At the initiation of this wastewater facilities planning effort,
background information was gathered on service area definition and
characteristics, population and land use projections, existing wastewater
flows and loadings, regulatory requirements, surface and ground water
resources, and capabilities of existing wastewater conveyance and
treatment facilities. From the background information, projections of
future wastewater flows and loadings were developed. This information was
compiled and issued as Spokane County Wastewater Facilities Plan, Draft
Basis of Planning Report,
[i]
in December 2000. In conjunction with release of the Draft Wastewater
Facilities Plan, the preliminary work has been updated and is being
reissued as the Final Basis of Planning Report
[ii]. The text
below presents a summary of the Final Basis of Planning Report.
The Basis of Planning Report provides the foundation for subsequent
identification, evaluation and selection of appropriate wastewater
management strategies. It identifies the goals and objectives of the
planning process, describes the current characteristics of the planning
area, projects future wastewater flows and loadings, defines key water
quality and water resource issues, reviews the capabilities of existing
wastewater systems, and presents insight into the values and concerns of
interested stakeholders.
Chapter 1 of the Basis of Planning Report describes the goal,
objectives, and planning elements for the development of the Facilities
Plan and EIS. At the outset of the planning process, the following goals
were established to guide development of a successful wastewater
management program for Spokane County:
·
Provide reliable wastewater service – both near-term
(20-years) and long-term (50-years)
·
Protect public health
·
Protect and improve the region’s water resources – surface
water and groundwater
·
Provide cost-effective solutions for County ratepayers
·
Provide for growth in concurrence with the Growth Management
Act
·
Ensure the County has adequate authority and control to meet
future wastewater needs
·
Gain approval by the public, elected officials and
regulatory agencies
To support these goals, the project team also identified a range of
project objectives. The objectives describe specific measures of success
used to guide the project and gauge its outcome.
The Basis of Planning report is just one element of the County’s current
wastewater planning efforts. A Comprehensive Wastewater Master Plan (CWMP)
Update is being prepared under a separate contract by Engineering and
Economic Services. The demographic and flow projections developed in the
CWMP Update serve as the basis for the flow and loading projections
presented in the Basis of Planning Report. The County is also working to
develop a new interlocal agreement with the City. Key areas of focus will
be the future allocation of capacity at the SAWTP and within the City’s
conveyance system, methodologies for equitable cost sharing, and the
responsibilities and rights of the City and County. Finally, this report
will serve as a springboard for development of the Wastewater Facilities
Plan and Programmatic Environmental Impact Statement (EIS). These
documents will provide the County with a recommended wastewater management
strategy that meets both near-term (20 year) and long-term (50 year)
needs, and is environmentally responsible.
The planning area comprises many varying features, which impact wastewater
management and treatment. These characteristics are described in Chapter
2 of the Basis of Planning.
The planning area for this facilities plan consists of two landmasses: one
located in North Spokane and one located in the Spokane Valley (see
Drawing 2-1. Planning Area). The 20-year boundaries for these
planning areas are defined by the Draft Urban Growth Area (Draft UGA) and
the service boundaries between the County and the nearby City of Spokane
and Liberty Lake Sewer and Water District No. 1. The Draft UGA was
established as part of the County’s on-going long-range planning, and has
yet to be approved by the Spokane County Board of County Commissioners.
While the Facilities Plan will examine infrastructure requirements for a
50-year planning horizon, this is a longer horizon than the Growth
Management Act (GMA) requires public agencies to consider. However, it is
assumed that only areas contiguous with the Draft UGA will be served in
the future by the County’s wastewater program.
Spokane County is located in northeastern Washington adjacent to the Idaho
border. While the County has an array of landscapes ranging from the
mountainous area in the northeast to the semiarid basalt plains in the
southwest, the planning area is nearly all urban landscapes with flat to
moderately rolling hills. The climate in the planning area is relatively
temperate, with average monthly temperatures ranging from approximately 30
degrees F in January to just over 70 degrees F in July. Precipitation is
relatively low, averaging 17 to 21 inches per year and ranging from
approximately ½-inch to 2.5 inches per month. Soils in the planning area
are porous with low water-holding capacity, although soils in the
southeastern and northern parts of the County are fine- to medium-textured
with moderate to slow permeability. These areas support much of the
County’s farming.
