Highly treated wastewater effluent is an important water resource in the
Spokane Region. Potential uses include streamflow augmentation,
irrigation, wetlands creation, industrial water supply and groundwater
recharge. In this chapter, alternative effluent management strategies are
reviewed by considering their applicability to Spokane County, defining
effluent quality requirements, outlining implementation steps, identifying
facility needs and associated costs, and listing key advantages and
disadvantages. Finally, the alternatives are compared against an array of
evaluation criteria.
Currently, nearly all of the County’s wastewater is treated at the Spokane
Advanced Wastewater Treatment Plant (SAWTP) and discharged year-round to
the Spokane River near Riverside State Park. To comply with the current
NPDES permit for the SAWTP, the treatment plant must achieve “secondary
treatment” standards for BOD and suspended solids, provide year-round
ammonia-nitrogen removal and seasonal phosphorus reduction.
Effluent from five small County treatment facilities (package wastewater
treatment plants or community septic tanks) is discharged to either
community drainfields or infiltration ponds. These facilities are being
phased out as the County extends its sewer system to remote service areas.
Chapter 3 of the Basis of Planning Report gives a detailed
evaluation of existing and future development to be served by the County’s
wastewater treatment facility. Flow is collected in three major
interceptors – two in the Spokane Valley area (North Valley Interceptor
north of Interstate 90 and Spokane Valley Interceptor south of Interstate
90) and one in the North Spokane area (North Spokane Interceptor). Average
wastewater flow projections for each of these interceptors are shown in
Table 5‑1. There is little seasonal variation in these flows.
Potential effluent demand under the various effluent end-use management
options will be compared to these values.
Effluent quality requirements will vary depending on the specific effluent
end-use application. To facilitate comparison of treatment costs for the
alternatives, a “baseline treatment level” was established based on the
anticipated requirements for year-round discharge to the Spokane River.
These standards were described in detail in Chapter 4 of the Basis of
Planning Report and are summarized later in this chapter (see Table 5‑2).
Figure 5‑1 presents a representative treatment train capable of
meeting the projected effluent quality requirements for discharge to the
Spokane River.
Table
5‑1. Projected
Effluent Flow
|
|
Average Flow, mgd |
|
Year |
North Spokane Interceptor |
North Valley Interceptor
|
Spokane Valley Interceptor
|
Total
|
|
1999 |
1.0 |
1.1 |
3.5 |
5.7 |
|
2000 |
1.3 |
1.4 |
3.9 |
6.5 |
|
2005 |
2.4 |
2.7 |
5.3 |
10.4 |
|
2010 |
3.6 |
4.1 |
6.8 |
14.5 |
|
2015 |
4.3 |
5.8 |
8.7 |
18.8 |
|
2020 |
4.7 |
6.5 |
9.5 |
20.6 |
|
2025 |
4.9 |
7.0 |
10.0 |
21.9 |
|
2030 |
5.1 |
7.4 |
10.4 |
23.0 |
|
2035 |
5.4 |
7.9 |
10.8 |
24.1 |
|
2040 |
5.6 |
8.4 |
11.2 |
25.2 |
|
2045 |
5.8 |
8.8 |
11.6 |
26.2 |
|
2050 |
6.0 |
9.3 |
12.0 |
27.3 |


Figure
5‑1.
Process Schematic for Baseline Effluent Quality
Many effluent management alternatives were identified during the
brainstorming workshop and in public meetings (see Chapter 3). Those
ideas selected for detailed review are listed below:
·
Discharge to surface waters
·
Spokane River
·
Little Spokane River
·
Tributaries
·
Irrigation of agricultural land
·
Irrigation of poplar farms
·
Irrigation of urban green spaces
·
Industrial reuse
·
Wetlands creation or enhancement
·
Groundwater recharge
In developing the relative capital costs for each alterative, four
components were considered:
·
Treatment cost: This represents the incremental
treatment cost (or savings) compared to the baseline treatment train
presented in Figure 5‑1.
·
Conveyance and storage cost: This includes the cost
of pipelines, pumping stations, reservoirs and outfalls needed to
implement the alternative.
·
Site development cost: This includes any on-site
development costs associated with the effluent use alternative such as
wetlands development, infiltration basins, etc.
·
Land cost: This includes the cost of land for
alternatives that require County-owned property.
A key challenge in developing the economic comparison is that the
different alternatives result in differing levels of demand for the
effluent. Some alternatives can use all of the effluent on a year-round
basis, whereas others can use only a portion of the effluent and/or
operate on a seasonal basis. For this reason, costs are presented based
on a unit cost per million gallons/year of effluent utilized.
It must also be pointed out that specific infrastructure required for some
alternatives cannot be accurately defined until additional study is
completed. Consequently, the actual costs of implementing some of the
alternatives may vary considerably from the values presented here.
Surface water discharge is the conventional effluent management practice
for municipal wastewater plants. During dry summer periods, highly
treated effluent may provide an important water supply to augment
streamflows and support beneficial uses.
Figure 5‑2.
Major Rivers and Tributaries near the Planning Area
|
During the alternatives development process, three opportunities for
surface discharge were identified:
·
Discharge to the Spokane River
·
Discharge to the Little Spokane River
·
Discharge to smaller tributaries
The Spokane River runs through the northern portion of the Spokane Valley
area and into the City of Spokane, while the Little Spokane River skirts
the northeastern boundary of the North Spokane area. Major tributaries
near the study area, shown in Figure 5‑2, include Latah Creek south
of the City of Spokane, and Deadman Creek near the North Valley area. All
of these water bodies have Class A (exceptional) designations, and are
protected for beneficial uses such as fish and shellfish rearing,
spawning, and harvesting; water supply; recreational use; wildlife
habitat; and commerce and navigation.
