To plan for future wastewater facility needs, it is necessary to project
the amount of wastewater that will be received and treated. The served
population, the magnitude of commercial and industrial activities, and
the quantity of extraneous flow, such as sewer system infiltration and
inflow, all influence wastewater quantity. To define required treatment
facilities, it also is necessary to define the projected wastewater
strength for such constituents as organic content and nutrients
(nitrogen and phosphorus). These characteristics help define the type
and size of facilities needed for liquid treatment and solids handling
processes. In this chapter, projected flows and loadings are developed
for both 20-year and 50-year planning horizons.
Wastewater facilities are typically planned for the service area
characteristics that will develop over a period of 20 years; however,
consideration of a longer planning period is useful to assess the
long-term feasibility of wastewater management strategies and to
identify land requirements for future expansion of facilities. For this
facilities plan, three planning horizons will be used: 2020, 2025 and
2050.
Year 2020 coincides with the planning horizon used in Spokane County’s
Growth Management Plan. Use of this planning year is needed to ensure
concurrency between the wastewater facilities plan and the Growth
Management Plan.
Spokane County Utilities has requested use of a Year 2025 planning
horizon when developing and comparing alternative wastewater management
strategies. The basis for this planning year is Utilities desire to
have a “20-year solution” once the recommended plan is implemented. It
is estimated that implementation (planning, design, construction) will
take about five years. This approach is consistent with the Washington
State Department of Ecology’s Criteria for Sewage Works Design
[i],
which require that the wasteload estimated for the 20-year horizon be
considered when selecting a wastewater management approach. The 20-year
period coincides with the anticipated life of major treatment process
equipment.
Use of a Year 2050 planning horizon will allow a “long-term” view of
wastewater management scenarios and allow planning for future
infrastructure, programmatic and land acquisition activities.
Realistic projections of population growth and development of industrial
and commercial properties provide the foundation for wastewater flow and
loading projections. Population and land use forecasts for 20-year and
50-year horizons were developed as part of the Year 2001
Comprehensive Wastewater Management Plan for Spokane County (CWMP)
[ii].
Table 3‑1 and Table 3‑2 present the results of these
projections and the subsequent discussion provides a summary of key
assumptions used. The reader is referred to the CWMP for a detailed
discussion of the forecasting methodology.
Table
3‑1.
Population Projections
|
Year |
Existing Population Served |
Population Growth Infill |
Population Increase, Sewer
Program Areas |
Population Increase, Non-Program
Areas |
Total Population Served |
|
1999 |
58,318 |
0 |
0 |
0 |
58,318 |
|
2000 |
58,318 |
1,906 |
3,635 |
0 |
63,859 |
|
2005 |
58,318 |
11,439 |
21,808 |
281 |
91,845 |
|
2010 |
58,318 |
20,971 |
39,981 |
1,688 |
120,958 |
|
2015 |
58,318 |
30,504 |
58,154 |
3,095 |
150,070 |
|
2020 |
58,318 |
40,036 |
58,154 |
4,502 |
161,010 |
|
2025 |
58,318 |
49,568 |
58,154 |
4,502 |
170,542 |
|
2030 |
58,318 |
59,101 |
58,154 |
4,502 |
180,074 |
|
2035 |
58,318 |
68,633 |
58,154 |
4,502 |
189,607 |
|
2040 |
58,318 |
78,166 |
58,154 |
4,502 |
199,139 |
|
2045 |
58,318 |
87,698 |
58,154 |
4,502 |
208,671 |
|
2050 |
58,318 |
97,230 |
58,154 |
4,502 |
218,204 |
|
Note: |
a |
b |
c |
d |
e |
a Estimated population
served by County sewers as of December 1999
b Growth projected to
occur within the sewer service area
c Population within
current sewer program area. This population is assumed
to become sewered
starting in 2000 and to be completely served by 2015
d Population outside
the current sewer program area. This population is assumed
to become sewered
starting in 2005 and to be completely served by 2020.
e Sum of Columns a
through d
Table
3‑2.
