Highly treated wastewater effluent is an important water resource in the
Spokane Region. Potential uses include streamflow augmentation,
irrigation, wetlands creation, industrial water supply and groundwater
recharge. In this chapter, alternative effluent management strategies are
reviewed by considering their applicability to Spokane County, defining
effluent quality requirements, outlining implementation steps, identifying
facility needs and associated costs, and listing key advantages and
disadvantages. Finally, the alternatives are compared against an array of
evaluation criteria.
Currently, nearly all of the County’s wastewater is treated at the Spokane
Advanced Wastewater Treatment Plant (SAWTP) and discharged year-round to
the Spokane River near Riverside State Park. To comply with the current
NPDES permit for the SAWTP, the treatment plant must achieve “secondary
treatment” standards for BOD and suspended solids, provide year-round
ammonia-nitrogen removal and seasonal phosphorus reduction.
Effluent from five small County treatment facilities (package wastewater
treatment plants or community septic tanks) is discharged to either
community drainfields or infiltration ponds. These facilities are being
phased out as the County extends its sewer system to remote service areas.
Chapter 3 of the Basis of Planning Report gives a detailed
evaluation of existing and future development to be served by the County’s
wastewater treatment facility. Flow is collected in three major
interceptors – two in the Spokane Valley area (North Valley Interceptor
north of Interstate 90 and Spokane Valley Interceptor south of Interstate
90) and one in the North Spokane area (North Spokane Interceptor). Average
wastewater flow projections for each of these interceptors are shown in
Table 5‑1. There is little seasonal variation in these flows.
Potential effluent demand under the various effluent end-use management
options will be compared to these values.
Effluent quality requirements will vary depending on the specific effluent
end-use application. To facilitate comparison of treatment costs for the
alternatives, a “baseline treatment level” was established based on the
anticipated requirements for year-round discharge to the Spokane River.
These standards were described in detail in Chapter 4 of the Basis of
Planning Report and are summarized later in this chapter (see Table 5‑2).
Figure 5‑1 presents a representative treatment train capable of
meeting the projected effluent quality requirements for discharge to the
Spokane River.
Table
5‑1. Projected
Effluent Flow
|
|
Average Flow, mgd |
|
Year |
North Spokane Interceptor |
North Valley Interceptor
|
Spokane Valley Interceptor
|
Total
|
|
1999 |
1.0 |
1.1 |
3.5 |
5.7 |
|
2000 |
1.3 |
1.4 |
3.9 |
6.5 |
|
2005 |
2.4 |
2.7 |
5.3 |
10.4 |
|
2010 |
3.6 |
4.1 |
6.8 |
14.5 |
|
2015 |
4.3 |
5.8 |
8.7 |
18.8 |
|
2020 |
4.7 |
6.5 |
9.5 |
20.6 |
|
2025 |
4.9 |
7.0 |
10.0 |
21.9 |
|
2030 |
5.1 |
7.4 |
10.4 |
23.0 |
|
2035 |
5.4 |
7.9 |
10.8 |
24.1 |
|
2040 |
5.6 |
8.4 |
11.2 |
25.2 |
|
2045 |
5.8 |
8.8 |
11.6 |
26.2 |
|
2050 |
6.0 |
9.3 |
12.0 |
27.3 |


Figure
5‑1.
Process Schematic for Baseline Effluent Quality
Many effluent management alternatives were identified during the
brainstorming workshop and in public meetings (see Chapter 3). Those
ideas selected for detailed review are listed below:
·
Discharge to surface waters
·
Spokane River
·
Little Spokane River
·
Tributaries
·
Irrigation of agricultural land
·
Irrigation of poplar farms
·
Irrigation of urban green spaces
·
Industrial reuse
·
Wetlands creation or enhancement
·
Groundwater recharge
In developing the relative capital costs for each alterative, four
components were considered:
·
Treatment cost: This represents the incremental
treatment cost (or savings) compared to the baseline treatment train
presented in Figure 5‑1.
·
Conveyance and storage cost: This includes the cost
of pipelines, pumping stations, reservoirs and outfalls needed to
implement the alternative.
·
Site development cost: This includes any on-site
development costs associated with the effluent use alternative such as
wetlands development, infiltration basins, etc.
·
Land cost: This includes the cost of land for
alternatives that require County-owned property.
A key challenge in developing the economic comparison is that the
different alternatives result in differing levels of demand for the
effluent. Some alternatives can use all of the effluent on a year-round
basis, whereas others can use only a portion of the effluent and/or
operate on a seasonal basis. For this reason, costs are presented based
on a unit cost per million gallons/year of effluent utilized.
It must also be pointed out that specific infrastructure required for some
alternatives cannot be accurately defined until additional study is
completed. Consequently, the actual costs of implementing some of the
alternatives may vary considerably from the values presented here.
Surface water discharge is the conventional effluent management practice
for municipal wastewater plants. During dry summer periods, highly
treated effluent may provide an important water supply to augment
streamflows and support beneficial uses.
Figure 5‑2.
Major Rivers and Tributaries near the Planning Area
|
During the alternatives development process, three opportunities for
surface discharge were identified:
·
Discharge to the Spokane River
·
Discharge to the Little Spokane River
·
Discharge to smaller tributaries
The Spokane River runs through the northern portion of the Spokane Valley
area and into the City of Spokane, while the Little Spokane River skirts
the northeastern boundary of the North Spokane area. Major tributaries
near the study area, shown in Figure 5‑2, include Latah Creek south
of the City of Spokane, and Deadman Creek near the North Valley area. All
of these water bodies have Class A (exceptional) designations, and are
protected for beneficial uses such as fish and shellfish rearing,
spawning, and harvesting; water supply; recreational use; wildlife
habitat; and commerce and navigation.
In this alternative, treated effluent would be discharged to the Spokane
River year-round. If all Spokane County flow were discharged to the
Spokane River, the average effluent flow rate in 2025 and 2050 would be 34
and 42 cfs, respectively. By comparison, average monthly streamflows in
the river (as measured at the Spokane Gage) range from 1,400 cfs in August
to 17,000 cfs in May. During the critical 7Q20 streamflow condition
(about 600 cfs), the Year 2025 effluent flow rate would represent
approximately 6 percent of the total streamflow.
Applicability to Spokane County
Year-round discharge to the Spokane River is currently practiced for most
wastewater generated in the Spokane Region. When considering ways to
modify or expand this practice, it is important to consider factors that
influence the ability of the river to assimilate the pollutant loading.
These factors include:
·
Proximity to existing dischargers. Currently, there
are four major dischargers to the Spokane River in Washington: Liberty
Lake Water and Sewer District, Kaiser Aluminum, Inland Empire Paper and
the City of Spokane (SAWTP). The first three discharges are located along
the Spokane River between the Idaho border and the Upriver Dam, whereas
the SAWTP’s discharge is downstream of the confluence with Latah Creek.
Spreading out point discharges along the river minimizes local toxicity
issues associated with ammonia, metals, and selected organics, and it
increases the river’s ability to assimilate impacts from nutrients and
dissolved-oxygen-consuming pollutants.
·
Interaction with Spokane Aquifer. It would be
preferable to discharge treated effluent to a reach of the river that is
recharged with groundwater from the aquifer (“gaining reach”). This has
multiple benefits. First, the aquifer recharge adds hardness to the
river, which reduces the toxicity of heavy metals of concern. Second,
discharge to gaining stretches of the river reduces potential regulatory
and public concerns regarding migration of the wastewater discharge into
the aquifer.
Figure 5‑3 shows the major municipal and industrial discharges on
the Spokane River in Washington (green circles), as well as gaining and
losing reaches of the river. Red circles indicate discharges to the Little
Spokane River. Based on the factors identified above, and discussions
with Ecology, Reach 4 appears to be the most attractive location for a new
wastewater discharge to the Spokane River. It is in a gaining stretch of
the river, has free-flowing characteristics to promote re-aeration, and
provides a good separation from the SAWTP discharge. Locating a discharge
at this location would require consideration of the interrelation with
upstream discharges such as that from Inland Empire Paper.
Effluent Quality Requirements
Chapter 4 of the Basis of Planning Report provided a detailed review of
anticipated effluent quality requirements for a new discharge to the
Spokane River. Since receiving waters are most sensitive to effluent
discharge during the late summer (when streamflows are lowest), it is
likely that Ecology would establish a seasonal permit for a new wastewater
discharge.
Based on preliminary discussions with Ecology and review of NPDES permits
for other discharges to the Spokane River, anticipated effluent quality
requirements have been identified for surface water discharge (see
Table 5‑2). Refinements to these requirements will be driven by the
exact location of the discharge, results of mixing zone studies, effluent
concentrations of metals, results of the dissolved oxygen TMDL study, and
negotiations with the Phosphorus Technical Advisory Committee (TAC).