In this alternative, treated effluent would be discharged to the Spokane
River year-round. If all Spokane County flow were discharged to the
Spokane River, the average effluent flow rate in 2025 and 2050 would be 34
and 42 cfs, respectively. By comparison, average monthly streamflows in
the river (as measured at the Spokane Gage) range from 1,400 cfs in August
to 17,000 cfs in May. During the critical 7Q20 streamflow condition
(about 600 cfs), the Year 2025 effluent flow rate would represent
approximately 6 percent of the total streamflow.
Applicability to Spokane County
Year-round discharge to the Spokane River is currently practiced for most
wastewater generated in the Spokane Region. When considering ways to
modify or expand this practice, it is important to consider factors that
influence the ability of the river to assimilate the pollutant loading.
These factors include:
·
Proximity to existing dischargers. Currently, there
are four major dischargers to the Spokane River in Washington: Liberty
Lake Water and Sewer District, Kaiser Aluminum, Inland Empire Paper and
the City of Spokane (SAWTP). The first three discharges are located along
the Spokane River between the Idaho border and the Upriver Dam, whereas
the SAWTP’s discharge is downstream of the confluence with Latah Creek.
Spreading out point discharges along the river minimizes local toxicity
issues associated with ammonia, metals, and selected organics, and it
increases the river’s ability to assimilate impacts from nutrients and
dissolved-oxygen-consuming pollutants.
·
Interaction with Spokane Aquifer. It would be
preferable to discharge treated effluent to a reach of the river that is
recharged with groundwater from the aquifer (“gaining reach”). This has
multiple benefits. First, the aquifer recharge adds hardness to the
river, which reduces the toxicity of heavy metals of concern. Second,
discharge to gaining stretches of the river reduces potential regulatory
and public concerns regarding migration of the wastewater discharge into
the aquifer.
Figure 5‑3 shows the major municipal and industrial discharges on
the Spokane River in Washington (green circles), as well as gaining and
losing reaches of the river. Red circles indicate discharges to the Little
Spokane River. Based on the factors identified above, and discussions
with Ecology, Reach 4 appears to be the most attractive location for a new
wastewater discharge to the Spokane River. It is in a gaining stretch of
the river, has free-flowing characteristics to promote re-aeration, and
provides a good separation from the SAWTP discharge. Locating a discharge
at this location would require consideration of the interrelation with
upstream discharges such as that from Inland Empire Paper.
Effluent Quality Requirements
Chapter 4 of the Basis of Planning Report provided a detailed review of
anticipated effluent quality requirements for a new discharge to the
Spokane River. Since receiving waters are most sensitive to effluent
discharge during the late summer (when streamflows are lowest), it is
likely that Ecology would establish a seasonal permit for a new wastewater
discharge.
Based on preliminary discussions with Ecology and review of NPDES permits
for other discharges to the Spokane River, anticipated effluent quality
requirements have been identified for surface water discharge (see
Table 5‑2). Refinements to these requirements will be driven by the
exact location of the discharge, results of mixing zone studies, effluent
concentrations of metals, results of the dissolved oxygen TMDL study, and
negotiations with the Phosphorus Technical Advisory Committee (TAC).
Figure
5‑3. Existing
Dischargers and River/Aquifer Interaction
Table
5‑2. Projected
Effluent Quality for Surface Water Discharge
|
Parameter |
Summer |
Winter |
|
BOD, mg/L1 |
10-20 |
30 |
|
Total Suspended Solids, mg/L |
30 |
30 |
|
Ammonia-Nitrogen, mg/L1,2 |
1-2 |
4-8 |
|
Total Nitrogen, mg/L |
No limit |
No limit |
|
Total Phosphorus, mg/L3 |
0.3-0.6 |
No limit |
|
Dissolved Oxygen, mg/L1 |
> 6.0 |
No limit |
|
Fecal Coliform, cfu/100 mL |
200 |
200 |
|
Chlorine Residual,
mg/L2 |
» 8 |
» 8 |
|
pH (s.u.)4 |
6.0-7.8 |
6.0-7.8 |
|
Lead, mg/L5 |
» 2 |
» 2 |
|
Zinc, mg/L5 |
» 60 |
» 60 |
|
Cadmium, mg/L5 |
» 0.2 |
» 0.2 |
1.
Required value will be defined by dissolved oxygen TMDL process.
2.
Required value will be defined by mixing zone study for toxicity.
3.
Required value will be defined through negotiation with Phosphorus TAC.
4.
Instantaneous value
5.
Required value will be defined based on monitoring of actual effluent
metals concentration.
6. This
effluent quality would be achieved using a treatment train similar to that
shown in Figure 5‑1.
Implementation
Implementing a new surface water discharge for the County’s treated
effluent would require:
·
Negotiating a new NDPES discharge permit with the Department
of Ecology. This effort would include:
·
Conducting dilution studies and a mixing zone study to
determine local impacts of the proposed discharge on toxicity and
temperature.
·
Conducting modeling to assess the near-field impact of the
discharge on dissolved oxygen levels.
·
Using Ecology’s new water quality model to assess the
far-field impacts of the discharge on algal growth and dissolved oxygen
levels.
·
Negotiating with the Phosphorus TAC to allow a new point
source discharge of phosphorus. Although the Long Lake Phosphorus
Management Agreement does not allow new point source discharges of
phosphorus, initial discussions with Ecology and the TAC indicate that
these groups would consider Spokane County as an existing discharger to
the river, not as a new discharger.
·
Conducting public information/public involvement efforts to
assure the public that the new discharge would not adversely impact
beneficial uses of the receiving water.
·
Gaining necessary permits for construction of the outfall,
including a Corps of Engineers 404 permit and a Shoreline Management
permit.
Facility Requirements and Cost
Assuming water quality criteria can be met, this alternative can handle
all Spokane County flow on a year-round basis. Facility requirements
primarily consist of an outfall pipeline and a multi-port diffuser.