Projected Commercial and Industrial Development
|
Year |
Existing Commercial/
Industrial Area, acres |
Future Commercial Area, acres |
Future Industrial Area, acres |
Combined Total Commercial/
Industrial Area, acres |
|
1999 |
1,265 |
0 |
0 |
1,265 |
|
2000 |
1,265 |
55 |
239 |
1,560 |
|
2005 |
1,265 |
332 |
1,435 |
3,033 |
|
2010 |
1,265 |
609 |
2,632 |
4,506 |
|
2015 |
1,265 |
886 |
2,898 |
5,049 |
|
2020 |
1,265 |
1,163 |
3,164 |
5,592 |
|
2025 |
1,265 |
1,225 |
3,333 |
5,823 |
|
2030 |
1,265 |
1,287 |
3,502 |
6,055 |
|
2035 |
1,265 |
1,350 |
3,671 |
6,286 |
|
2040 |
1,265 |
1,412 |
3,841 |
6,517 |
|
2045 |
1,265 |
1,474 |
4,010 |
6,749 |
|
2050 |
1,265 |
1,536 |
4,179 |
6,980 |
|
Note: |
a |
b |
c |
d |
a Estimated combined commercial/industrial
acreage served by County sewers as of
December 1999. Calculated from existing
Equivalent Residential Unit (ERU) data.
b From CWMP, based on Spokane County Long-Range
Planning Department Information.
c From CWMP, based on Spokane County Long-Range
Planning Department Information.
d Sum of columns a through c
As described in Chapter 2, the planning area for this study is the
Interim Urban Growth Area (IUGA). Major portions of the planning area
have been sewered by the County as part of the Septic Tank Elimination
Program (STEP). In December 1999, the estimated residential and
commercial/industrial developments connected to the County sewer were:
§
Residential population: 58,318
§
Commercial/industrial acreage: 1,265
This currently sewered area, and its resultant wastewater flow,
represent the “Current Base Condition” from which future projections
will be developed.
A key planning assumption is that during the next twenty years, sewers
will be extended to serve the entire planning area. In doing this, the
County will provide service to existing residential, commercial
and industrial development that are currently on septic tanks. This
affects two portions of the planning area:
§
Sewer Program Areas: Areas within the current sewer
program that become sewered starting in 2000 and are completely served
by 2015.
§
Non-Program Areas: Areas outside the current sewer
program that become sewered starting in 2005 and are completely served
by 2020.
For both areas, the CWMP provides estimates of (1) the amount of
current, unsewered development, and (2) the schedule for connecting
these existing developments to the collection system.
Projections of population growth and future development of commercial
and industrial properties are based on the forecasts presented in the
Spokane County Comprehensive Plan – Draft Plan 2000. Key assumptions
and observations are presented below.
Residential. The residential population growth within the
service area is projected to be 40,036 between 1999 and 2020.
Commercial. Projected commercial development is based the vacant
commercial property identified in the Draft 2000 Plan. A uniform rate
of development has been assumed for the next 20 years.
Industrial. Projected industrial development is based on the
vacant industrial property identified in the Draft 2000 Plan. It has
been assumed that properties within “Tiers 1 and 2” will be developed
between 2000 and 2020, and that properties within “Tier 3” will be
developed between 2010 and 2020.
In addition, an assumption was made that two “wet industries” would be
located within the planning area between 2011 and 2015 – one in the
North Valley service area and one in the Spokane Valley service area.
Beyond 2020, several simplifying assumptions were used to project
population and land use development:
§
The mix of residential, commercial and industrial
development in the years 2021 through 2050 will be the same as that in
2020 (i.e., all will increase at the same rate).
§
A straight-line annual growth rate (approximately 1.6
percent, based on the Year 2020 baseline) will occur for residential,
commercial and industrial contributions. This growth rate coincides
with the population growth rate from 1999 to 2020.
§
No further allowances for wet industries.
This section summarizes the development of flow projections for the
entire planning area.
As a preface to the discussion of flow projections, it is useful to
define the key terms employed:
General Classifications of
Wastewater by Source
Base Sanitary Flow
includes water-carried wastes from residences, businesses, institutions,
and industrial establishments. It consists of the following components:
§
Domestic Wastewater
is that wastewater which is principally derived from the sanitary
conveniences of residences or produced by normal residential
activities.
§
Commercial
Wastewater is that
wastewater which is generated in predominantly business or commercial
districts, including not only sanitary wastes but also wastes from the
commercial activities themselves. Typically, commercial wastewater
might include wastes from restaurants, laundromats, and service
stations.
§
Industrial
Wastewater is generated
from all activities conducted at industrial establishments.
Extraneous Flows consist of groundwater or stormwater that enters
the collection system. This overall classification of flows may be
divided into the following components:
§
Infiltration results from the unintentional entry
of water into the wastewater collection systems from the surrounding
soil. Common points of entry include broken pipes and defective joints
in the pipe or in walls of manholes. Infiltration may result from
sewers being laid below the groundwater table or from saturation of the
soil by rain or irrigation water. Infiltration usually varies
seasonally depending on precipitation or irrigation trends.