Figure
5‑3. Existing
Dischargers and River/Aquifer Interaction
Table
5‑2. Projected
Effluent Quality for Surface Water Discharge
|
Parameter |
Summer |
Winter |
|
BOD, mg/L1 |
10-20 |
30 |
|
Total Suspended Solids, mg/L |
30 |
30 |
|
Ammonia-Nitrogen, mg/L1,2 |
1-2 |
4-8 |
|
Total Nitrogen, mg/L |
No limit |
No limit |
|
Total Phosphorus, mg/L3 |
0.3-0.6 |
No limit |
|
Dissolved Oxygen, mg/L1 |
> 6.0 |
No limit |
|
Fecal Coliform, cfu/100 mL |
200 |
200 |
|
Chlorine Residual,
mg/L2 |
» 8 |
» 8 |
|
pH (s.u.)4 |
6.0-7.8 |
6.0-7.8 |
|
Lead, mg/L5 |
» 2 |
» 2 |
|
Zinc, mg/L5 |
» 60 |
» 60 |
|
Cadmium, mg/L5 |
» 0.2 |
» 0.2 |
1.
Required value will be defined by dissolved oxygen TMDL process.
2.
Required value will be defined by mixing zone study for toxicity.
3.
Required value will be defined through negotiation with Phosphorus TAC.
4.
Instantaneous value
5.
Required value will be defined based on monitoring of actual effluent
metals concentration.
6. This
effluent quality would be achieved using a treatment train similar to that
shown in Figure 5‑1.
Implementation
Implementing a new surface water discharge for the County’s treated
effluent would require:
·
Negotiating a new NDPES discharge permit with the Department
of Ecology. This effort would include:
·
Conducting dilution studies and a mixing zone study to
determine local impacts of the proposed discharge on toxicity and
temperature.
·
Conducting modeling to assess the near-field impact of the
discharge on dissolved oxygen levels.
·
Using Ecology’s new water quality model to assess the
far-field impacts of the discharge on algal growth and dissolved oxygen
levels.
·
Negotiating with the Phosphorus TAC to allow a new point
source discharge of phosphorus. Although the Long Lake Phosphorus
Management Agreement does not allow new point source discharges of
phosphorus, initial discussions with Ecology and the TAC indicate that
these groups would consider Spokane County as an existing discharger to
the river, not as a new discharger.
·
Conducting public information/public involvement efforts to
assure the public that the new discharge would not adversely impact
beneficial uses of the receiving water.
·
Gaining necessary permits for construction of the outfall,
including a Corps of Engineers 404 permit and a Shoreline Management
permit.
Facility Requirements and Cost
Assuming water quality criteria can be met, this alternative can handle
all Spokane County flow on a year-round basis. Facility requirements
primarily consist of an outfall pipeline and a multi-port diffuser.
Depending on the location and elevation of the treatment plant, effluent
pumping may be required. The estimated capital cost for this alternative
is presented in Table 5‑3.
Table
5‑3.
Capital Cost of Surface Discharge to Spokane River ($/MGY)
|
Cost Component 1 |
Gravity Discharge |
Pumped Discharge |
|
Incremental Treatment Cost/Savings |
$0 |
$0 |
|
Conveyance |
$190 |
$690 |
|
Site Development |
$0 |
$0 |
|
Land |
$0 |
$0 |
|
Total |
$190 |
$690 |
1. Alternative
can handle 8,000 MG/year (21.9 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Highly treated effluent can augment low streamflow during
the late summer, supporting fisheries and providing an environmental
benefit.
·
Surface water discharge facilities are simple to construct,
operate and maintain.
·
Anticipated water quality requirements for stream discharge
can be met with conventional treatment technologies.
·
The capital cost for an outfall is low.
Disadvantages
·
Surface water discharge does not maximize use of the
effluent as a water resource.
·
Depending on the results of the dissolved oxygen TMDL,
effluent quality requirements may be more restrictive than anticipated,
requiring higher treatment costs. Although unlikely, it is possible that
the allowable quantity of effluent discharged may be limited during
critical periods of receiving water quality.
·
Future regulatory changes may increase treatment
requirements and associated costs.
·
Siting a new outfall may encounter opposition from current
dischargers or other interest groups.
This alternative involves discharging treated effluent from the North
Spokane Service Area to the Little Spokane River below Dartford. Because
of the conveyance distance involved, the alternative does not include
sending flows from the Spokane Valley to a discharge point on the Little
Spokane River.
As shown in Figure 5-3, the stretch of river below Dartford is a gaining
reach, where the aquifer contributes to river flow. During critical summer
months, the estimated streamflow at Dartford is approximately 250 cfs
(personal conversation, Stan Miller). By comparison, the projected
effluent flow rate from the North Spokane Service Area in 2025 and 2050 is
8 and 9 cfs, respectively; or less than 4 percent of the summer
streamflow.
Applicability to Spokane County
The key considerations for locating a new outfall on the Little Spokane
River are the same as those for the Spokane River. As Figure 5-3 shows,
there are two existing discharges to the Little Spokane River, so
proximity to these discharges would be a consideration. In the stretch of
river below Dartford, potential impacts of a new outfall on the aquifer
would be minimal because the aquifer discharges to the river.
While there are portions of the Little Spokane River where declining flows
have been a concern in the past, these areas are upstream of Dartford and
therefore would not be positively impacted by the addition of treated
effluent (see later discussion of discharge to tributaries).
Effluent Quality Requirements
It is anticipated that effluent quality requirements for this alternative
would be similar to those for discharge to the Spokane River.
Implementation
Most key implementation considerations are the same as for discharge to
the Spokane River. The lower part of the Little Spokane River (from its
confluence with the Spokane River to River Mile 5) is a state-designated
wild and scenic river. While this designation does not carry the same
regulatory significance as a federal designation, there likely would be
some public opposition to any activities impacting the river in this
area. This may require additional mitigation.
Facility
Requirements and Cost
This alternative can handle flows from only the North Spokane Service
Area. Wastewater from the Spokane Valley must be handled by other means
such as discharge to the Spokane River.
Given the topography of the Little Spokane watershed, it has been assumed
that effluent from a new plant could be discharged by gravity. The
estimated unit cost is presented in Table 5‑4.
Table
5‑4.
Capital Cost of Surface Discharge to Little Spokane River
|
Cost Component1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$450 |
|
Site Development |
$0 |
|
Land |
$0 |
|
Total |
$450 |
1. Alternative
can handle 1,790 MG/year (4.9 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Key advantages listed for the Spokane River discharge option
apply to this alternative.
·
This concept returns the flows generated within the Little
Spokane watershed to the river rather than exporting them out of the
watershed.
·
Sending a portion of Spokane County’s effluent to the Little
Spokane River further spreads out the loading to the region’s receiving
waters, making greater use of assimilative capacity and reducing localized
impacts.
Disadvantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
This alternative handles only the flow generated in North
Spokane.
·
This alternative does not address the declining stream flows
experienced in the upper reaches of the Little Spokane River watershed.
·
Discharge to the Little Spokane River would likely encounter
opposition from local residents and environmental groups.
The concept of this alternative is to augment minimum streamflows in
smaller tributaries to augment beneficial uses such as fisheries, or to
offset declining streamflows due to overuse of surface withdrawals and
groundwater pumping.
Applicability to Spokane County
Three tributaries were identified as potential locations for augmenting
streamflow.
Latah Creek. As shown in Figure 5‑2, Latah Creek is one of
the closest tributaries to the planning area. There is little stream
gauging information for this tributary, however the estimated summer flow
in the stream is approximately 20-30 cfs (personal conversation, Stan
Miller). Because of insufficient data, further study would be required to
determine where an outfall should be located to augment streamflow and how
much effluent would be needed. During the alternatives workshop,
discharge to Latah Creek was discussed with staff from Ecology, the County
and the City. There was little support for the concept because no
significant environmental benefits were identified.
Crab Creek (Lincoln and Grant Counties). This concept was examined
as a streamflow augmentation option in the City of Spokane’s Facilities
Plan[i],
based on interest from Lincoln County, the State of Washington, and other
parties. Crab Creek is located approximately 15 miles west of Medical
Lake.
Upper Tributaries of the Little Spokane River. As mentioned
earlier, declining flows in the upper Little Spokane River basin have been
a concern. In 1975, water availability was of such concern that the major
tributaries of the Little Spokane River were closed to further water
appropriation, and water rights issued were conditioned to specific “base”
flows measured at Dartford. Continuing development of exempt wells
contributes to water shortages in the basin.
Effluent Quality Requirements
The majority of tributaries in the region are designated Class A streams,
and thus would be subject to the type of treatment illustrated in
Figure 5‑1. In discussions with the City regarding the potential Crab
Creek discharge, Ecology indicated that water quality requirements may be
relaxed somewhat if the streamflow augmentation project significantly
benefits water quality in a stream. However, this would need to be
evaluated on a case-by-case basis. For purposes of analysis, it is
assumed that the treatment train shown in Figure 5‑1 would be
required for discharge to any tributary.