Depending on the location and elevation of the treatment plant, effluent
pumping may be required. The estimated capital cost for this alternative
is presented in Table 5‑3.
Table
5‑3.
Capital Cost of Surface Discharge to Spokane River ($/MGY)
|
Cost Component 1 |
Gravity Discharge |
Pumped Discharge |
|
Incremental Treatment Cost/Savings |
$0 |
$0 |
|
Conveyance |
$190 |
$690 |
|
Site Development |
$0 |
$0 |
|
Land |
$0 |
$0 |
|
Total |
$190 |
$690 |
1. Alternative
can handle 8,000 MG/year (21.9 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Highly treated effluent can augment low streamflow during
the late summer, supporting fisheries and providing an environmental
benefit.
·
Surface water discharge facilities are simple to construct,
operate and maintain.
·
Anticipated water quality requirements for stream discharge
can be met with conventional treatment technologies.
·
The capital cost for an outfall is low.
Disadvantages
·
Surface water discharge does not maximize use of the
effluent as a water resource.
·
Depending on the results of the dissolved oxygen TMDL,
effluent quality requirements may be more restrictive than anticipated,
requiring higher treatment costs. Although unlikely, it is possible that
the allowable quantity of effluent discharged may be limited during
critical periods of receiving water quality.
·
Future regulatory changes may increase treatment
requirements and associated costs.
·
Siting a new outfall may encounter opposition from current
dischargers or other interest groups.
This alternative involves discharging treated effluent from the North
Spokane Service Area to the Little Spokane River below Dartford. Because
of the conveyance distance involved, the alternative does not include
sending flows from the Spokane Valley to a discharge point on the Little
Spokane River.
As shown in Figure 5-3, the stretch of river below Dartford is a gaining
reach, where the aquifer contributes to river flow. During critical summer
months, the estimated streamflow at Dartford is approximately 250 cfs
(personal conversation, Stan Miller). By comparison, the projected
effluent flow rate from the North Spokane Service Area in 2025 and 2050 is
8 and 9 cfs, respectively; or less than 4 percent of the summer
streamflow.
Applicability to Spokane County
The key considerations for locating a new outfall on the Little Spokane
River are the same as those for the Spokane River. As Figure 5-3 shows,
there are two existing discharges to the Little Spokane River, so
proximity to these discharges would be a consideration. In the stretch of
river below Dartford, potential impacts of a new outfall on the aquifer
would be minimal because the aquifer discharges to the river.
While there are portions of the Little Spokane River where declining flows
have been a concern in the past, these areas are upstream of Dartford and
therefore would not be positively impacted by the addition of treated
effluent (see later discussion of discharge to tributaries).
Effluent Quality Requirements
It is anticipated that effluent quality requirements for this alternative
would be similar to those for discharge to the Spokane River.
Implementation
Most key implementation considerations are the same as for discharge to
the Spokane River. The lower part of the Little Spokane River (from its
confluence with the Spokane River to River Mile 5) is a state-designated
wild and scenic river. While this designation does not carry the same
regulatory significance as a federal designation, there likely would be
some public opposition to any activities impacting the river in this
area. This may require additional mitigation.
Facility
Requirements and Cost
This alternative can handle flows from only the North Spokane Service
Area. Wastewater from the Spokane Valley must be handled by other means
such as discharge to the Spokane River.
Given the topography of the Little Spokane watershed, it has been assumed
that effluent from a new plant could be discharged by gravity. The
estimated unit cost is presented in Table 5‑4.
Table
5‑4.
Capital Cost of Surface Discharge to Little Spokane River
|
Cost Component1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$450 |
|
Site Development |
$0 |
|
Land |
$0 |
|
Total |
$450 |
1. Alternative
can handle 1,790 MG/year (4.9 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Key advantages listed for the Spokane River discharge option
apply to this alternative.
·
This concept returns the flows generated within the Little
Spokane watershed to the river rather than exporting them out of the
watershed.
·
Sending a portion of Spokane County’s effluent to the Little
Spokane River further spreads out the loading to the region’s receiving
waters, making greater use of assimilative capacity and reducing localized
impacts.
Disadvantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
This alternative handles only the flow generated in North
Spokane.
·
This alternative does not address the declining stream flows
experienced in the upper reaches of the Little Spokane River watershed.
·
Discharge to the Little Spokane River would likely encounter
opposition from local residents and environmental groups.
The concept of this alternative is to augment minimum streamflows in
smaller tributaries to augment beneficial uses such as fisheries, or to
offset declining streamflows due to overuse of surface withdrawals and
groundwater pumping.
Applicability to Spokane County
Three tributaries were identified as potential locations for augmenting
streamflow.
Latah Creek. As shown in Figure 5‑2, Latah Creek is one of
the closest tributaries to the planning area. There is little stream
gauging information for this tributary, however the estimated summer flow
in the stream is approximately 20-30 cfs (personal conversation, Stan
Miller). Because of insufficient data, further study would be required to
determine where an outfall should be located to augment streamflow and how
much effluent would be needed. During the alternatives workshop,
discharge to Latah Creek was discussed with staff from Ecology, the County
and the City. There was little support for the concept because no
significant environmental benefits were identified.
Crab Creek (Lincoln and Grant Counties). This concept was examined
as a streamflow augmentation option in the City of Spokane’s Facilities
Plan[i],
based on interest from Lincoln County, the State of Washington, and other
parties. Crab Creek is located approximately 15 miles west of Medical
Lake.
Upper Tributaries of the Little Spokane River. As mentioned
earlier, declining flows in the upper Little Spokane River basin have been
a concern. In 1975, water availability was of such concern that the major
tributaries of the Little Spokane River were closed to further water
appropriation, and water rights issued were conditioned to specific “base”
flows measured at Dartford. Continuing development of exempt wells
contributes to water shortages in the basin.