§
Direct Stormwater Inflow consists of rainwater that
enters the collection system through roof and patio drain connections,
catch-basin connections, and holes in the tops of manhole covers in
flooded streets. Occurrence of direct stormwater inflow is usually
indicated when the wastewater flow increases immediately in response to
precipitation or snowmelt.
§
Interflow, or rapid infiltration, is the entry of
infiltrated precipitation into building laterals and French drains. It
occurs as the recent precipitation percolates into the ground.
Interflow responds to precipitation on a delayed basis, and may take up
to six hours to develop after precipitation starts and may extend for
several days after precipitation ends.
Other Common Terms
Annual Average Flow is the total daily flow that occurs on average for a twelve-month
period. The period may be based on a calendar year (Jan – Dec) or a
water year (Nov – Oct).
Maximum Month Flow is the highest 30-day average flow that occurs
in a one-year period.
Maximum Week Flow is the highest 7-day average flow that occurs
in a one-year period.
Maximum Day Flow is the highest 24-hour average flow that
occurred in a one-year period.
Peak Hour Flow is the highest one-hour average flow that occurred
in a one-year period.
Dry Weather Flow
is the total wastewater flow during periods of little or no rainfall.
Rates of flow exhibit hourly, daily, and seasonal variations. A certain
amount of infiltration may be present.
Wet Weather Flow
is the total wastewater flow during periods of moderate to heavy
rainfall. Storm water inflow may increase the wet weather flow to a
rate many times greater than the dry weather flow and, unless provided
for in sewerage design, can produce hydraulic overloads resulting in
wastewater overflows to streets or watercourses.
Except for a minor amount of flow discharged to satellite treatment
facilities, Spokane County wastewater is discharged to the City
conveyance system at three points: (1) North Valley Interceptor, (2)
Spokane Valley Interceptor, and (3) North Spokane Interceptor.
Monitoring of average daily wastewater is performed at these locations.
A summary of the average daily flow for the three monitoring points for
the last six years is presented in Figure 3‑1. Nearly two-thirds
of the wastewater is generated in the area tributary to the Spokane
Valley Interceptor. Wastewater flow at each monitoring point has been
increasing annually as more homes and businesses are connected to the
sewer system. As of December 1999, average daily wastewater flow
discharged to the City of Spokane was measured to be 5.68 million
gallons per day (mgd).

Figure 3‑1.
Spokane County Wastewater Flow Monitoring
A review of the flow records for the three interceptors resulted in the
following observations:
§
There is no significant seasonal variation in flow rates.
§
On an annual basis, the volume of extraneous stormwater
and groundwater flows entering the collection system is quite low (less
than five percent of the total flow).
§
The estimated average unit flow rate in the three
interceptors is approximately 76 gallons per capita per day (gpcd).
This value falls in the lower range of typical domestic wastewater
generation rates (without infiltration and inflow) and is lower than the
100 gpcd planning value recommended in the Washington State Department
of Ecology’s Criteria for Sewage Works Design.
Projections of average annual flow rates were developed as part of the
CWMP. The results of this analysis are presented in Table 3‑3
for the full Spokane County planning area. The subsequent discussion
provides a summary of key assumptions used.
Table
3‑3.