Implementation
Implementation considerations would include those described for discharge
to the Spokane River. In addition, easements and right-of-ways would be
required for long conveyance pipelines. Studies would be required to
determine how much effluent could be sent to the tributaries during
various times of the year.
Facility Requirements and Cost
Depending on the carrying capacity of the tributary, this alternative may
not be able to handle all effluent generated by Spokane County. For the
purposes of this analysis, it has been assumed that one-half of the
wastewater generated by the County in 2025 could be discharged to
tributaries. The remaining flow must be discharged either to a major
stream or reused in some other manner.
Since the baseline treatment train would be used, the primary cost would
be associated with conveyance. With the exception of Latah Creek,
discharge to a tributary would require pumping treated effluent from 20-40
miles. Estimated costs are based on sending Spokane County’s flow through
a 20-mile pipeline. The estimated cost of this option is presented in
Table 5‑5.
Table
5‑5.
Capital Cost of Surface Discharge to Tributaries
|
Cost Component 1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$7,340 |
|
Site Development |
$0 |
|
Land |
$0 |
|
Total |
$7,340 |
1. Alternative can handle
4,000 MG/year (11 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
This concept could potentially enhance water resources in
the region by augmenting low streamflow or providing an alternative water
supply to groundwater.
·
This alternative spreads out loadings to receiving waters,
reducing localized water quality impacts.
Disadvantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
Requires significant infrastructure for conveyance.
·
Streamflow augmentation in tributaries may not be adequate
for all of the County’s flows, requiring an additional surface water
discharge to a major river.
·
Additional study would be necessary to determine whether
there is a true water quality or beneficial use benefit to augmenting
streamflow in the tributaries.
·
Discharging treated wastewater to tributaries may be opposed
by local property owners.

Figure 5‑4.
Irrigation of Agricultural Land
|
This alternative investigates the use of treated effluent for irrigation
of agricultural properties in Spokane County. Reclaimed water would be
used for irrigation on a seasonal basis to match crop demand. For the
remainder of the year, effluent would be discharged to surface water. The
concept is illustrated in Figure 5‑4.
Potential Reuse Locations
While development in the Spokane Valley has reduced the number of farms in
the County, many agricultural areas were protected through the growth
management practices outlined in the 1980 County Comprehensive Plan and
continued in the 2000 Draft Comprehensive Plan (Draft Comp Plan, 2000).
The Draft County Comprehensive Plan includes agricultural land in its
designation of Natural Resource lands, offering protection to “ensure
their viability for future generations” (Draft Comp Plan, Page NR-15).
According to the County’s Planning Department, protection of these natural
resource lands is anticipated to extend far into the future, well beyond
the horizon of either the current Comprehensive Plan or this Facilities
Plan.
Protected agricultural lands (based on zoning information from the Draft
Recommended Comprehensive Plan) are shown in Figure 1‑5. The five
primary areas have been numbered for later use in reuse demand analyses.
This figure also shows the total acreage for each area, and the boundaries
of the Draft Urban Growth Area (in black) and the Aquifer Sensitive Area
(in red).


When
evaluating agricultural reuse in these areas, there are several issues
that need to be considered:
·
Within the agricultural land designation, the County
identifies “large tract” (one residential unit per 40 acres) and “small
tract” (one residential unit per 10 acres) agricultural properties that
have long-term commercial significance. The large tract properties are
more attractive for an effluent reuse program because they result in fewer
contracts with farmers, require fewer metering points and are more likely
to remain in agricultural use on a long-term basis.
·
Much
of the southern portion of Area 5 is being converted to small ranchettes,
and the recent construction of a new high school will promote further
development. Based on this development pattern, any agricultural demand in
Area 5 is likely to be associated with small-scale farming operations.
·
Although not in a protected agricultural area, there are
existing farms in the Chattaroy area along the Little Spokane River east
of Area 4 (see Table 5‑6). Providing reuse water for irrigation in
this area would offset the surface water or groundwater impacts of
existing irrigation withdrawals. Local topography favors sending reuse
water from the planning area to the Chattaroy area.
·
Many of the potential reuse locations in all areas would
require pumping to higher elevations. For example, there are potential
reuse sites in the Green Bluff area (northern portion of Area 5); however,
reaching these locations would require pumping to an elevation of
approximately 2,400 feet.
Estimates of Demand Potential
David Bezdicek of Washington State University provided guidelines
regarding evaporative demand for representative crops grown in the
designated agricultural areas. These irrigation requirements (shown in
Figure 5-5) take into account monthly precipitation, as
well as the impacts of agricultural management practices (harvesting,
planting, etc.) that reduce the full evaporative demand.
For purposes of evaluation, the estimated demand for water has been based
on a blend of grain, wheat, alfalfa and pasture production. This provides
a representative mix of cropping patterns that may occur in the region.
To maximize water use, particularly in September and October, it would be
best to maximize use of pasture crops. However, this may not be
economically attractive to farmers.
Figure
5‑6.
Net Irrigation Requirement for Crops in Spokane County
To determine the volume of water demand for each of the designated
agricultural areas, the following assumptions were applied to the data
shown in Figure 5-6:
·
60% of the total land in the protected agricultural areas
would be available for crop production.
·
Irrigation with treated effluent would begin the last week
of April and continue through the end of September (October demand is
minimal).
·
Monthly irrigation demand is spread evenly over all days of
the month.
Based on these assumptions, Table 5‑6 shows the total irrigation
demand for each of the five designated agricultural areas. By comparison,
the average effluent production rate in 2025 and 2050 is projected to be
22 and 27 mgd, respectively.
Table
5‑6.
Irrigation Demand for Designated Agricultural Areas
|
|
|
Demand (mgd) for Designated Agricultural Area1 |
|
Month |
gal/d/acre |
1 |
2 |
3 |
4 |
5 |
|
January |
0 |
0 |
0 |
0 |
0 |
0 |
|
February |
0 |
0 |
0 |
0 |
0 |
0 |
|
March |
0 |
0 |
0 |
0 |
0 |
0 |
|
April |
1,560 |
60 |
210 |
11 |
31 |
18 |
|
May |
2,590 |
100 |
360 |
17 |
53 |
31 |
|
June |
4,860 |
190 |
670 |
33 |
100 |
58 |
|
July |
6,560 |
250 |
900 |
45 |
130 |
77 |
|
August |
3,080 |
120 |
420 |
22 |
63 |
36 |
|
September |
1,540 |
60 |
210 |
11 |
31 |
18 |
|
October |
90 |
0 |
0 |
0 |
0 |
0 |
|
November |
0 |
0 |
0 |
0 |
0 |
0 |
|
December |
0 |
0 |
0 |
0 |
0 |
0 |
1. See
Figure 5-5 for location of designated agricultural areas.
Based on the estimates of reuse demand shown in Table 5‑6, there is
sufficient potential demand in Areas 1, 2, 4 and 5 to handle all effluent
production from April through September for the year 2025. Area 3 could
handle all of the effluent in May through August, and most of the effluent
during April and September. Reuse demand in October would be minimal in
all areas.
Interest Level of Potential End Users
A targeted survey of farmers in the region was not conducted as part of
this project. The City of Spokane’s 1999 Facilities Plan also investigated
agricultural reuse as an effluent management option; however, no
investigations were made into the potential interest of regional farmers.
Issues that have been raised by farmers during other feasibility studies
of agricultural reuse in Northwest communities include:
·
Cost. For farmers with existing water supply, there
must be an economic incentive to switch to reuse.
·
Adequacy/availability of current water supply.
Interest is typically higher among farmers that lack adequate irrigation
water.
·
Water quality. Farmers value the nutrient content of
the reclaimed water but are concerned about other parameters that could
impact their crops such as salinity, chlorine or metals.
·
Food Processors. Farmers are concerned about the
reaction of the food processing industry to irrigation with treated
effluent.
·
Water Pressure. Various irrigation systems have
differing pressure requirements for operation. For example, “big gun”
irrigation systems require significantly higher pressure than most
irrigation methods. Farmers would prefer the reuse delivery pressure to be
adequate to operate their preferred irrigation equipment.
·
Reluctance to dedicate land for long-term agricultural
uses. Although the areas investigated for this study are protected for
long-term agricultural use, current owners may perceive a reduction in
value if they feel long-term agreements or use of reclaimed water could
complicate their ability to convert their property to other uses in the
future.
·
Regulation. Use of reuse water brings with it an
added set of regulatory requirements that farmers must comply with.
Based on the results of other feasibility studies for agricultural reuse,
it is clear that farmers would not be willing to pay the true cost to
deliver the reuse water to their sites. At best, they would be willing to
a price equivalent to that for other irrigation water supplies in the
region. Since this represents only a fraction of the true costs to supply
the water, an agricultural reuse program would need to be heavily
subsidized by the wastewater utility.
Water Resource Implications
The optimal locations for agricultural reuse are in areas where treated
effluent could replace existing surface water or groundwater withdrawals.