Many significant water resources are located in and around the planning
area (Drawing
2-2. Surface and Ground Water Sources). By far, the most significant
groundwater resource is the Spokane Valley-Rathdrum Prairie Aquifer, which
serves as a source of drinking water for over 400,000 people. In the
planning area, the aquifer is recharged along its margin on all sides from
percolation through porous soils overlying the aquifer and through seepage
from the Spokane River. Because of its importance as a primary drinking
water source, the United States Environmental Protection Agency has
declared the aquifer a “sole source” aquifer. Many other aquifers, most of
them also drinking water sources, are located within the County. Because
of the high permeability of soils overlying much of the aquifer,
contamination by surface and subsurface activities is always a primary
concern.
In addition to its rich groundwater resources, Spokane County has many
surface water bodies that provide a variety of economic, recreational and
aesthetic benefits and uses. The Spokane River is the principal surface
water body in the planning area. It begins in Idaho at Lake Coeur d’Alene
and flows west through Washington and finally into Long Lake. Various
reaches of the river gain water from or lose water to the Spokane Rathdrum
Aquifer. This interaction is also observed in lower segments of the
Little Spokane River, which originates north of Spokane County and flows
south to Long Lake. The other primary surface water feature in the
planning area is Latah Creek, which originates in Benewah County, Idaho
and flows north to a confluence with the Spokane River at the west side of
the City of Spokane.
Growth in Spokane County has increased since 1890, with a steady increase
of approximately 2 percent per year since 1940. The current (1999)
population in the County is 414,000, of which 121,000 are located within
the planning area and over 58,000 are currently served by the County’s
sewer system.
Land use within the planning area is primarily urban residential, with the
City of Spokane and surrounding areas providing the economic and cultural
center for much of eastern Washington and northern Idaho. This change has
largely occurred over the last 60 years as orchards and vegetable farming
were replaced by urban uses. This conversion of land use resulted from
accessibility to roads, a dependable supply of water, and level land
characteristics with few physical constraints to development. Prime
farmland still exists directly north of the planning area, and on the
western and southeastern boundaries of the County.
A wide range of governmental agencies have interest in wastewater
management issues in Spokane County. These agencies span many
jurisdictional levels: local, regional, state and federal. Local
wastewater service providers include the County, the City of Spokane, the
Town of Millwood, and the Liberty Lake Sewer and Water District. Many
other agencies have an interest in the facility plan because of their
regulatory functions, responsibility for facilities located within the
watershed, interest in the surface and groundwater resources, or ability
to impact development or implementation of the plan.
Chapter 3 of the Basis of Planning Report summarizes planning projections
for three planning horizons: 2020, which coincides with the planning
horizon used in Spokane County’s Growth Management Plan; 2025, which
provides the County with a 20-year management strategy after the
recommended plan has been implemented; and 2050 for long-range planning.
Planning projections include the following three primary elements:
·
Population and land use forecasts
·
Wastewater flow projections
·
Wastewater loading projections
Planning projections established in the Basis of Planning Report
rely on projections of population growth and development of industrial and
commercial properties developed through the CWMP Update. These projections
account for current users of the system, existing residents and
commercial/industrial facilities within the current Urban Growth Area that
have not yet been connected to the County’s system (i.e., are served by
septic tanks), and new development within the planning area. These
projections are shown in Figure 2‑1.


Figure
2‑
1. Population and
Commercial/Industrial
Development Projections
Wastewater flow projections include both base sanitary flow from
residences, businesses, institutions, and industrial establishments, and
extraneous flow (groundwater or stormwater) that enters the separated
sewer system. Minimal amounts of infiltration and inflow (I/I) exist in
the County collection system. Average flow projections were calculated by
starting with the 1999 base flow determined through meter readings at
three City/County connections, and adding:
·
Future residential, commercial, and industrial sanitary flow
based on the population and land use estimates reflected in Figure 2‑1,
and
·
Inflow and infiltration (I/I) estimated at 2 gallons per
capita per day (gpcd) in 2000, increasing to 10 gpcd in 2020, and
remaining steady at 10 gpcd through 2050.