Projected Average Flow
|
Year |
Base Flow, mgd |
Growth (In-Fill), mgd |
Commercial, mgd |
Industrial, mgd |
Sewer Program Areas, mgd |
Non-Program Areas, mgd |
Total Sanitary Flow, mgd |
Infiltration from Existing
Development, mgd |
Infiltration from New
Development, mgd |
Total Infiltration, mgd |
Total Wastewater Flow, mgd |
|
1999 |
5.68 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
5.7 |
0.00 |
0.00 |
0.00 |
5.7 |
|
2000 |
5.68 |
0.15 |
0.06 |
0.24 |
0.30 |
0.00 |
6.4 |
0.11 |
0.00 |
0.11 |
6.5 |
|
2005 |
5.68 |
0.92 |
0.33 |
1.44 |
1.79 |
0.02 |
10.2 |
0.22 |
0.02 |
0.24 |
10.4 |
|
2010 |
5.68 |
1.68 |
0.61 |
2.63 |
3.36 |
0.14 |
14.1 |
0.33 |
0.08 |
0.41 |
14.5 |
|
2015 |
5.68 |
2.44 |
0.89 |
3.90 |
5.00 |
0.26 |
18.2 |
0.43 |
0.18 |
0.62 |
18.8 |
|
2020 |
5.68 |
3.20 |
1.16 |
4.16 |
5.12 |
0.39 |
19.7 |
0.54 |
0.32 |
0.86 |
20.6 |
|
2025 |
5.68 |
3.97 |
1.23 |
4.33 |
5.23 |
0.40 |
20.8 |
0.54 |
0.50 |
1.04 |
21.9 |
|
2030 |
5.68 |
4.73 |
1.29 |
4.50 |
5.23 |
0.40 |
21.8 |
0.54 |
0.59 |
1.13 |
23.0 |
|
2035 |
5.68 |
5.49 |
1.35 |
4.67 |
5.23 |
0.40 |
22.8 |
0.54 |
0.69 |
1.23 |
24.1 |
|
2040 |
5.68 |
6.25 |
1.41 |
4.84 |
5.23 |
0.40 |
23.8 |
0.54 |
0.78 |
1.33 |
25.2 |
|
2045 |
5.68 |
7.02 |
1.47 |
5.01 |
5.23 |
0.40 |
24.8 |
0.54 |
0.88 |
1.42 |
26.2 |
|
2050 |
5.68 |
7.78 |
1.54 |
5.18 |
5.23 |
0.40 |
25.8 |
0.54 |
0.97 |
1.52 |
27.3 |
|
|
a |
b |
c |
d |
e |
f |
g |
h |
i |
j |
k |
1.
NOTES:
a Base Flow: Average daily flow for 1999, including current
infiltration, is based on meter readings at three City/County
connections and reflects flows from customers existing at that time.
b Sanitary wastewater flow increase due to study area growth
identified in Table 3-1, at 90 gpcd.
c Sanitary flow from the new commercial acreage identified in
Table 3-2, at 1,000 gpad.
d Sanitary flow from the new industrial acreage identified in
Table 3-2, at 1,000 gpad.
e Sanitary wastewater from sewer program population identified in
Table 3-1, at 90 gpcd.
f Sanitary wastewater from non-program population identified in
Table 3-1, at 90 gpcd.
g Sum of Columns a through f
h Infiltration from existing sewer system. Increases to 10 gpcd
by 2020.
i Infiltration from new development. Increases to 10 gpcd by
2020.
j Sum of columns d and e.
k Total Wastewater = Sum of sanitary wastewater and infiltration
(Columns g and j)
Future Residential Contributions
Additional domestic wastewater will be contributed by two sources: 1)
existing development to be served by sewer extensions and 2) population
growth within the planning area. In both cases, the projected sanitary
flow rate (excluding infiltration and inflow) was determined by
multiplying the population values in Table 3-1 by 90 gpcd. The 90 gpcd
value falls between the estimated current rate 76 gpcd) and Ecology’s
recommended planning value (100 gpcd). It was considered to represent a
reasonable, if slightly conservative estimate of future conditions.
Future Commercial Contributions
Future commercial contributions were estimated by multiplying the
projected developed acreage in Table 3-2 by a unit flow rate of 1,000
gallons per acre per day (gpad), a typical planning value for mixed
commercial development.
Future Industrial Contributions
Future industrial flow contributions are projected to be generated by 1)
typical industrial development and 2) wet industries. Flow from typical
industrial development was estimated by multiplying the projected
developed acreage in Table 3-2 by 1,000 gpad. To project future flows
from wet industries, it was assumed that two industries would be
developed, each with a wastewater flow rate of 0.5 mgd. They would be
located in the North Valley and Spokane Valley service areas.
Extraneous Flows
As described earlier, it appears that current flow contributions from
infiltration and inflow (I/I) are quite low. In projecting future
conditions, it was assumed that aging of the collection system would
gradually allow a modest amount of extraneous flow to enter the system.
The estimated future infiltration rates were calculated as follows:
§
Base Flow. No infiltration contribution was
assumed for the Year 1999 Base Flow. In the future, the rate of
infiltration contribution was assumed to be 2 gpcd for Year 2000 flows
and to increase by 2 gpcd every 5 years, until 2020, at which point it
is held constant at 10 gpcd through 2050.
§
Existing Development to be to be Served by Sewer
Extensions. The rate of infiltration contribution was assumed to be
2 gpcd through 2005 and to increase by 2 gpcd every 5 years, until 2020,
at which point it is held constant at 10 gpcd through 2050.