Effluent also could serve as a new source of water in areas that have no
water supply. This is attractive from the perspective of increasing the
value of the land; however, it does not free up other water supplies for
alternative use.

Figure 5‑7.
Timing of River Flow and Irrigation Demand
|
A large-scale agricultural reuse program could reduce or eliminate the
need for surface water discharge during much of the summer; however,
irrigation demand in September and October may be insufficient to use all
of the effluent. Figure 5‑7 compares the month-by-month trends for
streamflow in the Spokane River and irrigation demand, and shows that
river flows remain low after the irrigation demand sharply decreases.
Consequently, during the late summer and early fall, effluent would need
to be discharged to receiving waters, necessitating high levels of
nutrient removal.
Effluent quality requirements for agricultural reuse are set forth in
Washington’s Water Reclamation and Reuse Standards
[ii], and were
summarized in Chapter 4 of the Final Basis of Planning Report. The
reuse rules allow various qualities of reclaimed water to be used for
agricultural irrigation, depending on the crop to be grown, the irrigation
method, setback provisions and other considerations. Since the specific
types and uses of potential crops are not known at this time, it has been
assumed that effluent must be treated to Class A reuse standards, allowing
it to be used for the greatest variety of crops and with the least
restrictions on the end-user. This quality of water would have the
greatest appeal to farmers.
Class A water has more stringent disinfection requirements than the
effluent parameters listed in Table 5‑2 for surface water
discharge. However, the treatment process shown in Figure 5‑1
would be capable of meeting these tougher standards. Because some
nutrient loading is beneficial to crops, it may be possible to reduce the
amount of ammonia-nitrogen and phosphorus removal that must be provided at
the County’s treatment facility during the summer.
While there are no specific guidelines for reuse over the aquifer in
Washington, the Idaho Division of Environmental Quality developed the
Special Supplemental Guidelines for Spokane Valley-Rathdrum Prairie
Aquifer Wastewater Land Application (1995)
[iii] to provide
direction for a land application project for the Hayden Area Regional
Sewer Board (HARSB) in Idaho. These guidelines recommend that both
hydraulic application and nitrate-nitrogen loading be limited to amounts
required for crop uptake. As a general guideline, it has been assumed that
nitrate concentrations would need to be reduced to less than 10 mg/L for
large-scale agricultural irrigation over the aquifer.
Reclaimed water programs are administered jointly by the Departments of
Ecology and Health, with irrigation programs permitted through Ecology.
As part of the regulatory review process, the wastewater utility must
complete an Engineering Report that describes the design and operation of
the proposed program and indicates the means of compliance with all
applicable standards and regulations.
Other key implementation steps would include:
·
Conducting a needs survey/feasibility study to define
potential demand and end-user requirements.
·
Developing long-term agreements with private farmers or
purchasing sufficient land to meet the program requirements.
·
Developing an organizational structure to manage the reuse
program.
·
Siting and permitting critical infrastructure components
such as reservoirs and pipelines.
·
Preparing predesign and detailed design for all facilities.
·
Conducting environmental assessments necessary to meet
regulatory requirements.
·
Developing operational plans, including reliability and
emergency response measures.
·
Developing and implementing monitoring plans.
·
Implementing a comprehensive public education program.
The choice between purchasing land for irrigation or developing long-term
agreements with private farmers is a key consideration. The first option
would give the County more control over the long-term use of water and
crop selection for agricultural areas. On the other hand, it would
require greater capital expense, add the administrative task to develop
and maintain the lease relationship, and may encounter opposition from
individuals opposed to the County’s purchase of large tracts of farmland.
Developing long-term agreements would require that the farmer be committed
to long-term agriculture. It also may require two separate negotiations
(with the owner and the leaser) if the property is privately owned and
leased to a private farmer.
Another key decision is whether the County would operate the reuse system
or partner with a local water purveyor for this service.
The requirements described below are based on a system configuration that
includes pumping of treated effluent to one or more reservoirs located
near the various reuse areas, and subsequent pumping through a
distribution system to serve agricultural customers. There are four major
components to this system: treatment, transmission, storage and
distribution.
Treatment
To produce Class A reclaimed water, the required treatment train would be
equivalent to that presented in Figure 5‑1; however, the reuse
standards specify additional reliability and redundancy components that
must be incorporated into the treatment plant.
Transmission
Transmission distances to the designated agricultural areas vary widely.
Serving Area 5 would require pipeline lengths of 6 to 8 miles from a North
Spokane Plant and 8 to 12 miles from a plant located in the Spokane
Valley. Pumping from the North Spokane area to Area 4 would require
approximately 15 miles of transmission line. Transmission distances to
Areas 3, 1, and 2 increase to 25 miles, 30 miles, and over 40 miles,
respectively.
To the extent possible, transmission lines would be located in public
right of way. For purposes of this analysis, it is assumed that the County
would not need to pay to acquire any property or easements for reuse
transmission.
Storage
There are two options for storage: provide storage to meet all seasonal
irrigation demands, or provide irrigation water “on demand” with limited
local storage to meet peak demands.
To maximize reuse of treated effluent, it would be necessary to provide
storage during the early spring in order to meet the peak demand of June
and July. Storage volume requirements were calculated based on annual
average 2025 flows and 5,000 total acres of land application area. With
this demand, the excess flow produced in April and May at 2025 flow rates
would be sufficient to make up the deficit in wastewater flows through
June, July and August, resulting in no excess storage during the
non-irrigating period (late August through mid-April). This allows the
County to avoid adverse impacts due to long-term storage. Experience
shows that issues such as algal growth and odor generation can lead to
serious water quality degradation if reclaimed water is stored for long
periods without major reservoir maintenance efforts. The total storage
volume required at 2025 flows would be 400 million gallons. Initial
requirements, based on 2005 flow rates, would be 2,400 acres of land under
irrigation and a reservoir capacity of 200 million gallons.
For “on demand” application, detailed discussions with farmers would be
required to determine the daily peaking factor appropriate for sizing
storage. Initial estimates of facility requirements are based on two days
of storage.
Any storage reservoirs located over a potable water aquifer would need to
be lined.
Distribution
Most irrigation systems can be categorized as medium pressure (50-60 psi)
or high pressure (100-125 psi). Medium pressure systems include center
pivot, lateral move, and solid set irrigation, whereas high pressure
systems are needed for “big gun” irrigation. If the County were to
implement agricultural reuse, it would make sense to provide a medium
pressure system, with individual farmers providing booster stations as
needed for “big gun” equipment.
Cost
The estimated cost of this alternative is presented in Table 5‑7.
This cost is based on conveyance of all flow from April through September
to a storage reservoir located 14 miles from the treatment plant, and
distribution to multiple farms with an average size of 450 acres.
Table
5‑7.
Capital Cost of Agricultural Reuse
|
Cost Component 1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$8,600 |
|
Site Development (reservoirs) |
$5,900 |
|
Land |
$200 |
|
Total |
$14,900 |
1. Alternative
can handle 4,000 MG/year (21.9 mgd for six months)
Advantages
·
Effluent reuse can have significant water resource benefits
where irrigation water is currently obtained from surface water or
groundwater resources. It would conserve and stretch potable water
supplies
·
For agricultural property without a water supply, a reuse
program would increase crop yields and property value.
·
Implementing a reuse program could reduce or eliminate
discharge to surface waters during the spring and mid-summer months.
Disadvantages
·
During October and possibly September, irrigation demand
would not be sufficient to use all of the County’s effluent.
Consequently, treated effluent would need to be discharged to the river
during low streamflow conditions unless other effluent management
strategies were implemented for this period.
·
Effluent storage reservoirs may prove difficult to site and
permit.
·
Infrastructure development costs are high.
·
Operational costs for pumping would be high.
·
This concept requires long-term agreements with farmers or
purchase of large tracts of agricultural property. Both options may be
difficult to implement.
·
This alternative has risk associated with changing land
use. However, applying effluent to agricultural areas that have been
protected through the County’s comprehensive planning and zoning process
would reduce the risk that land will not be available for long-term
effluent reuse.
·
Local water purveyors may view this new water supply as
competition that could reduce their revenue.
·
Revenue from sale of the water would pay for only a fraction
of the development and operating costs. Consequently, wastewater
ratepayers would need to subsidize to program.
This alternative involves a variation of agricultural reuse in which
hybrid poplars would be grown. From an effluent management perspective,
poplars are attractive because they have a high water demand. Also, the
harvested poplars may produce revenue for the wastewater utility.
The use of poplars is an emerging management practice for municipal
wastewater. In the Northwest, several communities are in various stages
of implementation. The most established program is in Woodburn, Oregon
where poplars have been grown for the past seven years.
