, pump stations and pipelines.  Alternative 1 rated somewhat higher because no new treatment plants would be built. Alternative 5 would have no direct construction impacts, but may result in a building moratorium that would have a dramatic impact on the community.

6.11.9    Economics

This factor compares total life cycle costs, including capital and operating expenses.  This comparison is driven primarily by the relative capital costs of the alternatives, which was summarized in Error! Reference source not found..  Alternatives 1 and 2A were found to have the lowest capital costs with Alternatives 3A and 4A having capital costs that were 10 percent higher.  Operating costs are impacted by the size of the plant (economy of scale), treatment technology, and the age of the facilities (maintenance requirements).  It is anticipated that the new treatment plants planned for Alternatives 2A and 3A would have unit operating costs that are somewhat lower than the SAWTP.  Alternative 4A, with two smaller plants would have higher operating costs than Alternatives 2A and 3A.  Alternative 5 would not have capital costs, but the potential economic impact to the community would be very negative.

6.11.10 Financial Risk

This factor considers the risk associated with the economic assumptions used in the analysis.  Alternatives that relied on other jurisdictions buying conveyance or treatment capacity from the County were rated lower.  Also, those alternatives that required other jurisdictions to participate jointly in the financing of projects rated lower.

Alternatives 1 and 3A rated lowest because the County would be dependent on the City to jointly finance the treatment plant expansion projects.  The cost analyses for Alternatives 3A and 4A assume that the City would be willing to buy back conveyance capacity between the Spokane Valley and SAWTP; however, the allocated value for this action is small ($2 million) and has little impact on the economic viability or cost comparisons for these alternatives.

 

                                    This site was last updated on:  Thursday November 08, 2001