§
Residential Growth. The infiltration projection
assumes 2 gpcd through 2005, increasing by 2 gpcd every 5 years until
2020, after which it is 10 gpcd of total infiltration. The rate of
infiltration is held constant at 10 gpcd through 2050, but increases in
proportion to population increases within the planning area between 2020
and 2050.
§
Industrial and Commercial Development. No
infiltration allowance was provided for these flow contributions,
assuming that overall system infiltration is adequately addressed
through the assumptions made for residential contributions.
Total Wastewater Flow
The total wastewater flow is equal to the sanitary wastewater input plus
infiltration. Inflow is not a significant component if the average
annual flow. For new residential connections, the total wastewater
quantity is equal to 90 gpcd of sanitary flow plus 10 gpcd of
infiltration, for a total amount of 100 gpcd. Infiltration is projected
to develop over a period of 20 years.
Development of annual average flow projections provides a baseline for
future planning; however, design of facilities and assessment of permit
compliance are typically based on more extreme flow events such as
maximum-month, maximum-day or peak instantaneous conditions. This
section describes the development of peak flow projections for the
Spokane County system.
Review of Interceptor Flow Records
To gain an understanding of flow variation in the Spokane system, a
review was conducted of flow meter records for the major interceptors.
Unfortunately, electronic data were available only for the Spokane
Valley Interceptor (SVI). This record provided flow data in five-minute
increments. For the North Valley Interceptor (NVI), hard copies of
continuous circular charts were available. For the North Spokane
Interceptor, the flow meter is located downstream of the main pumping
station serving this area, and reflects the on/off operation of the
constant speed pumps. Consequently, this flow record was not found
useful for evaluating the relationship between rainfall and wastewater
flow.
Determination of Peaking Factors for Dry-Weather, Non-Storm Conditions
The NVI and SVI information for the last three years was reviewed to
identify maximum month, maximum week, maximum day, and instantaneous
peak flow values. From the data, peaking factors for the different
conditions were calculated. The term “peaking factor” refers to the
ratio of the flow event observed to the average annual flow for the year
of record.
Peak events were compared with precipitation events, and the estimated
wastewater contribution due to precipitation was subtracted from the
flow. As a result, the calculated peaking factors were based on
dry-weather, non-storm conditions. A summary of the observed peaking
factors for the SVI data is presented in Table 3‑4. This table
also presents the values that were selected for use in projecting peak
flow events. These peaking factors are representative of peak flow
conditions at the downstream end of the service area. Higher peaking
factors can be expected upstream in the collection system, where the
contributing sewer basin is smaller and localized impacts to flow rates
are not dampened by a large base flow rate.
Table
3‑4.
Analysis of Dry Weather Non-Storm Peaking Factors for Spokane Valley
Interceptor
|
|
Average |
|
|
|
|
|
|
|
|
|
|
Daily |
Peaking Factor |
|
Year |
Summer |
Month |
Week |
Day |
Instantaneous |
|
|
Flow |
Winter |
Summer |
Winter |
Summer |
Winter |
Summer |
Winter |
Summer |
|
1997-98 |
1.0 |
N/A |
1.0 |
NA |
1.0 |
N/A |
1.1 |
1.7 |
1.9 |
|
1998-99 |
1.0 |
1.0 |
1.0 |
1.2 |
1.0 |
1.5 |
1.1 |
1.8 |
1.8 |
|
1999-001 |
1.0 |
1.1 |
N/A |
1.1 |
N/A |
1.2 |
N/A |
N/A |
N/A |
|
Representative Value |
1.1 |
|
1.2 |
|
1.5 |
|
|
1.9 |
Determination Infiltration and Inflow Contributions
The SVI and NVI data were reviewed
to determine whether any evidence of infiltration, interflow, or inflow
exists. As described earlier, annual contributions of I&I appear quite
low, as evidenced by the low per capita wastewater generation rate (80
gpcd) and the lack of seasonal variation in flow rates. This may be
attributed to the relatively new collection system infrastructure and
the fact that the most common source of prolonged infiltration – rising
groundwater due to precipitation or irrigation – is not present in the
Spokane County service area.
Continuous flow data following
precipitation events were reviewed to ascertain whether short-duration
interflow or inflow events occur. Precipitation events between late
spring and early fall were selected to eliminate snowfall events that
would not generate an immediate flow response (i.e., flow response would
not occur until snowmelt).
Moderate precipitation events did
not appear to stimulate increased wastewater flow. However, inflow
responses in the Spokane Valley data were observed for heavy summer
thunderstorms that occurred on June 18, 1998 and August 14, 1999.