Applicability to Spokane County
In the Spokane climate, poplars would have an estimated water consumption
rate of 5 feet per year. If this water were applied over the six-month
summer permit season, the required area of trees under irrigation would be
2,400 acres in 2025 and 3,000 acres in 2050. Taking into consideration
buffers, harvesting requirements and other property management functions,
the total property requirements would increase about 50 percent to 3,600
and 4,500 acres in 2025 and 2050, respectively. To maintain control of
the irrigation and harvesting operations, the County would need to
purchase the property and operate the facility.
With such a large land requirement, the cost of this alternative becomes
highly dependent on the cost of land and the length of conveyance
pipelines to deliver the water. Two scenarios were considered:
·
A site in Peone Prairie located within 7 miles of the
treatment plant. Estimated property costs in this area would be $10,000
per acre.
·
A site in the Palouse, located 20 miles from the treatment
plant. Property costs in this area are based on $2,000 per acre.
Effluent Quality Requirements
Poplars may be irrigated with Class C reclaimed water, which requires
secondary treatment and effective disinfection. Since the poplar farm
would only receive water during the six dry-season months, effluent would
need to be discharged to a receiving water during the winter. This would
require the ability to provide nitrification during cold weather
conditions to meet in-stream toxicity limits for ammonia.
Implementation
Implementation requirements would be similar to that for agricultural
irrigation with the exception that market surveys and long-term agreements
with farmers would not be needed. Instead, the County would need to
identify and acquire the large tracts of land needed for the poplar
system.
Facility Requirements and Cost
Key facility requirements for a poplar system are outlined below:
·
Treatment plant – advanced secondary treatment with
nitrification (for winter discharge condition.
·
Effluent pumping – a high head lift station would be needed
to convey the effluent to the irrigation site.
·
Transmission main – depending on the site location, a 7 to
20 mile pipeline would be required.
·
Storage – a minimum of two days of operational storage
should be provided to balance supply and demand variations and to
accommodate emergency situations.
·
Site development – the property would need to be prepared
for growth of poplar trees, including clearing and grading, construction
of access roads, installation of surface runoff controls, and installation
of groundwater monitoring wells.
·
Irrigation system – a mechanical irrigation system would
need to be installed.
The estimated unit capital cost is shown in Table 5‑8 for both the
Peone Prairie and Palouse sites. Compared to the baseline treatment
system, elimination of effluent filtration and phosphorus removal is
projected to save approximately $1.50 per gallon of capacity. This
savings is offset by the other development costs for the system.
The potential revenue from a poplar operation is highly speculative.
Initially, poplars were thought to provide a quality source of pulp for
paper mills; however, the acceptance of the poplar pulp has been mixed and
the revenue generated small. Lately, interest has grown in the use of
poplars as a clear softwood for non-structural products, such as blinds.
The market value and demand potential for these products may be
significant, but this has not been firmly established. If such a market
exists, it is likely that the commercial wood products industry would grow
poplars in sufficient quantity to satisfy the demand. In such a market
place, a small to mid-size municipal utility would be a very small player
with limited market access and pricing leverage. For these reasons, no
revenue stream has been included for harvested poplars.
Table
5‑8.
Capital Cost of Poplar Farms
|
Cost Component 1 |
Cost, dollars per million gallon per Year |
|
Peone Prairie |
Palouse |
|
Incremental Treatment Cost/Savings |
-$8,200 |
-$8,200 |
|
Conveyance |
$5,400 |
$11,500 |
|
Site Development (reservoir, irrigation, etc.) |
$1,900 |
$1,900 |
|
Land |
$6,000 |
$1,200 |
|
Total |
$5,100 |
$6,400 |
1. Alternative can
handle 4,000 MG/year (21.9 mgd for six months)
Advantages and Disadvantages
Advantages
·
Eliminates discharge to receiving waters during the
dry-season.
·
Harvested poplars may generate revenue, although this
remains uncertain.
·
Growth of poplars may be positively viewed by the public and
regulatory agencies as a “green solution” to wastewater management.
·
Allows use of a less complex, less expensive treatment
system.
Disadvantages
·
Requires purchase of large tracts of agricultural land. The
agricultural community and other land use interests may view this
unfavorably.
·
Operational costs for pumping would be high.
·
Results in a more complex system to operate than river
discharge.
Urban reuse involves the use of treated effluent as an irrigation supply
for golf courses, school grounds, parks, and cemeteries. Reuse would be
during the summer months only, when irrigation demand is highest. The
basic concept of the program is illustrated in Figure 5‑8.

Figure 5‑8.
Irrigation of Urban Green spaces
|
Urban irrigation using treated effluent has been practiced for decades
across the nation and in the Northwest. In Oregon, the Unified Sewerage
Agency of Washington County has been irrigating school grounds and golf
courses with treated effluent for over 20 years. In Washington, urban
irrigation was included in several demonstration projects administered by
the Departments of Ecology and Health
[iv]. Treated
wastewater effluent is used for landscape irrigation by the City of
Sequim, and for irrigation at local churches, city parks, and a private
residence in the City of Yelm.
Location of Potential Reuse
Sites
Using the County’s land use information system, an investigation was
conducted to identify green space that could potentially be included in an
urban irrigation program. In the Spokane area, the most significant green
space are those associated with golf courses, parks, cemeteries and
schoolyards. Figure 5‑9 presents the location of these facilities
in the greater Spokane region. Appendix C,
consists of tables showing all of the parks, cemeteries, and schools
included for evaluation.
Figure
5‑9. Potential
Urban Irrigation Sites
Golf courses are typically the most attractive reuse customers because of
their large water demand. Areas with multiple golf courses include
Liberty Lake, along the Little Spokane River in North Spokane, near Latah
Creek at the south end of the City, and along the Spokane River near the
western boundary of the City.
In some communities, green space at industrial parks offer important reuse
opportunities. Based on discussions with County personnel, industrial
campuses with significant green space are limited to the Liberty Lake
area.
To initially screen candidate reuse sites, two criteria were used:
·
Proximity to the planning area
·
Complexity vs. benefit of administering reuse program
The first criterion was used to rule out sites such as the Sundance and
Fairways Golf Courses (located 15-20 miles from the planning area). The
second criterion was used to eliminate sites with small demand potential
such as individual schools with a single private owner.
Potential Reuse Demand
Demand for urban irrigation water was assessed similar to that for
agricultural irrigation, except that demand was based on turf requirements
rather than a mixture of crops. Urban irrigation demand in gallons per day
per acre is shown in Figure 5‑10.
|

Figure 5‑10.
Water demand for Urban Irrigation |
To put the potential demand in perspective, a typical 150-acre golf course
would have a maximum demand in August of 900,000 gpd, which represents 4
percent of the County’s projected effluent flow rate in 2025. During other
summer months, a smaller portion of the effluent would be used. Extending
this concept, Table 5‑9 illustrates the relationship between the
size of a reuse site and the percentage of the total County flow that can
be used on the site. As this table illustrates, many large sites or
clusters of smaller sites would be needed to use a substantial portion of
the County’s projected flow in 2025. As shown in Figure 5-9, potential
reuse sites are highly dispersed with few clusters of sizeable acreage.
Consequently, achieving a large volume of demand would require an
extensive distribution network.
Table
5‑9.
Urban Irrigation Reuse Potential
|
|
Peak Demand (as a percentage of projected
Annual Average flow) |
|
|
Year |
10 Acre Site |
20 Acre Site |
50 Acre Site |
100 Acre Site |
|
2000 |
1.00 |
2.00 |
5.00 |
10.00 |
|
2005 |
0.62 |
1.24 |
3.10 |
6.20 |
|
2010 |
0.45 |
0.90 |
2.25 |
5.50 |
|
2015 |
0.34 |
0.68 |
1.70 |
3.40 |
|
2020 |
0.31 |
0.62 |
1.55 |
3.10 |
|
2025 |
0.30 |
0.60 |
1.50 |
3.00 |
|
2030 |
0.28 |
0.56 |
1.40 |
2.80 |
|
2035 |
0.27 |
0.54 |
1.35 |
2.70 |
|
2040 |
0.26 |
0.52 |
1.30 |
2.60 |
|
2045 |
0.25 |
0.50 |
1.25 |
2.50 |
|
2050 |
0.24 |
0.48 |
1.20 |
2.40 |
| |
|
|
|
|
|
|
Golf Courses
Fourteen golf courses were evaluated as potential urban reuse sites. These
are shown in Table 5‑10. Ninety-eight percent of the total golf
course area is assumed to be irrigable.
Table
5‑10.