Effluent Quality Requirements
The majority of tributaries in the region are designated Class A streams,
and thus would be subject to the type of treatment illustrated in
Figure 5‑1. In discussions with the City regarding the potential Crab
Creek discharge, Ecology indicated that water quality requirements may be
relaxed somewhat if the streamflow augmentation project significantly
benefits water quality in a stream. However, this would need to be
evaluated on a case-by-case basis. For purposes of analysis, it is
assumed that the treatment train shown in Figure 5‑1 would be
required for discharge to any tributary.
Implementation
Implementation considerations would include those described for discharge
to the Spokane River. In addition, easements and right-of-ways would be
required for long conveyance pipelines. Studies would be required to
determine how much effluent could be sent to the tributaries during
various times of the year.
Facility Requirements and Cost
Depending on the carrying capacity of the tributary, this alternative may
not be able to handle all effluent generated by Spokane County. For the
purposes of this analysis, it has been assumed that one-half of the
wastewater generated by the County in 2025 could be discharged to
tributaries. The remaining flow must be discharged either to a major
stream or reused in some other manner.
Since the baseline treatment train would be used, the primary cost would
be associated with conveyance. With the exception of Latah Creek,
discharge to a tributary would require pumping treated effluent from 20-40
miles. Estimated costs are based on sending Spokane County’s flow through
a 20-mile pipeline. The estimated cost of this option is presented in
Table 5‑5.
Table
5‑5.
Capital Cost of Surface Discharge to Tributaries
|
Cost Component 1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$7,340 |
|
Site Development |
$0 |
|
Land |
$0 |
|
Total |
$7,340 |
1. Alternative can handle
4,000 MG/year (11 mgd for 365 days)
Key Advantages and Disadvantages
Advantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
This concept could potentially enhance water resources in
the region by augmenting low streamflow or providing an alternative water
supply to groundwater.
·
This alternative spreads out loadings to receiving waters,
reducing localized water quality impacts.
Disadvantages
·
Key disadvantages listed for the Spokane River discharge
option apply to this alternative.
·
Requires significant infrastructure for conveyance.
·
Streamflow augmentation in tributaries may not be adequate
for all of the County’s flows, requiring an additional surface water
discharge to a major river.
·
Additional study would be necessary to determine whether
there is a true water quality or beneficial use benefit to augmenting
streamflow in the tributaries.
·
Discharging treated wastewater to tributaries may be opposed
by local property owners.

Figure 5‑4.
Irrigation of Agricultural Land
|
This alternative investigates the use of treated effluent for irrigation
of agricultural properties in Spokane County. Reclaimed water would be
used for irrigation on a seasonal basis to match crop demand. For the
remainder of the year, effluent would be discharged to surface water. The
concept is illustrated in Figure 5‑4.
Potential Reuse Locations
While development in the Spokane Valley has reduced the number of farms in
the County, many agricultural areas were protected through the growth
management practices outlined in the 1980 County Comprehensive Plan and
continued in the 2000 Draft Comprehensive Plan (Draft Comp Plan, 2000).
The Draft County Comprehensive Plan includes agricultural land in its
designation of Natural Resource lands, offering protection to “ensure
their viability for future generations” (Draft Comp Plan, Page NR-15).
According to the County’s Planning Department, protection of these natural
resource lands is anticipated to extend far into the future, well beyond
the horizon of either the current Comprehensive Plan or this Facilities
Plan.
Protected agricultural lands (based on zoning information from the Draft
Recommended Comprehensive Plan) are shown in Figure 1‑5. The five
primary areas have been numbered for later use in reuse demand analyses.
This figure also shows the total acreage for each area, and the boundaries
of the Draft Urban Growth Area (in black) and the Aquifer Sensitive Area
(in red).


When
evaluating agricultural reuse in these areas, there are several issues
that need to be considered:
·
Within the agricultural land designation, the County
identifies “large tract” (one residential unit per 40 acres) and “small
tract” (one residential unit per 10 acres) agricultural properties that
have long-term commercial significance. The large tract properties are
more attractive for an effluent reuse program because they result in fewer
contracts with farmers, require fewer metering points and are more likely
to remain in agricultural use on a long-term basis.
·
Much
of the southern portion of Area 5 is being converted to small ranchettes,
and the recent construction of a new high school will promote further
development. Based on this development pattern, any agricultural demand in
Area 5 is likely to be associated with small-scale farming operations.
·
Although not in a protected agricultural area, there are
existing farms in the Chattaroy area along the Little Spokane River east
of Area 4 (see Table 5‑6). Providing reuse water for irrigation in
this area would offset the surface water or groundwater impacts of
existing irrigation withdrawals. Local topography favors sending reuse
water from the planning area to the Chattaroy area.
·
Many of the potential reuse locations in all areas would
require pumping to higher elevations. For example, there are potential
reuse sites in the Green Bluff area (northern portion of Area 5); however,
reaching these locations would require pumping to an elevation of
approximately 2,400 feet.
Estimates of Demand Potential
David Bezdicek of Washington State University provided guidelines
regarding evaporative demand for representative crops grown in the
designated agricultural areas. These irrigation requirements (shown in
Figure 5-5) take into account monthly precipitation, as
well as the impacts of agricultural management practices (harvesting,
planting, etc.) that reduce the full evaporative demand.
For purposes of evaluation, the estimated demand for water has been based
on a blend of grain, wheat, alfalfa and pasture production. This provides
a representative mix of cropping patterns that may occur in the region.
To maximize water use, particularly in September and October, it would be
best to maximize use of pasture crops. However, this may not be
economically attractive to farmers.
Figure
5‑6.
Net Irrigation Requirement for Crops in Spokane County
To determine the volume of water demand for each of the designated
agricultural areas, the following assumptions were applied to the data
shown in Figure 5-6:
·
60% of the total land in the protected agricultural areas
would be available for crop production.