During both events, a rainfall rate of 0.25 inches of rain in an hour
(measured at Geiger Field, approximately 10 miles from the flow
monitoring station) caused a short-term flow rate increase of about 0.9
million gallons per day. This response is shown in
Figure 3‑2 and Figure
3‑3. The response to precipitation was triggered only by
significant precipitation, and the response was nearly immediate. The
flow decreased as soon as precipitation ceased. No evidence of
interflow (rapid infiltration) was identified; consequently, the flow
contribution appears to be solely from inflow.
Using a standard runoff equation, a
runoff coefficient of 1, the storm intensity (0.25 inches per hour) and
the resulting instantaneous flow rate increase (0.9 mgd), the
approximate connected impervious surface was calculated (about 6
acres).
The short-duration inflow events
resulted in a relatively small volume of wastewater when viewed in terms
of the total wastewater generated during a one-week or one-month
period. However, inflow contributions are important when defining
maximum day and peak hour flow rates. To assess these impacts, the
results from the June 18, 1998 and August 14, 1999 storm events were
extrapolated to reflect 1-in-10-year storm events. The ten-year
recurrence is commonly used in guidelines for control of sanitary sewer
overflows, and was selected as an appropriate planning basis for
wastewater facilities. Department of Ecology guidelines do not
offer criteria for stormwater recurrence interval selection.
For the maximum-day contribution, a 24-hour storm intensity of 1.6
inches per day was used, whereas, a storm intensity of 0.5 inches per
hour was used for the peak hour event.

Figure 3‑2.
Spokane Valley Interceptor Flow, Summer
1998

Figure 3‑3.
Spokane Valley Interceptor Flow, Summer 1999
Summary of Peak Flow Projections
Table 3‑5 presents a summary of the estimated current and future
peak flows for the entire Spokane County service area. The methodology
used to calculate the values is presented in the table notes.
Table
3‑5.
Projected Peak Wastewater Flow
|
Year |
Average Sanitary Wastewater Flow, mgd |
Total Infiltration, mgd |
Average Wastewater Flow, mgd |
Maximum Month Average Flow, mgd |
Maximum Week Average Flow, mgd |
Apparent Impervious Surface Connected to Sanitary Sewer
System, acres |
Peak 24-hour, 10-year, Precipitation Intensity, inches per
hour |
Peak Daily Stormwater Inflow, mgd |
Maximum Day Average Flow, mgd |
Peak 1-hour, 10-year, Precipitation Intensity, inches per
hour |
Peak Hourly Stormwater Inflow, mgd |
Peak Instantaneous Flow, mgd |
Effective Instantaneous Peaking Factor |
|
1999 |
5.7 |
0.00 |
5.7 |
6.0 |
6.6 |
9.3 |
1.60 |
0.40 |
8.8 |
0.50 |
3.02 |
14.0 |
2.46 |
|
2000 |
6.4 |
0.11 |
6.5 |
6.9 |
7.6 |
10.2 |
1.60 |
0.44 |
10.0 |
0.50 |
3.33 |
15.8 |
2.46 |
|
2005 |
10.2 |
0.24 |
10.4 |
11.1 |
12.0 |
11.2 |
1.60 |
0.49 |
15.7 |
0.50 |
3.66 |
23.5 |
2.31 |
|
2010 |
14.1 |
0.41 |
14.5 |
15.4 |
16.8 |
12.4 |
1.60 |
0.54 |
21.7 |
0.50 |
4.02 |
31.6 |
2.24 |
|
2015 |
18.2 |
0.62 |
18.8 |
19.9 |
21.7 |
13.6 |
1.60 |
0.59 |
28.0 |
0.50 |
4.43 |
40.1 |
2.21 |
|
2020 |
19.7 |
0.86 |
20.6 |
21.8 |
23.7 |
14.9 |
1.60 |
0.65 |
30.6 |
0.50 |
4.87 |
43. |
2.22 |
|
2025 |
20.8 |
1.04 |
21.9 |
23.2 |
25.2 |
16.4 |
1.60 |
0.71 |
32.5 |
0.50 |
5.36 |
46.6 |
2.23 |
|
2030 |
21.8 |
1.13 |
23.0 |
24.3 |
26.4 |
18.1 |
1.60 |
0.79 |
34.1 |
0.50 |
5.89 |
49.1 |
2.25 |
|
2035 |
22.8 |
1.23 |
24.1 |
25.5 |
27.7 |
19.9 |
1.60 |
0.86 |
35.8 |
0.50 |
6.48 |
51.7 |
2.27 |
|
2040 |
23.8 |
1.33 |
25.2 |
26.6 |
28.9 |
21.9 |
1.60 |
0.95 |
37.4 |
0.50 |
7.13 |
54.4 |
2.28 |
|
2045 |
24.8 |
1.42 |
26.2 |
27.8 |
30.2 |
24.1 |
1.60 |
1.05 |
39.1 |
0.50 |
7.84 |
57.1 |
2.30 |
|
2050 |
25.8 |
1.52 |
27.3 |
28.9 |
31.4 |
26.5 |
1.60 |
1.15 |
40.7 |
0.50 |
8.63 |
59.9 |
2.32 |
|
Note: |
a |
b |
c |
d |
e |
f |
g |
h |
i |
j |
k |
l |
m |
Notes:
a Average sanitary flow from
Column g of Table
3-3.