Urban Golf Course Sites
|
Name |
Total Acres |
Irrigable Acres |
|
Indian Canyon Golf Course |
210 |
205 |
|
Spokane Country Club |
188 |
184 |
|
Hangman Valley Golf Course |
174 |
171 |
|
Esmeralda Golf Course |
165 |
162 |
|
Wandermere Golf Course |
159 |
156 |
|
Downriver Golf Course |
158 |
155 |
|
Manito Golf Club |
139 |
136 |
|
The Creek at Qualchan Golf Course |
138 |
135 |
|
MeadowWood Golf Course |
144 |
141 |
|
Liberty Lake Golf Course |
125 |
123 |
|
Painted Hills Golf Course |
89 |
87 |
|
Sundance Golf Course Inc. |
87 |
85 |
|
Valley View Golf Course |
61 |
60 |
|
TOTAL |
2,046 |
2,005 |
To evaluate the geographical distribution of reuse demand from golf
courses, the courses listed in Table 5‑10 were separated into six
regions:
·
North Spokane: Wandermere
·
East County: Valley View, Liberty Lake, MeadowWood
·
South Spokane: Manito, The Creek at Qualchan
·
Central Spokane: Indian Canyon, Downriver
·
Esmeralda
·
Painted Hills
The projected reuse demand for the golf courses within each region is
presented in Table 5‑11.
The Spokane Country Club was excluded from the demand projections based
upon discussions with a representative from the club, who indicated that
they irrigate using water from a private well, have very low irrigation
costs, and are not likely to consider replacing this source with treated
effluent.
The County Parks department would be willing to use reclaimed effluent for
irrigation of County-owned golf courses; however, two of their courses
(Liberty Lake and MeadowWood) are located in an area that is being annexed
by Liberty Lake and is within the Liberty Lake Water and Sewer District.
The County could implement reuse for irrigation of these courses if it
maintains ownership of them; however, the Liberty Lake Water and Sewer
District may also be interested in irrigating these courses if it has
trouble expanding its discharge to the Spokane River.
Table
5‑11.
Monthly Irrigation Demand for Golf Courses
1.
Alternative can handle 440 MG/year (1.2 mgd year-round)
2.
Alternative can handle 1,570 MG/year (4.3 mgd year-round)
Key Advantages and Disadvantages
Advantages
·
Potentially high-volume, year-round use.
·
Would replace a significant groundwater withdrawal.
·
Would reduce total volume of effluent discharged to Spokane
River.
·
May foster opportunities for the County and IEP to share
other wastewater management functions.
Disadvantages
·
There is risk that the industry may leave the area, change
operation or otherwise change in ways that would preclude or reduce the
ability to reuse the County’s effluent.
·
Depending on the implementation cost, and the willingness of
the industry to participate in the costs, this alternative may need to be
subsidized by the wastewater utility.
·
If there is any concern among customers of the industry that
using treated effluent as part of the industrial process could compromise
the quality of the product, then industrial reuse would not be successful.
·
Since the County’s reuse water would end up in the
industries discharge, this may create liability for the County in the
event the industry experiences compliance problems.
Treated effluent could be used to create constructed mitigation wetlands
or as a reliable water source to restore degraded natural wetlands.
Several of the State’s reuse demonstration projects have included
discharge of treated effluent to constructed wetlands, including projects
in Sequim (in Clallam County) and Yelm (in Thurston County).
Washington’s reuse standards dictate the wetted wetland area required for
a given volume of reclaimed water discharge based on both hydraulic
loading and water level. The criteria for constructed wetlands are:
·
Maximum annual average hydraulic loading rate of 5 cm/day
(calculated as the ratio of average annual flow rate of reclaimed water to
the effective wetted area of the wetland).
·
Average monthly water level elevations under the reclaimed
water wetland hydrologic regime are not to increase by more than 10 cm
compared to the average pre-augmentation monthly water level.

Figure 5‑15.
Acreage of Wetted Surface Area Needed to Accommodate All Spokane
County Flow
|
Based on annual average hydraulic loading, Figure 5‑15 shows the
acreage of wetted surface area that would be required to handle all
projected flow generated by Spokane County between 2000 and 2050. Taking
into consideration buffer requirements, actual land requirements would be
approximately 50 percent greater than those in the figure.
According to a wetland inventory conducted for Spokane County in 1991, the
majority of natural wetlands are located in the western and southwestern
portions of the county, and along the lower portion of the Little Spokane
River. This was illustrated in Drawing 2-9 of the Basis of Planning
Report. In the Spokane Valley, there are few wetlands due to the
permeable nature of the soils. Given this situation, developing wetlands
of the magnitude listed in Figure 5‑15 would be problematic. The
wetlands would need to be spread out over long distances, and conveyance
costs would be high. Consequently, the discussion of wetlands has been
limited to creation of small to mid-size faculties that could use a
portion of the effluent generated by the County.
Depending on their location and potential interaction with potable water
aquifers, created wetlands systems may need to be lined. Lining would
likely be required for wetlands located away from stream corridors in
locations underlain by porous soils. Unlined wetlands may be acceptable
along gaining stretches of the river where the water is allowed to
infiltrate and move laterally to the surface water. Unfortunately, in
Spokane, many locations where such systems could occur are already
developed. However, there maybe opportunities to site smaller wetlands
along the River in areas of where shoreline setback requirements make the
property immediately adjacent to the River undevelopable. Other potential
sites would be along the Little Spokane River north of the North Spokane
region (see Figure 5‑1). Most of the Little Spokane River is
recharged from the Aquifer in this area, so unless there are drinking
water wells located between the wetlands site and the river, the risk of
impacting water quality in a subsurface aquifer is minimal. Such a site
would be conveniently located for discharge from a plant in the North
Spokane area, but would require pumping effluent 12-15 miles from a plant
in the Valley.
Treated effluent provides a reliable water supply for restoring degraded
wetlands, so there may be some opportunities for the County to partner
with the Department of Fish and Wildlife to restore natural wetlands. This
alternative would not significantly impact the need for or size of the
primary effluent disposal facilities (surface water discharge), but it
would provide an opportunity to enhance natural resources in the area.
A final implementation option would be to locate constructed wetlands near
Shelly Lake in the South Valley region. According to the County, this
water body was once a stream-fed, but flows to the lake have decreased as
the area became developed. Currently, a developer of homes near the lake
pumps water to the lake during the summer to maintain the lake level. The
quantity of water added to the lake is not known, nor have specific
developments around the lake been evaluated to determine how much land may
be available for constructed wetlands. Since the lake bottom sits 30 feet
above the Spokane Aquifer, infiltration to the Aquifer would be a concern.
Effluent Quality Requirements
The Washington reuse standards establish conditions under which reclaimed
water may be used to create wetlands. Since constructed wetlands that
receive reclaimed water are considered waters of the State, the
requirements of constructed wetlands are dictated by the anticipated
beneficial use. To minimize public concern, it is assumed that any
constructed wetlands would be designed for potential human contact. This
means that the treated effluent would need to meet Class A treatment
standards, as well as the following specific standards from the reuse
guidelines:
·
BOD5 and TSS less than 20 mg/L (annual average)
·
Total Kjeldahl nitrogen less than 3 mg/L (annual average)
·
Total phosphorus less than 1 mg/L (annual average)
·
Un-ionized ammonia less than Washington’s chronic toxicity
standards
·
Metals concentrations less than Washington’s surface water
standards
These standards require a higher level of treatment than that provided by
the treatment train in Figure 5‑1. Specifically, year-round
phosphorus removal and complete denitrification would be required.
In addition to meeting these specific criteria, a hydrogeologic evaluation
must be conducted to determine whether the wetland is in an area that
provides groundwater recharge. If this is the case, then reclaimed water
discharged to the wetland must “exhibit parameter concentrations 50
percent or lower than the ground water quality criteria”, or must
demonstrate that local ground water quality will not be degraded.
Implementation
For approval of reclaimed water use in wetlands, the County would need to
perform sufficient background studies to:
·
Identify beneficial uses to be attained
·
Determine the hydrologic regime of the proposed systems
·
Identify the water quality to be provided and the annual
loading rates
·
Determine potential groundwater impacts
·
Provide an estimated description of the mature biological
structure for the wetland
·
Support any claims of net environmental benefit
Other implementation steps would include:
·
Property acquisition
·
Predesign and design
·
Conducting environmental assessments necessary to meet
regulatory requirements
·
Developing and implementing monitoring plans
·
Implementing a public education program
Facility Requirements and Cost
Preliminary development of facility requirements and cost are based on
creation of 40 acres of wetlands to handle 2 mgd of flow. Costs include
conveyance (estimated at 10 miles), construction of a lined wetland, land
acquisition, additional treatment to meet the annual phosphorus and TKN
requirement. Table 5‑15 summarizes the projected capital cost for
this alternative.
Table
5‑15.
Capital Cost of Wetlands Creation
|
Cost Component 1 |
Unit Cost ($/MGY) |
|
Incremental Treatment Cost/Savings |
$2,700 |
|
Conveyance |
$7,100 |
|
Site Development |
$6,400 |
|
Land |
$1,100 |
|
Total |
$17,900 |
1. Alternative can
handle 730 MG/year (2 mgd year-round)
Key Advantages and Disadvantages
Advantages
·
Constructed wetlands would improve natural conditions in the
County by providing additional wildlife habitat and creating additional
natural area.
·
Degraded wetlands may be improved through addition of
treated effluent.