·
Total County average wastewater flow is projected to
increase to 20.6 mgd by 2020, 21.9 mgd by 2025, and 27.3 mgd by 2050.
These values were summed to generate the total flow projection shown in
Figure 2‑2. Flow peaking factors were evaluated to determine the
maximum month, week, day, and peak instantaneous flow.

Figure
2‑2. Wastewater
Flow Projections
Wastewater loading projections reflect a combination of the baseline flows
described above, unit loading rates, and peaking factors that reflect
maximum month, week, and day conditions. To develop a reasonable
projection of future wastewater loadings, an assessment of County and City
data was supplemented by a review of other local wastewater utilities with
generally similar service area characteristics. Average concentrations
for utilities in the area are generally lower than literature values.
Because the County’s data are limited (quarterly sampling has been
conducted over three years), the Facilities Plan will be developed using
literature unit loading values. However, it is recommended that the
County’s recently implemented sampling program be continued to generate
more reliable local data. An allowance for septage (septic tank solids)
loadings has also been included. Wastewater peaking factors were
developed based on the average peaking factors for other communities in
the area. The final projected wastewater loadings are shown in Table
2‑1.
Table
2‑1.
Projected Wastewater Loadings
|
Year |
BODa,b |
Total Suspended Solidsa,b |
Total Nitrogena,b |
Total Phosphorusa,b |
|
Average Day,
1,000 lb/day |
Maximum Month, 1,000 lb/day |
Maximum Week, 1,000 lb/day |
Maximum Day, 1,000 lb/day |
Average Day,
1,000 lb/day |
Maximum Month, 1,000 lb/day |
Maximum Week, 1,000 lb/day |
Maximum Day, 1,000 lb/day |
Average Day,
1,000 lb/day |
Maximum Month, 1,000 lb/day |
Maximum Week, 1,000 lb/day |
Maximum Day, 1,000 lb/day |
Average Day,
1,000 lb/day |
Maximum Month, 1,000 lb/day |
Maximum Week, 1,000 lb/day |
Maximum Day, 1,000 lb/day |
|
Peaking Factorc |
|
1.2 |
1.5 |
2.7 |
|
1.3 |
1.6 |
2.7 |
|
1.2 |
1.5 |
2.0 |
|
1.2 |
1.5 |
2.7 |
|
1999 |
14 |
17 |
26 |
71 |
14 |
18 |
23 |
38 |
2.8 |
3.3 |
4.1 |
5.5 |
0.43 |
0.52 |
0.62 |
1.15 |
|
2000 |
16 |
19 |
29 |
80 |
16 |
20 |
26 |
43 |
3.1 |
3.7 |
4.6 |
6.1 |
0.48 |
0.58 |
0.70 |
1.29 |
|
2005 |
26 |
31 |
48 |
129 |
27 |
35 |
44 |
74 |
4.8 |
5.8 |
7.2 |
9.6 |
0.78 |
0.95 |
1.14 |
2.11 |
|
2010 |
34 |
42 |
64 |
173 |
36 |
46 |
58 |
98 |
6.5 |
7.7 |
9.7 |
12.9 |
1.05 |
1.27 |
1.53 |
2.82 |
|
2015 |
44 |
54 |
82 |
222 |
46 |
59 |
74 |
125 |
8.3 |
9.9 |
12.5 |
16.6 |
1.34 |
1.63 |
1.96 |
3.63 |
|
2020 |
48 |
58 |
88 |
239 |
49 |
63 |
79 |
134 |
8.9 |
10.7 |
13.4 |
17.8 |
1.44 |
1.75 |
2.11 |
3.89 |
|
2025 |
50 |
61 |
93 |
251 |
52 |
66 |
83 |
140 |
9.4 |
11.2 |
14.1 |
18.7 |
1.51 |
1.84 |
2.21 |
4.08 |
|
2030 |
52 |
64 |
97 |
263 |
54 |
69 |
87 |
147 |
9.9 |
11.8 |
14.8 |
19.6 |
1.58 |
1.92 |
2.31 |
4.28 |
|
2035 |
55 |
67 |
101 |
275 |
56 |
72 |
91 |
153 |
10.3 |
12.3 |
15.5 |
20.5 |
1.65 |
2.01 |
2.42 |
4.47 |
|
2040 |
57 |
70 |
106 |
286 |
59 |
75 |
95 |
159 |
10.8 |
12.8 |
16.2 |
21.5 |
1.73 |
2.09 |
2.52 |
4.66 |
|
2045 |
59 |
73 |
110 |
298 |
61 |
78 |
98 |
166 |
11.2 |
13.4 |
16.9 |
22.4 |
1.80 |
2.18 |
2.63 |
4.85 |
|
2050 |
62 |
75 |
115 |
310 |
64 |
81 |
102 |
172 |
11.7 |
13.9 |
17.5 |
23.3 |
1.87 |
2.27 |
2.73 |
5.04 |
Notes
a
Loadings based on data from other local sewer utilities with similar
service area characteristics.