b Infiltration from Column I of
Table
3-3.
c Average wastewater flow =
Average sanitary flow plus
infiltration
d Maximum month average flow =
(average sanitary flow x maximum month peaking factor) +
infiltration
e Maximum week average flow =
(average sanitary flow x maximum week peaking factor) +
infiltration
f Existing impervious surface
for the Spokane Valley Interceptor tributary area (5.8 acres) calculated
from storm
events of June 19, 1998 and
August 11, 1999. In both cases, one-quarter inch of rain increased peak
flow by 0.9
mgd. Calculations assume a
1.0 runoff coefficient. Existing impervious surface for SVI divided by
5/8 to
estimate impervious surfaces
for all three service areas. Impervious surface assumed to increase by
10 percent
every five
years
g From NOAA Precipitation Atlas
of the Western United
States
h Impervious surface x peak
hourly
precipitation
i Maximum day average flow =
(average sanitary flow x maximum day peaking factor) + infiltration +
peak daily
stormwater
inflow
j From Department of Commerce
Rainfall Frequency Atlas of the United
States
k Impervious surface x peak
hourly
precipitation
l Peak instantaneous flow =
(average sanitary flow x maximum instantaneous peaking factor) +
infiltration + peak
hourly stormwater
inflow
m Effective peaking factor
obtained by dividing peak instantaneous flow by average daily
flow
Wastewater strength and unit
wastewater loading rates may vary from one community to another because
of differences in the physical and economic environments. For this
reason, it is generally desirable to use historical sampling data from
the specific community as the basis for determining planning projections
for wastewater loadings. Only limited wastewater quality data exist for
the Spokane County system. City of Spokane data is only partially
representative of conditions in the County’s service area, because of
the differences in the collection system between the City and County.
To develop a reasonable projection of future wastewater loadings, an
assessment of County and City data was supplemented by a review of other
local wastewater utilities with generally similar service area
characteristics.
From the perspectives of treatment plant design and effluent quality
permit compliance, the primary constituents of interest are biochemical
oxygen demand, suspended solids, nitrogen, phosphorus and metals.
Biochemical Oxygen Demand
Biochemical oxygen demand refers to
the quantity of oxygen required by microorganisms to effect oxidation of
the organic matter present in wastewater to carbon dioxide and water.
Usually referred to as BOD, this characteristic defines the strength of
a wastewater in terms of its potential impact on dissolved oxygen levels
in a receiving stream. BOD strength often determines the type and
degree of treatment that must be provided to produce a required effluent
quality. BOD is traditionally expressed as the amount of oxygen
utilized when biological oxidation of organic matter is allowed to
proceed for 5 days at 20 degrees C (BOD5).
Suspended Solids
Suspended material transported in wastewater is referred to as suspended
solids. The quantity of suspended material removed during treatment
varies with the type and degree of treatment and has an important
bearing on the sizing of many mechanical and process units. The term
total suspended solids is often used to refer to the fact than solids
include both volatile (generally organic) and fixed portions.
Nitrogen
Nitrogen is of concern in treated wastewater since it can 1) increase
the oxygen demand in a stream, 2) act as a plant nutrient, stimulating
the growth of undesirable species, and 3) as unionized ammonia, it can
be toxic to fish. The term Total Kjeldahl Nitrogen represents the sum
of the organic nitrogen and ammonia present in the wastewater. It does
not include oxidized nitrogen, such as nitrates and nitrites. However,
since oxidized nitrogen is present in only minute quantities in raw
wastewater, Total Kjeldahl Nitrogen generally represents the entire
nitrogen concentration of an untreated wastewater. The term “Kjeldahl”
refers to the laboratory distillation process necessary to convert
organic nitrogen to measurable ammonia.