Disadvantages
·
Insufficient sites are available to create a large water
demand.
·
Regulatory restrictions addressing aquifer impact would
require most wetlands systems to be lined, increasing costs.
·
Wetlands systems create additional operational complexity
and maintenance requirements.
·
Mosquito generation is a potential problem with some
wetlands systems.
·
There may be localized public opposition to creation of
wetlands using treated wastewater.
Groundwater recharge is the use of treated effluent to supplement natural
water supply in subsurface aquifers. This practice has been used for
decades in the arid Southwest, and has recently become more common
throughout the United States. One of the largest and best-known facilities
– Water Factory 21 in Orange County, California – began using its 15-mgd
reclamation facility in 1976 to replenish the local aquifer that serves
nearly 2 million residents. Through development of Washington’s Water
Reclamation and Reuse Standards, the Departments of Health and Ecology
established guidelines for recharge of both potable water and nonpotable
water aquifers using treated effluent. Three demonstration projects in
Washington, including two in Grant County are currently using reclaimed
water for aquifer recharge. Four other projects in Washington are in
various stages of planning, design, and construction.
Nearly all of the planning area lies over the Spokane Aquifer, with four
other aquifers nearby or adjacent to the planning area (Little Spokane
River Aquifer, Green Bluff Aquifer, Peone Prairie Aquifer, and
Orchard-Pleasant Prairie Aquifer). All of these aquifers are used for
potable water supply. Drawing 2-4 in the Basis of Planning Report
shows the locations of all aquifers in the County.

Figure 5‑16.
Schematic of Surface Percolation System
|
Groundwater recharge is allowed through both surface percolation and
direct injection. With surface percolation, treated effluent would be
stored in an infiltration lagoon and allowed to seep into the aquifer
through natural percolation. This concept takes advantage of the soil as a
treatment system to produce a water that meets all drinking water and
groundwater quality requirements by the time it reaches the groundwater
beneath or down gradient of the recharge site. Figure 5‑16
illustrates this concept.
With direct injection, groundwater is pumped directly into the aquifer
through injection wells. Since treatment is not provided through the
soil, the injected water must meet all drinking water and groundwater
quality requirements. Figure 5‑17 presents a schematic of the
system.

Figure 5‑17.
Schematic of Direct Injection System
|
Two key guidelines in the Reuse Standards determine potential locations
for infiltration ponds or injection wells in potable water aquifers:
·
Reclaimed water shall be retained underground for a minimum
of 12 months prior to being withdrawn as a source of drinking water
supply.
·
The minimum horizontal separation distance between the point
of direct recharge and withdrawal as a source of drinking water supply
shall be 2,000 feet.
Figure 5‑18 shows the locations of aquifers in the Spokane County
area, and the locations of wells in the Spokane Aquifer (as cataloged by
the County). The figure also illustrates required separation based on the
two criteria given above:
·
The circle illustrates a 2000-foot radius from a given well
location.
·
The oval shows the wellhead protection area associated with
a 1-year time of travel. This figure was derived from the City’s Wellhead
Protection Program Phase I Technical Assessment Report (CH2M Hill, 1998).
Given the rapid movement of the Spokane Aquifer, the 1-year residence
criterion requires a large separation distance between a recharge location
and withdrawal well.
The separation criteria, combined with the large number of wells in the
aquifer, severely limits locations where groundwater recharge facilities
could be sited. More detailed study of the aquifer would be required to
determine if feasible locations are available. One potential approach for
the County would be to acquire enough existing wells to create the
separation distances established in the rules. Obviously, an alternative
water source would need to be provided to users of these wells.
Alternatively, groundwater recharge could be practiced in one of the other
local aquifers where there is less development and less rapid groundwater
movement.
Figure
5‑18. Aquifer
and Well Locations
Effluent Quality Requirements
Minimum effluent quality requirements for surface percolation are
addressed in the general requirements of the State’s reuse standards.
These rules specify Class A reclaimed water quality plus nitrogen
removal. However, the combination of the wastewater treatment plant and
the soil treatment provided in the vadose (unsaturated) zone must produce
a water quality meeting both drinking water and groundwater quality
requirements. By so doing, the total system ensures that “reclaimed water
used for groundwater recharge shall be at all times of a quality that
fully protects public health and the water quality of waters of the
state.” Given the porous nature of the sand and gravel soils in the study
area, it seems unlikely that a significant level of soil treatment would
occur before the recharged water reaches the groundwater table. Therefore,
it has been assumed that the water introduced to the percolation ponds
must meet both drinking water and groundwater quality requirements.
For groundwater injection, the rules establish both water quality limits
and specify a treatment technique. The treated water must comply with
dinking water standards plus the following limits:
·
Turbidity less than 1 NTU (average) and 0.5 NTU (average)
·
Total nitrogen less than 10 mg/L as N
·
TOC less than 1.0 mg/L
·
Other constituent limits deemed appropriate by Departments
of Ecology or Health
The treatment requirements specify a Class A treatment train plus reverse
osmosis.
Implementation
For a groundwater recharge project, an Engineering Report must be prepared
that provides a complete hydrogeologic characterization of the project
site. Specific requirements of this report are specified in the State’s
reuse rules.
More importantly, implementation of groundwater recharge will require
public support. To achieve this, the County will need to implement a
comprehensive, long-term public education program to clearly define the
benefits and risks associated with the approach.
At a minimum, a pilot project of any proposed treatment/recharge system
would need to be completed to demonstrate the ability of the process to
protect the area’s drinking water supply.
Facility Requirements and Costs
The key facility requirements are associated with treatment, storage and
the method of recharge.
Treatment. In addition to the treatment technology considerations
listed below under Effluent Quality Requirements, additional redundancy
would need to be provided at the treatment facility than that normally
provided. All key treatment processes (biological treatment, clarifiers,
coagulation facilities, filtration, reverse osmosis, and disinfection)
must have redundant units such that the entire flow can be treated at all
times with one unit out of service.
With reverse osmosis, a major cost consideration is brine disposal. Given
Spokane’s location, inexpensive solutions such as ocean disposal are
unavailable. Mechanical evaporation of this waste stream may be required.
Storage. Storage requirements for direct injection are mandated
for situations in which there is no alternative disposal system. In this
case, the storage volume must be three times the average daily flow. If
aquifer recharge is used as the only type of effluent disposal, the
storage volumes in 2025 and 2050 would be 66 and 82 million gallons,
respectively.
Surface Percolation. This
is the type of recharge used in Grant County, where liners were simply
removed from existing lagoons and percolation tests used to confirm that
adequate lagoon area was provided to accommodate all of the anticipated
effluent production. The percolation area required is determined by the
effluent flow rate, local hydraulic conductivity, the depth of the
infiltration pond, and the depth over which water will percolate to reach
the aquifer. Based on the discussion in Chapter 4 of the Final Basis of
Planning Report,
hydraulic conductivity is assumed to be 30 ft/day and the depth to the
aquifer is assumed to be 80 feet. Depending on the depth of water in the
infiltration pond (i), required infiltration areas are shown in Table
5‑16.
Table
5‑16.
Infiltration Area for Groundwater Recharge
|
|
|
Area (acres) at height i (ft) |
|
Year |
Q, cu ft/sec |
5 |
8 |
10 |
12 |
|
2000 |
10.7 |
0.66 |
0.64 |
0.63 |
0.61 |
|
2005 |
17.2 |
1.07 |
1.03 |
1.01 |
0.99 |
|
2010 |
23.8 |
1.48 |
1.43 |
1.40 |
1.37 |
|
2015 |
30.8 |
1.92 |
1.85 |
1.81 |
1.77 |
|
2020 |
33.7 |
2.10 |
2.03 |
1.98 |
1.94 |
|
2025 |
35.9 |
2.23 |
2.16 |
2.11 |
2.06 |
|
2030 |
37.6 |
2.34 |
2.26 |
2.21 |
2.16 |
|
2035 |
39.4 |
2.45 |
2.37 |
2.32 |
2.27 |
|
2040 |
41.2 |
2.56 |
2.47 |
2.42 |
2.37 |
|
2045 |
43.0 |
2.68 |
2.58 |
2.53 |
2.47 |
|
2050 |
44.7 |
2.78 |
2.69 |
2.63 |
2.57 |
Including buffer zones, and sloped sides, the actual infiltration area
would likely be double that listed in Table 5‑16.
Direct Injection. Direct injection into a potable water aquifer
has not been demonstrated in Washington, but if water quality standards
are met and adequate separation from drinking water wells is maintained,
the infrastructure needs are relatively simple. Design considerations
specific to aquifer recharge wells include (Groundwater and Wells, 1986):
·
Terminating the injection tube below the static water level
and maintaining positive pressure at all times.
·
Maintaining full flow to the injection well at all times to
eliminate air entrainment.
·
Controlling injection pressure to avoid fracture of the
formation.
·
Providing adequate screens and pumping capacity to
accommodate a decrease in recharge rate over time due to clogging.