b
Loadings include septage. 60 percent of 1999 SAWTP septage
loading assumed to be diverted to County facilities commencing in 2005.
Septage loads not assumed to increase.
c
Peaking factors are based on other communities
Chapter 4 of the Final Basis of Planning Report reviews the
characteristics of key water resources that may be impacted by the
County’s wastewater management program – the Spokane Valley-Rathdrum
Prairie Aquifer, and the Spokane and Little Spokane Rivers. These water
bodies comprise the major components of a large,
hydraulically-interconnected water system in the Spokane region. As such,
actions affecting one of the resources may have direct or indirect impacts
on the other resources as well. The chapter also reviews regulations.
Water quality issues and other factors that will shape quality
requirements for discharge of effluent to receiving waters, beneficial
reuse of effluent and beneficial reuse of biosolids.
The prolific exchange of surface water and groundwater through the
hydraulic connection between the rivers and the aquifer can have
significant implications with regard to the quality and quantity of the
surface and groundwater resources in the County. Permits for water
purveyors using the Spokane aquifer total 1,009 cfs, which is approaching
the natural supply of the aquifer and may actually exceed the aquifer’s
ability to meet demand. If more groundwater is pumped than is available,
the water table will be lowered and flow in the Spokane and Little Spokane
rivers may decrease. With minimum stream flows in these rivers established
by state regulation and by recommendations of the Washington Department of
Fish and Wildlife, and with ongoing watershed planning in the state, the
future may see a situation where little or no “new” water will be
available for consumptive use.
Water quality in the aquifer has been monitored routinely for the past 20
years. This data shows that while the quality of water in the aquifer is
generally good to excellent, the aquifer is clearly impacted by
development. In unsewered areas with residential and commercial
development, clear trends exist toward increasing contaminant
concentration in some wells. Stormwater injection through drywells also
leads to degradation of water quality. On a positive note, in areas where
sewering has occurred and/or development has slowed or stopped,
contamination levels have fallen.
The surface water features of interest in the planning area – the Middle
Spokane River (from Nine Mile Bridge to the state line), the Little
Spokane River, and Long Lake – are designated for “characteristic uses”
such as water supply; stock watering; fish and shellfish rearing,
spawning, and harvesting; wildlife habitat; primary contact recreation;
and commerce and navigation. To preserve the designated characteristic
uses, in stream water quality must comply with the numerical and narrative
guidelines given in the Washington State Surface Water Quality Standards.
Water quality standards for the Spokane and Little Spokane River system
are established for fecal coliform, dissolved oxygen, total dissolved gas,
temperature, pH, turbidity, toxic materials, radioactive materials,
aesthetics, and nutrients. There are currently seven permitted point
source discharges to the Spokane River between Coeur d’Alene Lake and Long
Lake, and two point source discharges to the Little Spokane River.
Potential effluent quality requirements for new surface water discharges
in the study area are impacted by the water quality standards described
above, and by Total Maximum Daily Loads (TMDLs), which have been
established or are being established to address identified water quality
limitations. Table 2‑2 below shows likely effluent quality
requirements for discharge of wastewater to the Spokane or Little Spokane
Rivers. Actual values will be determined by Ecology through the NPDES
program, and the County must be able to demonstrate that the effluent
discharge will allow the receiving water to meet water quality standards.
Consequently, the values shown in Table 2‑2 must be regarded as
speculative at this time.