·
Irrigation with treated effluent would begin the last week
of April and continue through the end of September (October demand is
minimal).
·
Monthly irrigation demand is spread evenly over all days of
the month.
Based on these assumptions, Table 5‑6 shows the total irrigation
demand for each of the five designated agricultural areas. By comparison,
the average effluent production rate in 2025 and 2050 is projected to be
22 and 27 mgd, respectively.
Table
5‑6.
Irrigation Demand for Designated Agricultural Areas
|
|
|
Demand (mgd) for Designated Agricultural Area1 |
|
Month |
gal/d/acre |
1 |
2 |
3 |
4 |
5 |
|
January |
0 |
0 |
0 |
0 |
0 |
0 |
|
February |
0 |
0 |
0 |
0 |
0 |
0 |
|
March |
0 |
0 |
0 |
0 |
0 |
0 |
|
April |
1,560 |
60 |
210 |
11 |
31 |
18 |
|
May |
2,590 |
100 |
360 |
17 |
53 |
31 |
|
June |
4,860 |
190 |
670 |
33 |
100 |
58 |
|
July |
6,560 |
250 |
900 |
45 |
130 |
77 |
|
August |
3,080 |
120 |
420 |
22 |
63 |
36 |
|
September |
1,540 |
60 |
210 |
11 |
31 |
18 |
|
October |
90 |
0 |
0 |
0 |
0 |
0 |
|
November |
0 |
0 |
0 |
0 |
0 |
0 |
|
December |
0 |
0 |
0 |
0 |
0 |
0 |
1. See
Figure 5-5 for location of designated agricultural areas.
Based on the estimates of reuse demand shown in Table 5‑6, there is
sufficient potential demand in Areas 1, 2, 4 and 5 to handle all effluent
production from April through September for the year 2025. Area 3 could
handle all of the effluent in May through August, and most of the effluent
during April and September. Reuse demand in October would be minimal in
all areas.
Interest Level of Potential End Users
A targeted survey of farmers in the region was not conducted as part of
this project. The City of Spokane’s 1999 Facilities Plan also investigated
agricultural reuse as an effluent management option; however, no
investigations were made into the potential interest of regional farmers.
Issues that have been raised by farmers during other feasibility studies
of agricultural reuse in Northwest communities include:
·
Cost. For farmers with existing water supply, there
must be an economic incentive to switch to reuse.
·
Adequacy/availability of current water supply.
Interest is typically higher among farmers that lack adequate irrigation
water.
·
Water quality. Farmers value the nutrient content of
the reclaimed water but are concerned about other parameters that could
impact their crops such as salinity, chlorine or metals.
·
Food Processors. Farmers are concerned about the
reaction of the food processing industry to irrigation with treated
effluent.
·
Water Pressure. Various irrigation systems have
differing pressure requirements for operation. For example, “big gun”
irrigation systems require significantly higher pressure than most
irrigation methods. Farmers would prefer the reuse delivery pressure to be
adequate to operate their preferred irrigation equipment.
·
Reluctance to dedicate land for long-term agricultural
uses. Although the areas investigated for this study are protected for
long-term agricultural use, current owners may perceive a reduction in
value if they feel long-term agreements or use of reclaimed water could
complicate their ability to convert their property to other uses in the
future.
·
Regulation. Use of reuse water brings with it an
added set of regulatory requirements that farmers must comply with.
Based on the results of other feasibility studies for agricultural reuse,
it is clear that farmers would not be willing to pay the true cost to
deliver the reuse water to their sites. At best, they would be willing to
a price equivalent to that for other irrigation water supplies in the
region. Since this represents only a fraction of the true costs to supply
the water, an agricultural reuse program would need to be heavily
subsidized by the wastewater utility.
Water Resource Implications
The optimal locations for agricultural reuse are in areas where treated
effluent could replace existing surface water or groundwater withdrawals.
Effluent also could serve as a new source of water in areas that have no
water supply. This is attractive from the perspective of increasing the
value of the land; however, it does not free up other water supplies for
alternative use.

Figure 5‑7.
Timing of River Flow and Irrigation Demand
|
A large-scale agricultural reuse program could reduce or eliminate the
need for surface water discharge during much of the summer; however,
irrigation demand in September and October may be insufficient to use all
of the effluent. Figure 5‑7 compares the month-by-month trends for
streamflow in the Spokane River and irrigation demand, and shows that
river flows remain low after the irrigation demand sharply decreases.
Consequently, during the late summer and early fall, effluent would need
to be discharged to receiving waters, necessitating high levels of
nutrient removal.
Effluent quality requirements for agricultural reuse are set forth in
Washington’s Water Reclamation and Reuse Standards
[ii], and were
summarized in Chapter 4 of the Final Basis of Planning Report. The
reuse rules allow various qualities of reclaimed water to be used for
agricultural irrigation, depending on the crop to be grown, the irrigation
method, setback provisions and other considerations. Since the specific
types and uses of potential crops are not known at this time, it has been
assumed that effluent must be treated to Class A reuse standards, allowing
it to be used for the greatest variety of crops and with the least
restrictions on the end-user. This quality of water would have the
greatest appeal to farmers.
Class A water has more stringent disinfection requirements than the
effluent parameters listed in Table 5‑2 for surface water
discharge. However, the treatment process shown in Figure 5‑1
would be capable of meeting these tougher standards. Because some
nutrient loading is beneficial to crops, it may be possible to reduce the
amount of ammonia-nitrogen and phosphorus removal that must be provided at
the County’s treatment facility during the summer.
While there are no specific guidelines for reuse over the aquifer in
Washington, the Idaho Division of Environmental Quality developed the
Special Supplemental Guidelines for Spokane Valley-Rathdrum Prairie
Aquifer Wastewater Land Application (1995)
[iii] to provide
direction for a land application project for the Hayden Area Regional
Sewer Board (HARSB) in Idaho. These guidelines recommend that both
hydraulic application and nitrate-nitrogen loading be limited to amounts
required for crop uptake. As a general guideline, it has been assumed that
nitrate concentrations would need to be reduced to less than 10 mg/L for
large-scale agricultural irrigation over the aquifer.
