Monroe Street Preservation & Improvements

Project No: CRP 3196
Project Design Engineer:  Tim Schwab, P.E.
Stormwater Design Engineer:  Jake Saxon, E.I.T.
Project Start:  Spring/Summer 2017

Project Description:  This project will grind and inlay 2" of HMA for the existing pavement.  There will be traffic signal improvements, upgrades and pedestrian countdown improvements that will require modifications at the Wall/Monroe intersection.  ADA ramps improvements will be constructed.  Stormwater improvements will include catch basins and piping to convey stormwater to new bio-infiltration swales for stormwater treatment and disposal.

Public Involvement


Monroe/Wall St Project Open House
Thursday, December 8, 2016
5:30pm - 7:30pm |  St. David's Episcopal Church
7315 N Wall St | Spokane, WA  99208
Open House Postcard

Open House Displays
Construction Funding
Monroe-Wall Intersection
Road Project Overview
Stormwater Project - Detail 1
Stormwater Project - Detail 2
Stormwater Projects Overview
Typical Road Section