Cost. The estimated cost for aquifer recharge is driven strongly
by the cost of reverse osmosis treatment and brine disposal (approximately
$4/gallon). Cost estimates for the recharge options are presented in
Table 5‑17:
Table
5‑17. Capital
Cost of Groundwater Recharge
|
Cost Component 1 |
Cost, dollars per million gallons per year |
|
Surface Percolation |
Direct Injection |
|
Incremental Treatment Cost/Savings |
$11,000 |
$11,000 |
|
Conveyance |
$1,100 |
$1,100 |
|
Site Development |
$300 |
$900 |
|
Land |
$0 |
$0 |
|
Total |
$12,600 |
$13,000 |
1. Alternative
can handle 8,000 MG/year (21.9 mgd year-round)
Key Advantages and Disadvantages
Advantages
·
Provides the most complete and versatile use of the
effluent.
·
Groundwater recharge could be used year-round, so there
would be no need for an alternate discharge as with other options.
Disadvantages
·
Public perception of the value of the regional raw water
supply is very high, and any efforts to recharge potable water aquifers
with treated effluent are likely to be met with skepticism.
·
Local water purveyors may oppose the project.
·
Treatment costs are very high.
·
Brine disposal from the reverse osmosis process would be
problematic and expensive.
Comparison of the effluent end-use alternatives with the evaluation
criteria is summarized in Figure 5-19.
The capacity criterion addresses the ability of the alternative to handle
all effluent produced by Spokane County. In performing this assessment,
it has been assumed that the implementation hurdles and regulatory
constraints for each alternative have been overcome.
Only surface water discharge and groundwater recharge can accommodate all
flow produced year-round. Agricultural irrigation and poplar farms can
handle all effluent during the summer months, but require discharge to a
surface water or some other effluent management strategy during the
winter. Industrial reuse at the IEP has the
Figure
5‑19
. Comparison of Alternatives with Evaluation Criteria
potential to use about 20 percent of the County’s projected effluent in
2025 on a year- round basis. Urban irrigation would produce a small to
moderate demand for water during the summer months, depending on the
extent of the distribution system. The effluent capacity of wetlands
systems would likely be very small.
From a technical/operational standpoint, surface water discharge is
clearly the simplest option. This is the conventional method of effluent
disposal, and could be used year-round with minimal operational
requirements. Any of the other alternatives require more complicated
wastewater management, including some or all of the following:
·
Pumping to offsite facilities
·
Maintaining offsite facilities (storage reservoirs,
infiltration ponds, recharge wells, poplar farms, wetlands)
·
Addition of more sophisticated treatment processes
·
Coordination of effluent supply with the needs of
agricultural, urban, or industrial reuse customers
This criterion relates to the complexity and size of conveyance facilities
needed to implement the alternative. Aside from surface water discharge,
aquifer recharge through surface percolation requires the simplest
conveyance, since it can be located relatively close to a treatment
facility and discharge is to a single site. Industrial reuse at Inland
Empire would not require conveying treated effluent very far (from a
Valley plant); however, significant improvements could be needed to the
on-site piping systems.
Conveyance to urban reuse sites and wetlands facilities could be
relatively straight forward or complex, depending on the extent of the
distribution system. Both the agricultural irrigation and poplar farm
alternatives require extensive conveyance systems with high-head pumping.
The implementation criterion addresses the number and difficulty of
approvals, permits and agreements that must be attained plus the amount of
land that must be acquired. Although there are certainly issues to be
addressed, surface water discharge would likely be the simplest
alternative to implement. Urban reuse and wetlands were given moderate
ratings for this criterion because of the relatively small size of the
programs and the likelihood of public and agency acceptance. Poplar farms
and agricultural irrigation rated fairly low because they require either
purchase of large tracts of land or agreements with many end users.
Industrial reuse also rated fairly low because of the lukewarm interest
expressed by potential users. Groundwater recharge received the lowest
rating because it would be challenging to convince the public and elected
officials that this practice would not negatively impact water quality in
a potable water aquifer.
Assuming the necessary permits could be attained, the County could
implement surface discharge without reliance on another agency or on end
users. Similarly, the County would have complete implementation control
over a poplar farm solution if adequate land could be acquired. County
control is also maintained through beneficial reuse at County-owned
offsite facilities such as golf courses or Plante’s Ferry Park. If
agricultural irrigation is implemented, the County could choose to
purchase land and lease the land to farmers, thus maintaining control over
the long-term use of and types of crops grown on the land. Otherwise,
agricultural reuse would be dependent on agreements with many end users.
This also is the case for industrial reuse. Aquifer recharge received a
low rating because of the need to gain acceptance from the many water
purveyors using the aquifer.
The alternatives with highest risk are those that involve discharge to
potable water aquifers. Regulatory requirements for potable water supplies
are likely to become increasingly stringent in the future as analytical
methods for contaminants improve and more health effects studies are
conducted. Consequently, groundwater recharge practices that may meet
regulatory requirements now may be inadequate in the future. Also,
groundwater recharge is highly dependent on public perception. Even if
the public initially approves the concept, real or perceived problems with
other recharge projects around the country could reverse public sentiment.
The industrial reuse alternative has significant risk since it depends on
a user that could relocate, experience financial failure, modify
operational practices or otherwise change in ways that could eliminate the
need for the water.
Alternatives that continue summertime discharge to surface waters also
face some risk that future changes in water quality requirements could
restrict this practice.
It has been assumed that all alternatives would be designed and operated
to be in compliance with regulatory requirements. Consequently, this
criterion addresses the level of treatment that must be provided. The
poplar farm alternative would require the lowest level of treatment;
whereas, groundwater discharge would require the greatest treatment.
Many of the options presented have the opportunity to enhance water
resources in the region. Groundwater recharge received the highest rating
because it provides the most extensive and versatile use of the treated
effluent. Agricultural and urban irrigation, industrial reuse and
wetlands received high ratings, particularly if these practices replace
current surface or groundwater withdrawal. Poplar irrigation received the
lo
west
rating since the water is consumed as part of the effluent management
strategy and does not replace current water withdrawals.
Constructing wetlands for effluent discharge would benefit the environment
by increasing wildlife habitat. The other alternatives were viewed as
having similar impacts on the environment. Those with high pumping or
treatment requirements (agricultural reuse, poplar farms and groundwater
recharge) would create high energy consumption, consuming natural
resources.
The alternatives were considered similar with respect to community
impact. The agricultural and urban reuse options received slightly higher
ratings since provision of a new water supply may increase property values
or facilitate development in water short areas.
Table 5‑18 presents the unit capital costs for the alternatives.
These are expressed in terms of dollars per million gallons per year of
effluent processed. This table also shows the volume of effluent that
each alternative can handle in one year.
Table
5‑18.
Cost Comparison of Effluent End-Use Alternatives
|
Alternative |
Capacity (MGY) |
Unit Cost ($/MGY) |
|
Surface Discharge |
|
|
|
Spokane River (gravity flow) |
8,000 |
$190 |
|
Little Spokane River |
1,790 |
$450 |
|
Tributaries |
4,000 |
$7,300 |
|
Agricultural Irrigation |
4,000 |
$14,900 |
|
Poplar Irrigation |
|
|
|
Peone Prairie |
4,000 |
$5,100 |
|
Palouse |
4,000 |
$6,300 |
|
Urban Irrigation |
340 |
$21,200 |
|
Industrial Reuse - Option 1 |
|
|
|
Cooling water supply without
added treatment |
440 |
$3,400 |
|
General mill use supply without
added treatment |
1,570 |
$1,700 |
|
General mill use supply with
added treatment |
1,570 |
$4,400 |
|
Split cooling/mill supply with
added treatment for mill |
1,570 |
$3,800 |
|
Wetlands Discharge |
730 |
$17,900 |
|
Aquifer Recharge |
|
|
|
Surface Percolation |
8,000 |
$12,400 |
|
Direct Injection |
8,000 |
$13,000 |
While there is a wide range in costs between the alternatives, some
general conclusions can be drawn:
·
Surface discharge is significantly less expensive than other
options.
·
Alternatives that can only handle a small portion of the
effluent have high unit capital costs.
·
Groundwater recharge has a high unit cost because of the
need for reverse osmosis treatment.
·
Agricultural reuse has a high unit cost because of the need
for large storage reservoirs.

[i] City of Spokane
Wastewater Facilities Plan. Bovay Northwest, Inc. March 2000.
[ii] Water Reclamation and
Reuse Standards. Washing State Department of Health and Washington
State Department of Ecology. September 1997.
[iii] Special
Supplemental Guidelines for Spokane Valley-Rathdrum Prairie Aquifer
Wastewater Land Application. Idaho Department of Health and Welfare,
Division of Environmental Quality. January 1995
[iv] Water
Reclamation and Reuse – The Demonstration Projects, Publication Number
00-10-062. Washington State Department of Ecology. December 2000.