Table
2‑2. Potential
Effluent Quality Requirements
|
|
Spokane River |
Little Spokane River |
|
Parameter |
Summer |
Winter |
Summer |
Winter |
|
BOD, mg/La |
10-20 |
30 |
10-20 |
30 |
|
Total Suspended Solids, mg/L |
30 |
30 |
30 |
30 |
|
Ammonia-Nitrogen, mg/La,b |
1-2 |
4-8 |
1-2 |
4-8 |
|
Total Nitrogen, mg/L |
No limit |
No limit |
No limit |
No limit |
|
Total Phosphorus, mg/Lc |
0.3-0.6 |
No limit |
0.3-0.6 |
No limit |
|
Dissolved Oxygen, mg/La |
>6.0 |
No limit |
>6.0 |
No limit |
|
Fecal Coliform, cfu,100 mL |
200 |
200 |
200 |
200 |
|
Chlorine Residual, mg/Lb |
8 |
8 |
8 |
8 |
|
pH (s.u.) d |
6.0-7.8 |
6.0-7.8 |
6.0-7.8 |
6.0-7.8 |
|
Lead, mg/Ld |
2 |
2 |
2 |
2 |
|
Zinc, mg/Le |
60 |
60 |
60 |
60 |
|
Cadmium, mg/Le |
0.2 |
0.2 |
0.2 |
0.2 |
1.
a.
Required value will be defined by dissolved oxygen TMDL process.
2.
b.
Required value will be defined by mixing zone study for toxicity.
3.
c
Required value will be defined through negotiation with Phosphorus TAC.
4.
d
Instantaneous value.
5.
e
Required value will be defined based on monitoring of actual effluent
metals concentration.
With appropriate levels of treatment and system management, reclaimed
water has been used successfully for many applications. Reuse programs in
the study area must consider the state’s guidance provided in the Water
Reclamation and Reuse Standards, which outlines four classes of reclaimed
water that can be used for different applications. These range from Class
A water, which has the most stringent treatment requirements but minimal
restrictions on use, to Class D water which has limited uses which must be
accompanied by strict controls to minimize human contact. Reuse must also
be protective of groundwater quality. Potential reuse opportunities and
some of their considerations are listed below.
Irrigation: Water quality requirements are typically impacted by
the opportunity for human contact, the opportunity for contact with food
for human consumption, and the level of sterilization the food crop will
receive before reaching the consumer. The classification of the reclaimed
water (A through D) as well as management practices impact acceptable
reuse for irrigation.
Impoundments: Restrictions on the use of reclaimed water in
impoundments varies depending on the level of treatment the water has
received.
Industrial and Commercial Applications: Class D reclaimed water can
only be used for sanitary sewer flushing, whereas Class A reclaimed water
has a variety of potential industrial and commercial applications.
Additional treatment requirements may be imposed by the specific needs of
the end user.
Wetlands: The Washington reuse standards establish conditions under
which reclaimed water may be used to create or enhance wetlands. Natural
or constructed wetlands that receive reclaimed water are considered waters
of the State, and are differentiated from treatment wetlands, which are
considered part of the wastewater treatment process and not waters of the
State. In addition to the designated reclaimed water classes, Washington
uses restrictions on total suspended solids (TSS), nutrients, and metals
to assure that water quality in the constructed wetlands and any
downstream waters of the State are protected.
Streamflow Augmentation: This application is defined as use of
reclaimed water for a beneficial purpose such as in-stream flow
enhancement, irrigation supply, water right replenishment, and fisheries
propagation, and must meet the requirements of the federal water pollution
control act.
Groundwater Recharge: Both surface percolation and direct injection
of reclaimed water require a minimum of Class A reclaimed water quality.
Additional nitrogen reduction must be provided for surface percolation,
and direct injection to a potable aquifer requires significant additional
treatment beyond that needed for the Class A designation.
Land application, composting and land filling are the biosolids management
techniques typically used in Eastern Washington and Northern Idaho. These
uses are regulated by Ecology using rules which closely follow those
promulgated by the U.S. EPA under 40 CFR 503 (“Part 503 regulations”).
These regulations use three measures to determine the level of restriction
placed on the application practice: (1) concentration of trace elements,
(2) quantity of pathogens, and (3) vector attraction. Several degrees of
pathogen reduction are recognized, with associated differences in the
level of restriction placed on reuse of the treated biosolids.