Reclaimed water programs are administered jointly by the Departments of
Ecology and Health, with irrigation programs permitted through Ecology.
As part of the regulatory review process, the wastewater utility must
complete an Engineering Report that describes the design and operation of
the proposed program and indicates the means of compliance with all
applicable standards and regulations.
Other key implementation steps would include:
·
Conducting a needs survey/feasibility study to define
potential demand and end-user requirements.
·
Developing long-term agreements with private farmers or
purchasing sufficient land to meet the program requirements.
·
Developing an organizational structure to manage the reuse
program.
·
Siting and permitting critical infrastructure components
such as reservoirs and pipelines.
·
Preparing predesign and detailed design for all facilities.
·
Conducting environmental assessments necessary to meet
regulatory requirements.
·
Developing operational plans, including reliability and
emergency response measures.
·
Developing and implementing monitoring plans.
·
Implementing a comprehensive public education program.
The choice between purchasing land for irrigation or developing long-term
agreements with private farmers is a key consideration. The first option
would give the County more control over the long-term use of water and
crop selection for agricultural areas. On the other hand, it would
require greater capital expense, add the administrative task to develop
and maintain the lease relationship, and may encounter opposition from
individuals opposed to the County’s purchase of large tracts of farmland.
Developing long-term agreements would require that the farmer be committed
to long-term agriculture. It also may require two separate negotiations
(with the owner and the leaser) if the property is privately owned and
leased to a private farmer.
Another key decision is whether the County would operate the reuse system
or partner with a local water purveyor for this service.
The requirements described below are based on a system configuration that
includes pumping of treated effluent to one or more reservoirs located
near the various reuse areas, and subsequent pumping through a
distribution system to serve agricultural customers. There are four major
components to this system: treatment, transmission, storage and
distribution.
Treatment
To produce Class A reclaimed water, the required treatment train would be
equivalent to that presented in Figure 5‑1; however, the reuse
standards specify additional reliability and redundancy components that
must be incorporated into the treatment plant.
Transmission
Transmission distances to the designated agricultural areas vary widely.
Serving Area 5 would require pipeline lengths of 6 to 8 miles from a North
Spokane Plant and 8 to 12 miles from a plant located in the Spokane
Valley. Pumping from the North Spokane area to Area 4 would require
approximately 15 miles of transmission line. Transmission distances to
Areas 3, 1, and 2 increase to 25 miles, 30 miles, and over 40 miles,
respectively.
To the extent possible, transmission lines would be located in public
right of way. For purposes of this analysis, it is assumed that the County
would not need to pay to acquire any property or easements for reuse
transmission.
Storage
There are two options for storage: provide storage to meet all seasonal
irrigation demands, or provide irrigation water “on demand” with limited
local storage to meet peak demands.
To maximize reuse of treated effluent, it would be necessary to provide
storage during the early spring in order to meet the peak demand of June
and July. Storage volume requirements were calculated based on annual
average 2025 flows and 5,000 total acres of land application area. With
this demand, the excess flow produced in April and May at 2025 flow rates
would be sufficient to make up the deficit in wastewater flows through
June, July and August, resulting in no excess storage during the
non-irrigating period (late August through mid-April). This allows the
County to avoid adverse impacts due to long-term storage. Experience
shows that issues such as algal growth and odor generation can lead to
serious water quality degradation if reclaimed water is stored for long
periods without major reservoir maintenance efforts. The total storage
volume required at 2025 flows would be 400 million gallons. Initial
requirements, based on 2005 flow rates, would be 2,400 acres of land under
irrigation and a reservoir capacity of 200 million gallons.
For “on demand” application, detailed discussions with farmers would be
required to determine the daily peaking factor appropriate for sizing
storage. Initial estimates of facility requirements are based on two days
of storage.
Any storage reservoirs located over a potable water aquifer would need to
be lined.
Distribution
Most irrigation systems can be categorized as medium pressure (50-60 psi)
or high pressure (100-125 psi). Medium pressure systems include center
pivot, lateral move, and solid set irrigation, whereas high pressure
systems are needed for “big gun” irrigation. If the County were to
implement agricultural reuse, it would make sense to provide a medium
pressure system, with individual farmers providing booster stations as
needed for “big gun” equipment.
Cost
The estimated cost of this alternative is presented in Table 5‑7.
This cost is based on conveyance of all flow from April through September
to a storage reservoir located 14 miles from the treatment plant, and
distribution to multiple farms with an average size of 450 acres.
Table
5‑7.
Capital Cost of Agricultural Reuse
|
Cost Component 1 |
Unit Cost ($/MG/Year) |
|
Incremental Treatment Cost/Savings |
$0 |
|
Conveyance |
$8,600 |
|
Site Development (reservoirs) |
$5,900 |
|
Land |
$200 |
|
Total |
$14,900 |
1. Alternative
can handle 4,000 MG/year (21.9 mgd for six months)
Advantages
·
Effluent reuse can have significant water resource benefits
where irrigation water is currently obtained from surface water or
groundwater resources. It would conserve and stretch potable water
supplies
·
For agricultural property without a water supply, a reuse
program would increase crop yields and property value.
·
Implementing a reuse program could reduce or eliminate
discharge to surface waters during the spring and mid-summer months.
Disadvantages
·
During October and possibly September, irrigation demand
would not be sufficient to use all of the County’s effluent.
Consequently, treated effluent would need to be discharged to the river
during low streamflow conditions unless other effluent management
strategies were implemented for this period.
·
Effluent storage reservoirs may prove difficult to site and
permit.
·
Infrastructure development costs are high.
·
Operational costs for pumping would be high.