Total Phosphorus
Like nitrogen, phosphorus is a plant nutrient. It is usually present in
raw wastewater as orthophosphate (PO4), polyphosphate, and
organic particular forms.
Metals
Metals may exhibit aquatic toxicity at low concentrations, particularly
in receiving waters with low hardness levels. In the Spokane River,
current instream concentrations of some metals exceed water quality
criteria because of historical mining activities in the upper reaches of
the watershed.
BOD, Suspended Solids and Nutrient Data - Spokane County Interceptors
Useful water quality data for the County’s interceptor system is limited
to quarterly sampling conducted by the City along the North Valley and
Spokane Valley interceptors. Figure 3‑4 and Figure 3‑5
present the sampling results at each location for BOD, suspended solids
and total phosphorus. No data have been gathered on ammonia or total
nitrogen concentrations. Currently, the County is conducting more
extensive sampling to supplement this database.

Figure 3‑4.
North Valley Interceptor Wastewater Characteristics

Figure 3‑5.
Spokane Valley Interceptor Wastewater Characteristics
A summary of the quarterly monitoring results is presented in Table
3‑6. The data appear to show that the North Valley wastewater has
the greater concentration of total suspended solids and total
phosphorus, but the Spokane Valley wastewater has a higher concentration
of BOD. This observation may reflect the greater number of industrial
customers in the North Valley area.
Table
3‑6.
Interceptor Sampling, Summary of Quarterly Sampling 1996 to 1999
|
Interceptor |
Biochemical Oxygen Demand,
mg/L |
Total Suspended Solids,
mg/L |
Total Phosphorus, mg/L |
|
|
Ave. |
Max. |
Ave. |
Max. |
Ave. |
Max. |
|
Spokane Valley |
202 |
316 |
163 |
354 |
6.0 |
7.2 |
|
North Valley |
151 |
230 |
226 |
476 |
9.8 |
21.4 |
BOD, Suspended Solids and Nutrient Data – Other Local Communities
Since limited information on Spokane County wastewater quality is
available, information from surrounding communities was obtained to
characterize regional wastewater trends. Data were obtained from
Liberty Lake Water and Sewer District #1
[iii],
City of Cheney
[iv],
City of Spokane (which includes Spokane County contribution)
[v],
City of Coeur d’Alene
[vi],
City of Deer Park
[vii],
City of Post Falls
[viii],
and Hangman Valley (Spokane County Utilities)
[ix].
Information on regional wastewater characteristics is summarized in
Table 3‑7. To provide a point of reference for the regional data,
Table 3‑7 also presents literature values for per capita loading
rates and wastewater concentrations. These values are typically used if
local data are insufficient or considered unreliable.
Table
3‑7.
Wastewater Loading Summary for Nearby Communities
|
|
BOD |
Suspended Solids |
Total Nitrogen |
Total Phosphorus |
|
|
|
mg/l |
lb/day/
capita |
mg/l |
lb/day/
capita |
mg/l |
lb/day/
capita |
mg/l |
lb/day/
capita |
|
|
Community |
Note |
|
|
|
|
|
|
|
|
|
|
|
|
Liberty Lake Water and Sewer District #1 |
270 |
0.180 |
286 |
0.191 |
N/A |
N/A |
5.9 |
0.0040 |
b |
|
City of Cheney |
200 |
0.135 |
150 |
0.101 |
N/A |
N/A |
N/A |
N/A |
c |
|
City of Spokane |
165 |
0.230 |
165 |
0.230 |
32 |
0.044 |
5 |
0.0070 |
d |
|
City Coeur d'Alene |
249 |
0.147 |
203 |
0.120 |
N/A |
N/A |
6.85 |
0.0040 |
e |
|
City of Deer Park |
164 |
0.122 |
282 |
0.209 |
N/A |
N/A |
N/A |
N/A |
f |
|
City of Post Falls |
195 |
0.155 |
245 |
0.194 |
N/A |
N/A |
6.9 |
0.0056 |
g |
|
Spokane Co. - Hangman Valley STP |
225 |
N/A |
178 |
N/A |
N/A |
N/A |
N/A |
N/A |
h |
|
Spokane Co. - Spokane Valley Interceptor |
202 |
0.127 |
163 |
0.103 |
N/A |
N/A |
5.95 |
0.0038 |
i |
|
|
|
|
|
|
|
|
|
|
|
|
Average |
209 |
|