The County’s wastewater management facilities are integrated into a
regional network of conveyance and treatment facilities serving the
greater Spokane area. A simplified schematic of the regional network is
shown in Figure 2‑3.

Figure
2‑3.
Simplified Schematic of Regional Collection and Treatment Facilities for
Municipal Wastewater
Figure 2‑3 reflects that the County’s interceptor system receives
flow from the City of Millwood, and has agreed to accept “excess” flow
from the Liberty Lake Sewer and Water District No. 1. All flow from these
dischargers and from most sewered areas of the County are treated at the
City of Spokane Advanced Wastewater Treatment Plant (SAWTP) and discharged
to the Spokane River.
Through the end of 1999, the County’s collection system included 270 miles
of sewer. These sewers serve two distinct systems, one serving Spokane
Valley and one serving North Spokane. The Spokane Valley system includes
two main interceptors that discharge to the City’s collection system: the
Spokane Valley Interceptor (SVI) which serves the area south of Interstate
90, and the North Valley Interceptor (NVI) which serves the area north of
Interstate 90. Because of the topography of the North Spokane area, five
major pumping stations are used to lift wastewater to the City’s
collection system. Flow from these pumping stations is combined in a
single interceptor that discharges to the City.
Through a 1980 interlocal agreement, Spokane County purchased capacity in
the City’s collection system to convey 10 mgd of County wastewater to the
SAWTP. If the County needs to send wastewater flows in excess of its
current capacity allowance, improvements to the City’s collection system
will be needed. However, the nature, cost, and implementation time frame
for these improvements will be determined in part by the City’s on-going
combined sewer overflow (CSO) planning effort.
The City of Spokane collection system consists of 290 miles of separated
sanitary sewer, 130 miles of storm sewer and 400 miles of combined sewer.
In the 1980s, the City implemented a major sewer separation program that
reduced the annual volume of CSO discharge by approximately 85 percent.
Despite these measures, CSOs continue to occur at a frequency that exceeds
State requirements. Currently, the system has 30 CSO regulating
structures and 24 potential CSO discharge points. In 1994, the State
approved a City plan to further eliminate CSOs, but the City delayed
implementation of the improvements. A new implementation schedule was
approved by the State in March 1999, giving the City until 2017 to meet
the State’s CSO requirements. (Ecology, 2000) However, the City is now
conducting a further multi-year study to revisit its approach to CSO
control. It is anticipated that the recommendations of the new study may
substantially change the 1999 implementation plan. Consequently, the
future configuration and capacity of the City collection system remains
unclear and may not be defined for an additional two to three years.
Through a 1980 interlocal agreement, Spokane County purchased capacity in
the City collection system to convey 10 mgd of County wastewater to the
SAWTP. The original agreement provided “dry-weather” capacity to the
County, requiring the County to implement flow equalization or other flow
control measures during wet-weather periods when flows from the City’s
combined system exceed the hydraulic capacity of the interceptor system.
In 1983, the City and County amended the interlocal agreement to provide
the County with 10 mgd of “wet-weather” conveyance capacity for service to
the Spokane Valley. In exchange, the County agreed to pay for sewer
separation projects in the Trent and Mallon basins and installation of a
sewer to bypass the Hartson collection system.
The City’s ability to convey future County flows, beyond the current
capacity allocation, is impacted by hydraulic limitations in several
interceptor sections and the City’s need to maximize conveyance and
treatment of flows generated in its combined system. According to the
City’s Wastewater Facilities Plan, the interceptors that appear to have
the most significant capacity constraints in the near term are the South
River and North River Interceptors. In addition, the North River-Bridge
Interceptor is nearing its capacity during peak flows. (City of Spokane,
1999) Finally, there may be hydraulic limitations in the City pipelines
that convey County flow from North Spokane to the SAWTP, although this
seems to a less significant constraint than the other conveyance
bottlenecks.
If the County needs to send wastewater flows in excess of its current
capacity allowance, improvements to the City collection system will be
needed. Unfortunately, the nature, cost and implementation time frame for
these improvements may not be identified until the City completes its
on-going CSO planning effort. Consequently, this information may not be
available in sufficient time for use in the County’s facility planning
effort.