·
This concept requires long-term agreements with farmers or
purchase of large tracts of agricultural property. Both options may be
difficult to implement.
·
This alternative has risk associated with changing land
use. However, applying effluent to agricultural areas that have been
protected through the County’s comprehensive planning and zoning process
would reduce the risk that land will not be available for long-term
effluent reuse.
·
Local water purveyors may view this new water supply as
competition that could reduce their revenue.
·
Revenue from sale of the water would pay for only a fraction
of the development and operating costs. Consequently, wastewater
ratepayers would need to subsidize to program.
This alternative involves a variation of agricultural reuse in which
hybrid poplars would be grown. From an effluent management perspective,
poplars are attractive because they have a high water demand. Also, the
harvested poplars may produce revenue for the wastewater utility.
The use of poplars is an emerging management practice for municipal
wastewater. In the Northwest, several communities are in various stages
of implementation. The most established program is in Woodburn, Oregon
where poplars have been grown for the past seven years.
Applicability to Spokane County
In the Spokane climate, poplars would have an estimated water consumption
rate of 5 feet per year. If this water were applied over the six-month
summer permit season, the required area of trees under irrigation would be
2,400 acres in 2025 and 3,000 acres in 2050. Taking into consideration
buffers, harvesting requirements and other property management functions,
the total property requirements would increase about 50 percent to 3,600
and 4,500 acres in 2025 and 2050, respectively. To maintain control of
the irrigation and harvesting operations, the County would need to
purchase the property and operate the facility.
With such a large land requirement, the cost of this alternative becomes
highly dependent on the cost of land and the length of conveyance
pipelines to deliver the water. Two scenarios were considered:
·
A site in Peone Prairie located within 7 miles of the
treatment plant. Estimated property costs in this area would be $10,000
per acre.
·
A site in the Palouse, located 20 miles from the treatment
plant. Property costs in this area are based on $2,000 per acre.
Effluent Quality Requirements
Poplars may be irrigated with Class C reclaimed water, which requires
secondary treatment and effective disinfection. Since the poplar farm
would only receive water during the six dry-season months, effluent would
need to be discharged to a receiving water during the winter. This would
require the ability to provide nitrification during cold weather
conditions to meet in-stream toxicity limits for ammonia.
Implementation
Implementation requirements would be similar to that for agricultural
irrigation with the exception that market surveys and long-term agreements
with farmers would not be needed. Instead, the County would need to
identify and acquire the large tracts of land needed for the poplar
system.
Facility Requirements and Cost
Key facility requirements for a poplar system are outlined below:
·
Treatment plant – advanced secondary treatment with
nitrification (for winter discharge condition.
·
Effluent pumping – a high head lift station would be needed
to convey the effluent to the irrigation site.
·
Transmission main – depending on the site location, a 7 to
20 mile pipeline would be required.
·
Storage – a minimum of two days of operational storage
should be provided to balance supply and demand variations and to
accommodate emergency situations.
·
Site development – the property would need to be prepared
for growth of poplar trees, including clearing and grading, construction
of access roads, installation of surface runoff controls, and installation
of groundwater monitoring wells.
·
Irrigation system – a mechanical irrigation system would
need to be installed.
The estimated unit capital cost is shown in Table 5‑8 for both the
Peone Prairie and Palouse sites. Compared to the baseline treatment
system, elimination of effluent filtration and phosphorus removal is
projected to save approximately $1.50 per gallon of capacity. This
savings is offset by the other development costs for the system.
The potential revenue from a poplar operation is highly speculative.
Initially, poplars were thought to provide a quality source of pulp for
paper mills; however, the acceptance of the poplar pulp has been mixed and
the revenue generated small. Lately, interest has grown in the use of
poplars as a clear softwood for non-structural products, such as blinds.
The market value and demand potential for these products may be
significant, but this has not been firmly established. If such a market
exists, it is likely that the commercial wood products industry would grow
poplars in sufficient quantity to satisfy the demand. In such a market
place, a small to mid-size municipal utility would be a very small player
with limited market access and pricing leverage. For these reasons, no
revenue stream has been included for harvested poplars.
Table
5‑8.
Capital Cost of Poplar Farms
|
Cost Component 1 |
Cost, dollars per million gallon per Year |
|
Peone Prairie |
Palouse |
|
Incremental Treatment Cost/Savings |
-$8,200 |
-$8,200 |
|
Conveyance |
$5,400 |
$11,500 |
|
Site Development (reservoir, irrigation, etc.) |
$1,900 |
$1,900 |
|
Land |
$6,000 |
$1,200 |
|
Total |
$5,100 |
$6,400 |
1. Alternative can
handle 4,000 MG/year (21.9 mgd for six months)
Advantages and Disadvantages
Advantages
·
Eliminates discharge to receiving waters during the
dry-season.
·
Harvested poplars may generate revenue, although this
remains uncertain.
·
Growth of poplars may be positively viewed by the public and
regulatory agencies as a “green solution” to wastewater management.
·
Allows use of a less complex, less expensive treatment
system.
Disadvantages
·
Requires purchase of large tracts of agricultural land. The
agricultural community and other land use interests may view this
unfavorably.
·
Operational costs for pumping would be high.
·
Results in a more complex system to operate than river
discharge.
Urban reuse involves the use of treated effluent as an irrigation supply
for golf courses, school grounds, parks, and cemeteries. Reuse would be
during the summer months only, when irrigation demand is highest. The
basic concept of the program is illustrated in Figure 5‑8.

Figure 5‑8.
Irrigation of Urban Green spaces
|
Urban irrigation using treated effluent has been practiced for decades
across the nation and in the Northwest. In Oregon, the Unified Sewerage
Agency of Washington County has been irrigating school grounds and golf
courses with treated effluent for over 20 years. In Washington, urban
irrigation was included in several demonstration projects administered by
the Departments of Ecology and Health
[iv]. Treated
wastewater effluent is used for landscape irrigation by the City of
Sequim, and for irrigation at local churches, city parks, and a private
residence in the City of Yelm.