Nearly all of the wastewater generated in the Spokane County service area
is conveyed to the SAWTP for treatment and disposal. A small portion of
the wastewater is treated at five satellite wastewater treatment
facilities that are owned and operated by the County. These treatment
facilities have capacities ranging from 22,500 to 86,000 gallons per day.
One facility is scheduled to be removed from service within 5 years; three
others will be removed from service within 20 years. The Hangman Valley
Treatment Plant is the only small facility that is planned to remain in
service for the foreseeable future.
The SAWTP is located in northwest Spokane along the north bank of the
Spokane River. It was initially constructed as a primary treatment plant
in 1958, and has since been upgraded and expanded to its current capacity
and process configuration, which includes the following:
·
Screening, flow measurement, and aerated grit removal
·
Venturi meter to split divert excess flow (over 77 mgd) to
CSO primary clarifiers, where flow is either stored and returned to the
plant for full treatment, or clarified and combined with effluent from the
secondary treatment process
·
Preaeration and primary clarification
·
Activated sludge treatment with alum addition and secondary
clarification for removal of carbonaceous BOD, TSS, ammonia-nitrogen, and
phosphorus (through process modifications, nutrient removal is only
practiced during the summer permit season)
·
Chlorination/dechlorination
·
Gravity thickening of primary sludge
·
Dissolved air flotation thickening of secondary sludge (soon
to be eliminated through solids handling improvements)
·
Anaerobic digestion
·
Belt filter press dewatering (currently being upgraded
through solids handling improvements)
Effluent from the treatment process is discharged year-round to the
Spokane River, while dewatered biosolids are beneficially used through
land application to agricultural fields in Spokane and Lincoln counties.
The plant has generally been viewed as having an average dry weather
capacity of 44 mgd and a maximum secondary treatment capacity of 77 mgd.
The preliminary treatment facilities have a design capacity of 146 mgd and
the CSO treatment system has an estimated capacity of 70 mgd. This
capacity is being re-evaluated in light of a new NPDES permit, which was
issued in March of 2000. This permit included changes in the
ammonia-nitrogen and metals discharge criteria. Preliminary results of
this current investigation indicate that near-term capacity bottlenecks
will occur in the solids handling and activated sludge processes. A phased
solids handling improvements program has been approved by the City, and
will be completed in 2004.
Stakeholders from various sectors of the community were interviewed during
the Basis of Planning phase to gain an understanding of the various
community priorities, issues and concerns regarding wastewater management.
The objective was to understand the variety of community issues early in
the planning process so they could be considered during the review and
identification of wastewater management alternatives.
Twenty-two representatives from various agency, business association,
development, industry, environmental, and neighborhood stakeholder groups
were interviewed during the summer of 2000. A set of fourteen questions
were asked, and the following summarizes the comments:
·
Most of those interviewed felt the County has been providing
good sewer service, however, concerns were raised regarding the current
City/County wastewater management arrangement. There was strong support
for both the County expanding its wastewater management services and for
developing a comprehensive regional wastewater management approach.
·
The top wastewater priorities were public health,
aquifer/drinking water protection, and Spokane River water quality
protection.
·
Support was expressed for a new effluent discharge to the
Spokane River; use of the Liberty Lake treatment plant; use of reclaimed
wastewater for agricultural irrigation, urban irrigation, creation of
wetlands, and underground storage for irrigation or stream flow
augmentation. However, there were varied opinions and concerns regarding a
new effluent discharge to Little Spokane River, and using highly treated
wastewater for irrigation of school and park landscapes. The majority of
those interviewed felt recharge of the Spokane Aquifer with treated
effluent would not be a viable option due to public health concerns and
public perceptions.
·
Most supported recycling of
treated effluent and biosolids, with some concerns expressed, and most
indicated they would pay more to achieve recycling benefits. Half of those
interviewed supported including recreational enhancements at new
wastewater treatment facilities, and many ideas were shared on how the
County might increase public benefit from new facilities.

[i]
Spokane County, Wastewater Facilities Plan, Draft Basis of Planning
Report, HDR Engineering, December 2000.
[ii]
Spokane County, Wastewater Facilities Plan, Final Basis of Planning
Report, HDR Engineering, October 2001.