Location of Potential Reuse
Sites
Using the County’s land use information system, an investigation was
conducted to identify green space that could potentially be included in an
urban irrigation program. In the Spokane area, the most significant green
space are those associated with golf courses, parks, cemeteries and
schoolyards. Figure 5‑9 presents the location of these facilities
in the greater Spokane region. Appendix C,
consists of tables showing all of the parks, cemeteries, and schools
included for evaluation.
Figure
5‑9. Potential
Urban Irrigation Sites
Golf courses are typically the most attractive reuse customers because of
their large water demand. Areas with multiple golf courses include
Liberty Lake, along the Little Spokane River in North Spokane, near Latah
Creek at the south end of the City, and along the Spokane River near the
western boundary of the City.
In some communities, green space at industrial parks offer important reuse
opportunities. Based on discussions with County personnel, industrial
campuses with significant green space are limited to the Liberty Lake
area.
To initially screen candidate reuse sites, two criteria were used:
·
Proximity to the planning area
·
Complexity vs. benefit of administering reuse program
The first criterion was used to rule out sites such as the Sundance and
Fairways Golf Courses (located 15-20 miles from the planning area). The
second criterion was used to eliminate sites with small demand potential
such as individual schools with a single private owner.
Potential Reuse Demand
Demand for urban irrigation water was assessed similar to that for
agricultural irrigation, except that demand was based on turf requirements
rather than a mixture of crops. Urban irrigation demand in gallons per day
per acre is shown in Figure 5‑10.
|

Figure 5‑10.
Water demand for Urban Irrigation |
To put the potential demand in perspective, a typical 150-acre golf course
would have a maximum demand in August of 900,000 gpd, which represents 4
percent of the County’s projected effluent flow rate in 2025. During other
summer months, a smaller portion of the effluent would be used. Extending
this concept, Table 5‑9 illustrates the relationship between the
size of a reuse site and the percentage of the total County flow that can
be used on the site. As this table illustrates, many large sites or
clusters of smaller sites would be needed to use a substantial portion of
the County’s projected flow in 2025. As shown in Figure 5-9, potential
reuse sites are highly dispersed with few clusters of sizeable acreage.
Consequently, achieving a large volume of demand would require an
extensive distribution network.
Table
5‑9.
Urban Irrigation Reuse Potential
|
|
Peak Demand (as a percentage of projected
Annual Average flow) |
|
|
Year |
10 Acre Site |
20 Acre Site |
50 Acre Site |
100 Acre Site |
|
2000 |
1.00 |
2.00 |
5.00 |
10.00 |
|
2005 |
0.62 |
1.24 |
3.10 |
6.20 |
|
2010 |
0.45 |
0.90 |
2.25 |
5.50 |
|
2015 |
0.34 |
0.68 |
1.70 |
3.40 |
|
2020 |
0.31 |
0.62 |
1.55 |
3.10 |
|
2025 |
0.30 |
0.60 |
1.50 |
3.00 |
|
2030 |
0.28 |
0.56 |
1.40 |
2.80 |
|
2035 |
0.27 |
0.54 |
1.35 |
2.70 |
|
2040 |
0.26 |
0.52 |
1.30 |
2.60 |
|
2045 |
0.25 |
0.50 |
1.25 |
2.50 |
|
2050 |
0.24 |
0.48 |
1.20 |
2.40 |
| |
|
|
|
|
|
|
Golf Courses
Fourteen golf courses were evaluated as potential urban reuse sites. These
are shown in Table 5‑10. Ninety-eight percent of the total golf
course area is assumed to be irrigable.
Table
5‑10.
Urban Golf Course Sites
|
Name |
Total Acres |
Irrigable Acres |
|
Indian Canyon Golf Course |
210 |
205 |
|
Spokane Country Club |
188 |
184 |
|
Hangman Valley Golf Course |
174 |
171 |
|
Esmeralda Golf Course |
165 |
162 |
|
Wandermere Golf Course |
159 |
156 |
|
Downriver Golf Course |
158 |
155 |
|
Manito Golf Club |
139 |
136 |
|
The Creek at Qualchan Golf Course |
138 |
135 |
|
MeadowWood Golf Course |
144 |
141 |
|
Liberty Lake Golf Course |
125 |
123 |
|
Painted Hills Golf Course |
89 |
87 |
|
Sundance Golf Course Inc. |
87 |
85 |
|
Valley View Golf Course |
61 |
60 |
|
TOTAL |
2,046 |
2,005 |
To evaluate the geographical distribution of reuse demand from golf
courses, the courses listed in Table 5‑10 were separated into six
regions:
·
North Spokane: Wandermere
·
East County: Valley View, Liberty Lake, MeadowWood
·
South Spokane: Manito, The Creek at Qualchan
·
Central Spokane: Indian Canyon, Downriver
·
Esmeralda
·
Painted Hills
The projected reuse demand for the golf courses within each region is
presented in Table 5‑11.
The Spokane Country Club was excluded from the demand projections based
upon discussions with a representative from the club, who indicated that
they irrigate using water from a private well, have very low irrigation
costs, and are not likely to consider replacing this source with treated
effluent.
The County Parks department would be willing to use reclaimed effluent for
irrigation of County-owned golf courses; however, two of their courses
(Liberty Lake and MeadowWood) are located in an area that is being annexed
by Liberty Lake and is within the Liberty Lake Water and Sewer District.
The County could implement reuse for irrigation of these courses if it
maintains ownership of them; however, the Liberty Lake Water and Sewer
District may also be interested in irrigating these courses if it has
trouble expanding its discharge to the Spokane River.
Table
5‑11.
Monthly Irrigation Demand for Golf Courses